Rayrock Remediation Project

Fairness monitor final report: November 9, 2022

Addendum to final report: November 29, 2022

Submitted to: Director, Fairness Monitoring Program

Submitted by: Raymond Chabot Grant Thornton Consulting Inc.

On this page

Attestation of assurance

The fairness monitor (FM) hereby provides the unqualified assurance statement below concerning the Rayrock Remediation project request for proposal (RFP) phase.

It is our professional opinion that the procurement process that we observed or monitored was carried out in a fair, open, and transparent manner.

Original signed by:

Marco Perron
Fairness monitoring contractor’s representative
President and Chief Executive Officer
Chartered Professional Accountant
Chartered Accountant
Certification in Risk Management Assurance

Jacques Lamothe
Chartered Professional Accountant
Certified General Accountant
Certified Internal Auditor
Master of Business Administration
Fairness Monitor Specialist

Project requirement

Raymond Chabot Grant Thornton Consulting Inc. (RCGT) was engaged on July 16, 2021 as a FM to observe the Rayrock Remediation Project procurement process, issued by Public Works and Government Services Canada on behalf of Crown-Indigenous Relations and Northern Affairs Canada under bid solicitations EW669-220778/A, EW669-220778/B and EW699-220778/C. RCGT is an independent third party with respect to this activity.

This report covers the activities of the FM during the RFP phase, from July 16, 2021 continuing through to the conclusion of the evaluation phase on October 20, 2022.

The Rayrock Remediation project involves the environmental remediation of historical mining and exploration sites including:

All Rayrock Remediation project sites are within the boundaries of the Tlicho Comprehensive Land Claim Agreement. Rayrock and Sun Rose are on Federal (Crown) lands within defined exclusion zones, while all other sites are on Tlicho Lands.

The Rayrock Remediation Project will involve numerous tasks, some of which are of lower complexity (debris pick-up and stockpiling) through to those of higher complexity (water treatment, sediment removal and cell construction). It is anticipated that the project will require up to 3 construction seasons, with initial mobilization occurring in winter 2022, and remediation work occurring in the summers of 2023, 2024, and 2025, depending how the work is sequenced. A typical construction season for these locations starts in May and concludes by late October, which allows approximately 180 days. However, some work activities, including winter road construction, are anticipated during the winter months.

We reviewed all of the information provided and observed all relevant activities.

This report includes:

Fairness monitoring engagement and observations

In accordance with the terms of our engagement, we:

Request for proposal phase

The following activities were performed by the FM during this phase:

The RFP closed on November 16, 2021, at 14:00 Mountain Standard Time (MST).

Two submissions were received to this RFP. Both submissions were deemed to be technically non-compliant.

A decision was subsequently made to re-issue a limited retender to the 2 non-compliant bidders. Some limited changes were made to the requirements, and a second RFP was issued.

Second request for proposal phase

A limited retender RFP EW699-220778/C was issued on August 9, 2022 for the Rayrock Remediation project.

The following activities were performed by the FM during this phase:

The second RFP closed on September 20, 2022 at 14:00 MST. One submission was received to the limited retender RFP.

Bid evaluation phase

The following activities were performed by the FM during this phase:

The evaluators performed an individual evaluation of the submission first and then consensus meetings were conducted to come to a consensus score for the technical criteria. The meeting was mediated by the technical authority with support from the CA.

Using the evaluation criteria, it was determined that the sole bidder was compliant with the requirements.

Reference documents

The documents related to solicitation EW699-220778/A; EW699-220778/B and EW699-220778/C are available on CanadaBuys or through the project office.

Addendum to the final report

November 29, 2022

Addendum to the final report dated November 9, 2022 for the Rayrock Remediation project procurement process.

This addendum covers the period following the conclusion of the evaluation phase including contract award and debriefings.

The FM reviewed all the information provided and observed or monitored all relevant activities of the contract award and debriefing activity, as identified in this report. We hereby submit the addendum to the final report, which is based on information made available to us by the CA from October 25 to November 29, 2022.

The following activities were performed or monitored by the FM during this phase:

No debriefings were held.

RCGT reserves the right, but will be under no obligation, to review and/or revise the report if further information that may impact our observations becomes known to us after the date of this report.

Attestation of assurance

The FM hereby provides the unqualified assurance statement below concerning the contract award and debriefing activities for the Rayrock Remediation Project.

It is our professional opinion that the contract award and debriefing activities that we observed or monitored was carried out in a fair, open and transparent manner.

Original signed by:

Marco Perron
Fairness monitoring contractor’s representative
President and Chief Executive Officer
Chartered Professional Accountant
Chartered Accountant
Certification in Risk Management Assurance

Jacques Lamothe
Chartered Professional Accountant
Certified General Accountant
Certified Internal Auditor
Master of Business Administration
Fairness Monitor Specialist

Page details

Date modified: