January 7, 2014 – Ottawa, ON – Office of the Minister of the Environment
The Honourable Leona Aglukkaq, Minister of the Environment and Minister responsible for the Canadian Environmental Assessment Agency, today announced the referral of the proposed Roberts Bank Terminal 2 Project in British Columbia for an environmental assessment by an independent review panel.
The decision to refer the project was made after considering its potential for significant adverse environmental effects and concerns expressed by the public and Aboriginal groups in relation to these effects.
The Minister has set timelines for the environmental assessment of the Roberts Bank Terminal 2 Project as follows:
- The timeline for the review panel to be established (pre-panel phase) is 150 days (5 months) from the date of referral of the project up to the establishment of the review panel.
- The timeline for the review panel to submit its report (panel phase) is 430 days (14 months) from the date of establishment of the review panel.
- The timeline for the federal Minister's decision statement (post-panel phase) is 150 days (5 months) from the date of submission of the review panel's report.
The above timelines do not include the time the proponent, Port Metro Vancouver, takes to gather information required for the environmental assessment.
Jennifer Kennedy
Director of Communications
Office of the Minister of the Environment
Telephone: 819-997-1441
Lucille Jamault
Communications
Canadian Environmental Assessment Agency
Telephone: 613-957-0434
Lucille.Jamault@ceaa-acee.gc.ca