Quebec Small Craft Harbours – Temporary Measures at the Grande-Entrée harbour
Backgrounder
Temporary measures that will be put in place following the fire at the Grande-Entrée harbour in the Magdalen Islands on June 30, 2024.
These measures will be completed for the opening of the fishery in the spring of 2025.
Further details on the nature and cost of each measure will be available as the respective tendering processes are completed.
Development of a new line of floating pontoons (Manufacture of pontoons, footbridges, anchor blocks, push arms and lamppost bases) |
---|
Call for tenders: November 2024* |
Completion and completion of the work: March 2025* |
Reinforcement of the existing riprap |
Environmental Approval: Fall 2024* |
Call for tenders: December 2024* |
Completion and completion of the work: April 2025* |
Dredging of the new location |
Environmental Approval: Fall 2024* |
Call for tenders: December 2024* |
Completion and completion of the work: April 2025* |
*Dates announced may be subject to change without notice.