Backgrounder: Improving local roads and bridges in Saskatchewan's rural municipalities

Backgrounder

Federal Gas Tax Fund allocated towards 309 projects in 2016

The federal Gas Tax Fund (GTF) provides Canadian municipalities with a permanent, predictable and indexed source of long-term funding. The Government of Canada will provide Saskatchewan with more than $59.1 million for community infrastructure through the federal GTF in 2016-17.

Based on project planning in 2016, federal GTF funding supported the following local roads and bridges projects in Saskatchewan's rural municipalities:

Rural Municipality Project Name Estimated
Total Cost
Federal GTF Allocated to Project

Antelope Park No. 322

Reconstruct 4.8 km of Hjalte Road West

$499,664

$62,596

Argyle No. 1

Reconstruct 3.2 km of 5 Mile Road

$200,000

$79,758

Arlington No. 79

Reconstruct 9.7 km of Grid 613

$789,483

$113,417

Arm River No. 252

Reconstruct 8 km of Girvin Grid

$1,215,167

$73,555

Auvergne No. 76

Clay Cap 3.2 km of Grid #628

$160,930

$20,725

Auvergne No. 76

Pave Two Bridge Decks

$30,000

$30,000

Auvergne No. 76

Replace Bridge with Two Culverts

$163,328

$80,000

Baildon No. 131

Replace Skyline Bridge

$620,000

$81,390

Baildon No. 131

Replace Old Guard Bridge

$622,373

$94,078

Barrier Valley No. 397

Clay Cap 4.0 km of Road

$80,920

$80,920

Barrier Valley No. 397

Clay Cap 3.2  km of Algrove Lake Curve

$50,000

$40,000

Battle River No. 438

Repave 9.6 km of Old Highway 4

$297,393

$297,393

Bayne No. 371

Project 301/303 Road Reconstruction

$710,680

$169,916

Bengough No. 40

Upgrade Access Road

$9,296

$9,296

Bengough No. 40

Rebuild 1.6 km of Class 5 Torkelson Grid Road

$35,000

$35,000

Benson No. 35

Reconstruct 29 km of Viewfield Grid

$411,000

$144,746

Big Arm No. 251

Replace Code Bridge

$550,000

$59,080

Big Quill No. 308

Rebuild 3.2 km of Gillis Road

$265,000

$150,000

Big Quill No. 308

Clay Cap and Rebuild Grade on Tower Road

$65,000

$23,400

Big Stick No. 141

Reconstruct Grid Road

$273,776

$43,719

Biggar No. 347

Construct a Highway Turning Lane

$50,000

$50,000

Birch Hills No. 460

Upgrade Bridge - Id 226-46A-06 E

$25,000

$25,000

Birch Hills No. 460

Replace Bridge with Culverts

$100,000

$100,000

Bjorkdale No. 426

Replace Two Bridges with New Culverts

$200,000

$50,000

Blaine Lake No. 434

Radnga Creek Upgrade

$204,712

$124,712

Bratt's Lake No. 129

Bridge Replacement with Large Dimension Culverts

$120,000

$120,000

Britannia No. 502

Pavement Overlay 13.2 km of 4 Mile Road and Dump Road

$2,401,750

$174,783

Brock No. 64

Clay Cap Range Road 2052

$800,000

$70,305

Brokenshell No. 68

Replace 3 Bridges with Culverts

$331,018

$90,983

Buchanan No. 304

Bridge Upgrades

$70,000

$50,000

Buckland No. 491

Paddockwood Bridge Replacement

$500,000

$500,000

Cambria No. 6

Upgrade Grid 606

$390,000

$89,802

Cana No. 214

Install Four Culverts 2-2014

$2,909

$2,909

Cana No. 214

Install Two Culverts 5-2014

$2,599

$2,599

Cana No. 214

Install Culvert 6-2014

$1,030

$1,030

Cana No. 214

Install Four Culverts 1-2014

$17,338

$17,338

Cana No. 214

Install Two Culverts 3-2014

$2,480

$2,480

Cana No. 214

Reconstruct 0.8 km of Road

$50,000

$50,000

Cana No. 214

Install Three Culverts in Division Two

