A new list of water and wastewater projects has been approved under the Canada-Ontario Clean Water and Wastewater Fund (CWWF) agreement, which is designed to improve the safety and quality of water for Canadian families, while supporting a clean economy.
The Government of Canada is providing Ontario with more than $569 million under CWWF, and will fund up to 50 percent of the eligible project costs. The provincial government is providing up to 25 percent of total eligible project costs, and the municipalities will provide the balance of funding.
As part of the bilateral agreement with Ontario, the following 18 projects across Ontario have been approved for federal funding amounting to over $6.1 million in total eligible costs. Additional projects in these and other Ontario municipalities will be identified in the coming weeks.
Location |
Project Name |
Federal Funding |
Provincial Funding |
Anticipated Start Date |
Fort Erie, Town of |
Dufferin Street Sanitary Sewer - Replacement of vitrified clay pipe |
$ 275,000 |
$137,500 |
April 30, 2017 |
Fort Erie, Town of |
Murray Street Water - Replacement of cast-iron watermain |
$163,600 |
$81,800 |
April 30, 2017 |
Fort Erie, Town of |
Murray Street Sanitary Sewer - Replacement of vitrified clay pipe |
$421,400 |
$210,700 |
April 30, 2017 |
Fort Erie, Town of |
Battery Street Water - Replacement of cast-iron watermain |
$86,250 |
$43,125 |
April 30, 2017 |
Fort Erie, Town of |
Battery Street Sanitary Sewer - Replacement of vitrified clay pipe |
$201,250 |
$100,625 |
April 30, 2017 |
Niagara, Region of |
Treated water booster pumping station upgrade (electrical & mechanical) - Kent Avenue Reservoir and Booster Pumping Station - located in the City of Niagara Falls |
$366,667 |
$183,333 |
March 6, 2017 |
Niagara, Region of |
DeCew Falls Water Treatment Plant - Spillway Reconstruction - located in the City of St. Catharines |
$173,333 |
$86,667 |
March 6, 2017 |
Niagara, Region of |
Old Orchard Pump Station Upgrade (forcemain / valve & bypass chamber / pumps / piping / security / electrical / instruments) - located in the Town of Grimsby |
$566,667 |
$283,333 |
February 24, 2017 |
Niagara, Region of |
Stamford Interceptor Renewal - Phase I (sewer lining & maintenance holds)- located in the City of Niagara Falls |
$1,493,333 |
$746,667 |
April 14, 2017 |
Niagara, Region of |
Oakes Park Trunk Sewer Relining & Maintenance Hole rehabilitation - located in the Town of Fort Erie |
$520,000 |
$260,000 |
May 26, 2017 |
Niagara, Region of |
Niagara Falls Waste Water Treatment Plant Flocculation, Grit and Primary Tank Gate Upgrade - located in the City of Niagara Falls |
$195,333 |
$97,667 |
April 3, 2017 |
Niagara, Region of |
Seaway Secondary Clarifier Upgrade (Clarifier Gearbox assemblies/scraper arms/drive motor & electrical) - located in the City of Port Colborne |
$303,333 |
$151,667 |
April 3, 2017 |
Niagara, Region of |
DeCew Falls Water Treatment Plant - Distribution feed upgrade (150 mm diameter Polyvinyl Chloride (PVC) watermain 400 meters long) - located in the City of St. Catharines |
$216,667 |
$108,333 |
April 3, 2017 |
Niagara-on-the-Lake, Town of |
Line 3 Road asbestos clay watermain upgrade |
$195,762 |
$97,881 |
April 1, 2017 |
Niagara-on-the-Lake, Town of |
King Street cast iron watermain upgrade |
$454,858 |
$227,429 |
April 1, 2017 |
Niagara-on-the-Lake, Town of |
Simcoe Street cast iron watermain upgrade |
$161,216 |
$80,608 |
April 1, 2017 |
Niagara-on-the-Lake, Town of |
Centre Street cast iron watermain upgrade |
$86,366 |
$43,183 |
April 1, 2017 |
Niagara-on-the-Lake, Town of |
Niagara on the Lake Commons cast iron watermain upgrade |
$305,158 |
$152,579 |
April 1, 2017 |