2018-2019 Annual Summary of Inspection Activities

On-site Inspections

On-site inspections are conducted at the place where the designated project is being carried out; or where a record or anything relating to the designated project is located, such as the office or other premises of the proponent or of a third party.

On-site Inspections

Project name

Number of On-site Inspections

Date of Inspections

Howse Property Iron Mine Project

1

August 14 to 15, 2018

Kemess Underground Project

1

July 11 to 12, 2018

LNG Canada Export Terminal Project

1

October 2 to 3, 2018

Rainy River Project

2

November 7, 2018
June 5 to 6, 2018

Site C Clean Energy Project

4

October 30 to November 2, 2018
July 14 to 15, 2018
April 30 to May 1, 2018
April 9 to 12, 2018

Whabouchi Mining Project

1

September 12 to 14, 2018

Woodfibre LNG Project

1

September 25, 2018

Total

11

 

Off-site Inspections

Off-site inspections are conducted in the office of the designated person under the Canadian Environmental Assessment Act, 2012 and can include reviewing reports submitted by a proponent.

Off-site Inspections

Project name

Number of Off-site Inspections

Date of Inspections

Akasaba West Copper-Gold Mine Project

9

February 22, 2019
November 22, 2018
November 12, 2018 (2)
November 6, 2018
November 5, 2018
October 19, 2018
September 10, 2018
August 27, 2018

Black Point Quarry Project

2

June 20, 2018
June 18, 2018

Brucejack Gold Mine Project

3

May 25, 2018
April 11, 2018
April 4, 2018

Howse Property Iron Mine Project

1

October 26, 2018

Kemess Underground Project

10

December 5, 2018
June 19, 2018
May 16, 2018
April 30, 2018
April 18, 2018 (2)
April 9, 2018 (4)

LNG Canada Export Terminal Project

8

December 20, 2018
October 5, 2018
July 13, 2018
July 4, 2018 (2)
June 29, 2018
June 28, 2018 (2)

Port of Quebec Deep-Water Wharf Project - Beauport Sector

1

July 3, 2018

Rainy River Project

24

March 12, 2019 (2)
February 27, 2019
February 26, 2019
January 29, 2019
December 21, 2018
November 27, 2018
November 22, 2018
October 1, 2018
September 27, 2018
September 15, 2018
September 13, 2018
August 31, 2018
August 27, 2018
August 25, 2018
August 20, 2018
July 20, 2018
June 9, 2018
June 6, 2018 (2)
May 25, 2018
May 3, 2018
April 8, 2018
April 6, 2018

Scotian Basin Exploration Drilling Project

2

November 13, 2018
June 22, 2018

Site C Clean Energy Project

1

November 19, 2018

Whabouchi Mining Project

4

October 31, 2018
July 6, 2018
June 21, 2018
April 3, 2018

Total

65

 