$3,350

$3,350

Cana No. 214

Reconstruct 0.8 km of Kennel Road

$41,000

$41,000

Cana No. 214

Replace Culvert at Kaposvar Dam

$19,500

$19,500

Cana No. 214

Install Culvert on Brewer Road

$3,200

$3,200

Cana No. 214

Install Four Culverts in Division Five

$4,550

$4,550

Cana No. 214

Install 10 Culverts in Division Six

$11,900

$11,900

Canaan No. 225

Upgrade 2.2 km of Covill Hill Road

$225,551

$44,015

Canwood No. 494

Revitalize 3.2 km Gravel Road

$75,000

$75,000

Caron No. 162

Replace Bridge with Two 2400 mm Culverts

$154,125

$107,888

Chaplin No. 164

Clay Cap 3.2 km of Range Road 3050

$50,000

$33,931

Chaplin No. 164

Reconstruct 0.4 km of Range Road 3053

$15,500

$15,500

Chester No. 125

Reconstruct 8 km of CTP Road

$1,050,000

$110,184

Colonsay No. 342

Upgrade CWB Terminal Road

$86,354

$70,896

Connaught No. 457

Upgrade Three Bridges and Replace One Culvert

$1,000,000

$225,942

Cote No. 271

Clay Capping 0.8 km of Road

$80,000

$44,107

Cote No. 271

Install Culvert in Division 4 (by Runnymede)

$17,500

$17,500

Cote No. 271

Install Culvert in Division 5

$12,000

$12,000

Cote No. 271

Replace Bridge at Division 6 2015

$260,000

$138,388

Coteau No. 255

Replace Pavement on 4.0 km of Road

$25,000

$23,856

Coteau No. 255

Rebuild Flood Damaged Roads

$449,714

$66,664

Coulee No. 136

Replace Two Bridges and Culvert with Six Culverts

$450,000

$182,191

Cupar No. 218

Clay Cap 3.2 km Hospital Road

$62,000

$62,000

Cymri No. 36

Pave 6.85 km of Grid No. 702

$3,222,912

$154,790

District of Lakeland No. 521

Lakeshore Drive - Carwin Park Redesign

$291,000

$152,197

Duck Lake No. 463

Lake Road Project

$6,500

$6,500

Duck Lake No. 463

Lily Plain Road Upgrade

$145,000

$118,592

Dufferin No. 190

1.6 km of Grid Road 642 CTP Improvement

$203,000

$101,500

Eagle Creek No. 376

Replace Culvert SK-784

$50,000

$50,000

Edenwold No. 158

Enhance Emerald Park Walkways

$440,586

$440,586

Eldon No. 471

Repave 12.8 km of Grid 684

$5,539,646

$221,845

Elfros No. 307

Road Recap

$90,000

$43,359

Emerald No. 277

Reconstruct and Recap 1.6 km of Suttil Road

$325,535

$66,022

Enfield No. 194

Old Ducks Unlimited Project Culvert Replacement

$46,000

$38,989

Enfield No. 194

Reconstruct 2 km of Boot Hill Road

$100,000

$79,758

Enniskillen No. 3

Incorporation of Gravelock

$522,000

$105,2260

Enterprise No. 142

Reconstruct 12 km of Truck Route and Richmound Grid Roads

$186,750

$41,356

Estevan No. 5

Reconstruct 3.2 km of Primary Grid #703

$483,000

$336,461

Eye Hill No. 382

Denzil Grid Reconstruction

$5,337,600

$291,025

Fertile Valley No. 285

Reconstruct 1.6 km of Road E 31-29-8 W3

$174,039

$30,456

Fertile Valley No. 285

Reconstruct 0.5 km of Road ESE 35-28-09 W3

$210,470

$58,050

Flett's Springs No. 429

Reconstruct 8.0 km of Road

$220,000

$220,000

Flett's Springs No. 429

Replace Bridges with Culverts

$165,000

$165,000

Foam Lake No. 276

Replace Cement Bridge with Four Culverts

$623,820

$162,140

Fox Valley No. 171

Pave Street

$16,475

$16,475

Francis No. 127

Replace Bridge

$190,000

$190,000

Frenchman Butte No. 501

Reconstruct 3 km of Oil Road

$1,400,000

$424,785

Garden River No. 490

Replace Bridge with 2 Span Wood Bridge (Weirdale Grid)

$173,000

$44,750

Garry No. 245

Reconstruct 1.6 km of road

$30,000

$30,000

Garry No. 245

Replace Two Culverts and Raise Grade

$50,000

$50,000

Glen Mcpherson No. 46

Replace Three Culverts and Culvert Extension

$63,339

$28,360

Glenside No. 377

Reconstruct 3.2 km of Road

$15,000

$15,000

Golden West No. 95

Reconstruct 5.6 km of Road

$677,327

$103,538

Grandview No. 349

Upgrade Skog Road

$9,713

$9,713

Grant No. 372

Clay Cap 9.6 km Smuts Grid 767

$425,000

$125,545

Grass Lake No. 381

Reconstruction of Salvador Grid Road

$1,950,000

$109,003

Grassy Creek No. 78

Resurface 1.6 km of 722 Road

$185,000

$83,894

Gravelbourg No. 104

Reconstruct 2 km of Grid Road 718

$55,782

$55,782

Gravelbourg No. 104

Neubekker Bridge Resurfacing

$36,000

$34,610

Grayson No. 184

Reconstruct 4.8 km of Road

$195,000

$141,201

Great Bend No. 405

Construct Low-Level Crossing

$45,000

$45,000

Griffin No. 66

Install Culvert at NE 34-7-10-W2

$1,500

$1,500

Gull Lake No. 139

Pave 4.49 km Green Terminal Road

$3,500,000

$59,375

Happy Valley No. 10

Short Line Railway Funding

$750,000

$108,497

Happyland No. 231

Reconstruct 6.4 km of Road

$1,000,000

$83,893

Harris No. 316

Upgrade Clayton Bridge

$130,000

$12,723

Hart Butte No. 11

Rebuild 4.82 km of Road

$736,265

$77,986

Hazelwood No. 94

Reconstruct 4.8 km of Road

$300,000

$72,668

Hillsborough No. 132

Culvert Installation and Grid Road Reconstruction

$10,285

$9,361

Hillsborough No. 132

Install Culvert on Road and Replace Smaller Culverts

$16,130

$15,836

Hillsborough No. 132

Replace Small Culverts with Large Culverts

$12,996

$12,776

Hoodoo No. 401

Repave 3.2 km of Grid 777

$200,000

$104,276

Hoodoo No. 401

Replace Wakaw Lake Culvert on Bonne Madonne Grid

$104,276

$104,276

Hudson Bay No. 394

Municipal Culvert Installation Division 2

$90,900

$90,900

Hudson Bay No. 394

Municipal Culvert Installation Divisions 3 and 4

$28,000

$28,000

Hudson Bay No. 394

Municipal Culvert Installation Division 5

$45,500

$45,500

Hudson Bay No. 394

Municipal Culvert Installation Division 6

$35,650

$35,650

Humboldt No. 370

Reconstruct 2.5 km of Road

$479,784

$340,807

Huron No. 223

Reconstruct 1.6 km of Road

$223,571

$107,974

Indian Head No. 156

Rebuild 7.8 km of Grid 619

$792,229

$112,252

Insinger No. 275

Construction of 8.1 km of CTP Road

$1,276,998

$96,005

Invermay No. 305

Clay Capping Chain of Lakes Mile-Grid 617

$60,245

$51,381

Kellross No. 247

Clay Cap NW-20-25-14-W2 Grid Road

$11,800

$11,800

Kellross No. 247

Clay Cap 4.8 km of 639 South

$300,000

$108,321

Kelvington No. 366

Replace DesRoches Bridge with Culverts

$75,000

$75,000

Kelvington No. 366

Replace Mitton Bridge with Culverts

$75,000

$72,405

Key West No. 70

Road Re-construction

$150,000

$112,856

Keys No. 303

Upgrade ENE 21-31-2- W2 Bridge

$1,051,725

$123,182

King George No. 256

Reconstruct 2 km of Gravel Pit Road

$30,065

$30,065

Kingsley No. 124

Clay Cap 4.9 km of Grid 605 South

$277,463

$124,363

Kinistino No. 459

Upgrade Bridge at E 17-47-21-W2

$735,000

$130,000

Lac Pelletier No. 107

Lac Pelletier Trail Reconstruction

$30,000

$30,000

Lacadena No. 228

Dryland Road Relocation

$74,857

$74,857

Laird No. 404

Upgrade and Clay Cap 1.6 km Carmen Grid

$84,801

$84,801

Lajord No. 128

Construction, Clay Cap & Gravel 3.2 km of Road

$103,175

$87,425

Lake Johnston No. 102

Reconstruct 2.5 km of Mitchellton Road

$82,000

$48,435

Lake Lenore No. 399

Road Rehabilitation

$45,000

$45,000

Lake Lenore No. 399

Replace Bridge with Culverts

$60,000

$60,000

Lake Of The Rivers No. 72

Reconstruct 1.6 km of Road RR2293

$50,000

$50,000

Lake Of The Rivers No. 72

Reconstruct 6.44 km of Road RR2291 to RR2283

$60,000

$39,211

Lakeside No. 338

Reconstruct 11.2 km of Quill Plains Grid

$193,380

$114,320

Lakeview No. 337

Clay Cap .9 km of Hendon Grid

$125,510

$62,755

Last Mountain Valley No. 250

Rebuild 1.6 km and Clay Cap 3.2 km of Road

$210,625

$98,793

Lawtonia No. 135

Clay Cap 3.2 km of Flowing Well Road

$308,000

$128,204

Leroy No. 339

Replace Bridge with Culverts over Lanigan Creek

$309,430

$65,484

Lipton No. 217

Reconstruct 11.2 km of Strasbourg Grid

$861,000

$231,493

Livingston No. 331

Bridge Installation

$170,000

$67,647

Livingston No. 331

Rebuild 1.6 km of Fort Livingston Road

$40,000

$40,000

Lomond No. 37

Replace Bridge Over Long Creek

$975,000

$89,802

Lone Tree No. 18

Upgrade 10 km of Road

$110,000

$106,871

Longlaketon No. 219

Pavement Reversion to Gravel

$465,000

$413,068

Loon Lake No. 561

Replace Old Bridge with a New Bridge on Range Road 3211

$181,650

$106,000

Loon Lake No. 561

Replace Cement Culvert with Box Culvert on Range Road 3202

$27,175

$25,884

Loon Lake No. 561

Replace Culvert at Low Level Crossing

$72,788

$69,365

Loon Lake No. 561

Replace Culvert on Range Road 3200

$28,423

$12,916

Lost River No. 313

Cygnet Lake Road Clay Capping

$71,000

$35,356

Lost River No. 313

Upgrade Roads with Rip Rap

$123,739

$61,739

Manitou Lake No. 442

Rebuild and Widen 6.4 km of Road 454

$195,000

$62,139

Mankota No. 45

Clay Cap 4 km of Summercove Road

$190,000

$132,773

Maple Bush No. 224

Replace 3 Culverts-Main Farm Access TWP RD 224

$50,000

$49,332

Maple Creek No. 111

Upgrade 7.2 km of Galloway Road

$450,000

$357,308

Marquis No. 191

Bridge Replacement

$491,500

$199,177

Marriott No. 317

Replace Cleland Dam Culvert

$15,608

$15,608

Maryfield No. 91

Thunder Road Bridge Replacement

$120,000

$94,233

McCraney No. 282

Road Reconstruction

$145,000

$97,331

Meadow Lake No. 588

Replace 317-60-19N Bridge with a New Bridge

$175,427

$175,427

Medstead No. 497

Clay Capping Roads

$327,000

$29,138

Meeting Lake No. 466

Replace Four Culverts

$20,000

$20,000

Meota No. 468

Rebuild and Resurface Birch Road

$259,600

$259,600

Milton No. 292

Reconstruct 4.02 km Marengo West Road

$403,433

$92,165

Monet No. 257

Upgrade Road Beds

$149,694

$139,729

Montrose No. 315

Chip Seal 5.6 km of O'Malley Road

$140,000

$140,000

Moose Creek No. 33

Clay Cap 6.7 km of Dam Road

$683,125

$109,889

Moose Mountain No. 63

Clay Cap 4.8 km of Road

$220,000

$141,792

Moose Range No. 486

Replace Classen/Thesen Bridge with Culverts

$50,000

$40,000

Moose Range No. 486

Construct Forbes/Wlaz Low Level Crossing

$60,000

$50,000

Moose Range No. 486

Upgrade Schmitt Bridge

$80,000

$30,000

Moose Range No. 486

Replace Stacey (East) Bridge With Two Culverts

$130,000

$36,150

Moose Range No. 486

Replace Stagman (East) Culvert with Two Culverts

$100,000

$100,000

Moose Range No. 486

Upgrade Codette Grid Bridge

$80,000

$30,000

Moosomin No. 121

Reconstruct and Pave 3.2 km of Road

$645,838

$148,882

Morris No. 312

Clay Cap 6.5 km of 205/206 Road

$485,000

$92,346

Morse No. 165

Clay Cap 8.4 km of Road 612

$635,000

$118,455

Mountain View No. 318

Reconstruct 0.8 km of Valley Centre Road

$55,852

$49,184

Mountain View No. 318

Reconstruct 0.8 km of Winona Road

$53,775

$49,184

North Qu'Appelle No. 187

Resurface 3.2 km of Road with Asphalt

$113,000

$93,000

Norton No. 69

Replace Bridge with 2 Culverts

$53,035

$53,035

Oakdale No. 320

Upgrade 13.05 km of Hopedale Road

$4,453,075

$76,213

Orkney No. 244

Replace Springside Bridge with Three Culverts

$593,000

$426,255

Paddockwood No. 520

Hanson Hill Heavy Haul Road Upgrade

$721,000

$191,989

Paynton No. 470

Upgrade 1.5 km of Grid 674

$105,672

$46,418

Pense No. 160

Clay Cap 3.2 km of TWP 174 Road

$220,000

$139,133

Perdue No. 346

Reconstruct Road-E of SE 22-10-36 W3

$38,650

$38,650

Perdue No. 346

Reconstruct Road-S of SE 04-34-10 W3

$39,825

$39,825

Piapot No. 110

Rebuild and Widen 4.8 km of Kealey Springs Road

$225,000

$114,717

Pinto Creek No. 75

Upgrade Bridge at E22-08-08 W3M

$30,000

$30,000

Pittville No. 169

Reconstruction of Verlo Hill Road

$254,934

$67,984

Pittville No. 169

Upgrade 3.2 km of Class 4 Road

$329,709

$60,262

Pleasant Valley No. 288

Upgrade 3.2 km of Wilson Road

$130,000

$101,913

Pleasantdale No. 398

3L South-Upgrade

$95,000

$75,000

Pleasantdale No. 398

Thompson North

$90,000

$30,000

Pleasantdale No. 398

Hardy Pit Road South

$120,000

$30,000

Ponass Lake No. 367

Fosston Grid Construction

$291,245

$155,676

Poplar Valley No. 12

Purchase Rail Line

$750,000

$154,941

Porcupine No. 395

Replace Grisdale and Zubrowski Bridges

$1,268,265

$242,228

Prairie Rose No. 309

Reconstruct 5.3 km of Esk South Road

$1,158,820

$76,509

Prairiedale No. 321

Reconstruct 1.6 km of Municipal Road - Phase I

$128,121

$74,736

Preeceville No. 334

Clay Cap 6.4 km of CTP Corridor

$120,000

$120,000

Preeceville No. 334

Clay Cap 3.2 km of CTP Corridor Self Tender

$70,000

$70,000

Prince Albert No. 461

Reconstruct 4.0 km of Gerrond Road

$603,271

$603,271

Prince Albert No. 461

Reconstruct 3.0 km of RusStan Road

$345,000

$137,423

Prince Albert No. 461

Reconstruct 1.6 km of RusStan Road

$235,000

$235,000

Redberry No. 435

Clay Cap 3.2 km of Grid 781

$423,335

$109,889

Redburn No. 130

Upgrade Thule Bridge

$362,000

$123,791

Reford No. 379

Clay Cap 0.8 km of Road

$20,000

$20,000

Reno No. 51

Replace Cattle Underpass with Culverts

$4,701

$4,701

Reno No. 51

GWR Crossing Improvements

$8,807

$8,807

Reno No. 51

Install Culverts at Cypress Lake Road

$12,059

$12,059

Reno No. 51

Upgrade Schmidt Bridge

$32,295

$32,295

Riverside No. 168

Reconstruct 4 km of Road

$173,000

$144,746

Rocanville No. 151

Upgrade 8 km of Road

$225,000

$30,274

Rodgers No. 133

Replace Culverts and Build Up Road at 6 Locations

$46,056

$29,835

Rosedale No. 283

Replace Bridge with Culverts

$200,000

$152,131

Rosemount No. 378

Upgrade 3.2 km of Randy's Road

$70,000

$58,489

Rosthern No. 403

Replace Friesens Bridge with Culverts

$323,210

$323,210

Round Hill No. 467

Clay Cap 1.6 km of Primary Weight Corridor

$318,364

$124,535

Round Valley No. 410

Reconstruct 6.4 km of Primary Grid 787

$883,500

$184,645

Rudy No. 284

Reconstruct 4.7 km on Highway 219 Connector

$583,678

$108,401

Sarnia No. 221

Reconstruct 4.8 km of Penzance Grid

$400,000

$78,576

Saskatchewan Landing No. 167

Culvert Replacement

$30,556

$30,556

Saskatchewan Landing No. 167

Reconstruct 8 km of Propane Grid

$53,000

$53,000

Saskatchewan Landing No. 167

Reconstruct 1.6 km of Site #1 Road

$15,778

$15,778

Sasman No. 336

Reconstruct 4.83 km of Super Grid

$436,538

$92,787

Sasman No. 336

Reconstruct 3.22 km of Primary Grid

$504,075

$231,168

Sasman No. 336

Replace Bridge with Three Culverts

$120,606

$74,634

Scott No. 98

Upgrade Bridge at N 36-11-17-W2

$46,000

$4,998

Scott No. 98

Upgrade Bridge at E 22-10-16-W2

$79,900

$41,483

Scott No. 98

Upgrade Bridge at E 17-12-16-W2

$37,700

$5,509

Sherwood No. 159

Reconstruct 4.82 km of Inland Drive

$6,600,000

$274,427

Sliding Hills No. 273

Clay Cap 3.2 km Mazeppa Grid

$200,000

$138,280

Snipe Lake No. 259

Reconstruct 4.8 km of Grid 752

$949,414

$133,521

Souris Valley No. 7

Replace Long Creek Bridge

$730,000

$70,896

South Qu'Appelle No. 157

Reconstruct 6.2 km of Road

$448,000

$328,339

South Qu'Appelle No. 157

Clay Cap 4 km Blair's Grid Phase 2

$135,000

$135,000

Spalding No. 368

Clay Cap 4.8 km of Grid 640

$300,000

$186,693

Spiritwood No. 496

Replace Witchekan Bridge with Culverts

$250,000

$10,000

Spiritwood No. 496

Reconstruct Zuk Road

$75,000

$75,000

Spiritwood No. 496

Replace Golf Course Bridge

$105,000

$105,000

Spiritwood No. 496

Rehabilitate Hunt Farm Bridge

$32,000

$32,000

Spiritwood No. 496

Rehabilitate Town of Spiritwood Bridge

$76,000

$76,000

St. Andrews No. 287

Upgrade 1.6 km of Cosway Road

$41,375

$41,375

St. Andrews No. 287

Upgrade Bridge at SE 33-30-15-W3

$25,777

$24,550

St. Andrews No. 287

Upgrade Green Road SE 33-30-15 W3

$7,730

$7,730

St. Andrews No. 287

Upgrade Cosway Westside E 17-28-15-W3

$82,130

$82,130

St. Louis No. 431

Upgrade 2.5 km CTP Road

$400,000

$254,286

St. Philips No. 301

Replace Three Culverts

$40,000

$40,000

Stanley No. 215

Clay Cap Grid 618

$800,000

$170,000

Stanley No. 215

Upgrade 21 km of Old Highway 10

$355,335

$180,819

Star City No. 428

Upgrade 0.8 km of Provincial Grid 681

$85,000

$85,000

Star City No. 428

Upgrade 1.6 km of Provincial Grid 681

$170,000

$119,173

Storthoaks No. 31

Replace Bridge with 3 Culverts

$250,000

$89,802

Surprise Valley No. 9

Construct 3.2 km of Road

$160,000

$74,145

Sutton No. 103

Upgrade Dry Lake Road

$185,083

$70,896

Swift Current No. 137

Clay Cap 7.2 km of Sand Road

$933,376

$600,253

Tecumseh No. 65

Reconstruct 1.4 km of Road

$200,000

$79,758

Terrell No. 101

Reconstruct 4.8 km of Eisen Road

$68,000

$60,582

Three Lakes No. 400

Construct St. Benedict Lagoon Road

$30,360

$30,360

Tisdale No. 427

Replace Bridge with Culvert and Upgrade Bridge

$338,233

$270,586

Torch River No. 488

Upgrade Madryga Bridge

$120,400

$25,710

Torch River No. 488

Replace Bridge with Large Diameter Culverts

$255,000

$77,000

Touchwood No. 248

Upgrade Mission Lake Road

$125,000

$78,872

Tramping Lake No. 380

Reconstruct 6.5 km of Road

$450,000

$121,114

Tullymet No. 216

Rebuild 4.82 km of Goodeve Grid

$150,000

$64,988

Turtle River No. 469

Rebuild Range Road 3195

$470,000

$106,444

Usborne No. 310

Resurface 22 km PG 668 HH - Phase 2

$4,500,000

$161,584

Val Marie No. 17

Reconstruct 2.6 km of Rosefield Grid

$215,137

$143,428

Vanscoy No. 345

Haul Road Reconstruction

$1,200,000

$1,200,000

Victory No. 226

Clay Cap 3.2 km of Park Road

$224,898

$80,862

Viscount No. 341

Upgrade Langston Road

$27,000

$20,000

Viscount No. 341

Upgrade St. John's Cemetery Road

$40,000

$35,000

Viscount No. 341

Upgrade Buffalo Fence North Road

$30,000

$25,000

Viscount No. 341

Upgrade Glenfield Road

$81,000

$70,980

Walpole No. 92

Clay Cap 4.8 km of Ryerson Road

$180,450

$99,845

Waverley No. 44

Replace Two Bridges with Culverts

$60,000

$50,000

Wawken No. 93

Clay Cap 2.4 km of Scammel Road and Install Culverts

$181,978

$165,129

Webb No. 138

Reconstruct 4.8 km of Range Road 3170

$240,000

$157,448

Wellington No. 97

Replace Two Culverts

$23,200

$23,200

Weyburn No. 67

Widen 22nd Ave SE Turn off

$29,004

$29,004

Weyburn No. 67

Upgrade Golf Course Bridge

$183,000

$183,000

Whiska Creek No. 106

Reconstruct 1.6 km of Division 2 Haul Route Road

$65,000

$65,000

Whiska Creek No. 106

Replace Culvert Project 'A' and 'B'

$140,438

$123,758

Whiska Creek No. 106

Replace Culvert Project 'C'

$66,020

$66,020

Willner No. 253

Reconstruct 8 km of Girvin Grid #749

$1,408,250

$72,373

Willow Bunch No. 42

Upgrade Pavement on Park Access Road

$45,500

$25,000

Willow Creek No. 458

Replace Bridge with Culvert-ESE 21-48-16 W2

$22,000

$20,927

Willow Creek No. 458

Replace Bridge with Culvert-ENE 13-48-17 W2

$22,000

$20,332

Willow Creek No. 458

Replace Bridge with Two Culverts-ENE 26-48-17 W2

$23,000

$21,755

Willow Creek No. 458

Replace Little Bridge Creek Bridge with Two Culverts

$30,000

$28,800

Willow Creek No. 458

Upgrade Sandhill Creek Road

$50,000

$45,000

Willow Creek No. 458

Construct McFarlane Low Level Crossing

$19,000

$18,000

Willow Creek No. 458

Upgrade Bohaychuk Road

$12,000

$11,500

Willow Creek No. 458

Upgrade Swanson Road

$20,000

$18,500

Willow Creek No. 458

Replace McKenzie Bridge with 2 Culverts

$45,000

$42,800

Willow Creek No. 458

Replace Metcalfe Bridge with Culvert

$35,000

$33,000

Winslow No. 319

Reconstruct 6.5 km of Main Farm Access

$1,192,179

$95,710

Wise Creek No. 77

Replace Culvert and Rebuild Road Grade

$12,000

$12,000

Wise Creek No. 77

Reconstruct Thin Membrane Pavement

$210,240

$38,000

Wolseley No. 155

Replace Culvert at Rose Lane Road

$100,000

$80,427

Wolseley No. 155

Rebuild 1.6 km of McMain Road

$60,000

$39,210

Wood Creek No. 281

Upgrade 4.9 km of Simpson Grid

$410,780

$60,557

Wreford No. 280

Install Culvert at SSW 4-29-24

$5,521

$5,521

Wreford No. 280

Replace Culverts on Two Adjoining Roads

$21,985

$21,985

For more information on the federal Gas Tax Fund, please visit: http://www.infrastructure.gc.ca/plan/gtf-fte-eng.html

 


Search for related information by keyword

Page details

2024-08-22