Media Response Lines on National Shipbuilding Strategy
On this page
Commitment to Canadian Shipbuilding / National Shipbuilding Strategy
- The Government of Canada is ensuring that the Royal Canadian Navy operates as a blue- water maritime force, maintaining its capability to defend Canadian sovereignty and security and contribute to international efforts.
- Under this program, the Royal Canadian Navy will acquire its next generation of surface combatant ships, Arctic and Offshore Patrol ships, and replenishment vessels. These new vessels will ensure the Canadian Armed Forces can continue to conduct sovereignty and surveillance operations off all three coasts, as well as participate in international efforts to combat terrorism and piracy.
- Significant progress has been made on each of the naval shipbuilding projects for the Royal Canadian Navy, namely the Joint Support Ships, Arctic and Offshore Patrol Ships, and the Canadian Surface Combatants.
- Canada’s new, phased approach to shipbuilding ensures that preparatory work is completed before proceeding to construction, reducing risk and ultimately improving the efficiency of the shipbuilding process, and ensuring maximum value for taxpayer dollars.
- In recent years, the Government of Canada has made significant investments in the marine sector as a result of the contracts flowing from the prime shipyards that have been selected as part of the National Shipbuilding Strategy that are strengthening the workforce, infrastructure, and technical expertise needed for this historic fleet renewal.
Speaking Points/Media Lines – National Shipbuilding Strategy
- The Government of Canada is ensuring that the Royal Canadian Navy operates as a blue-water maritime force, maintaining its capability to defend Canadian sovereignty and security and contribute to international efforts.
- Under the National Shipbuilding Strategy (NSS), the Royal Canadian Navy will acquire its next generation of surface combatant ships, Arctic and Offshore Patrol ships, and replenishment vessels. These new vessels will ensure the Canadian Armed Forces can continue to conduct sovereignty and surveillance operations off all three coasts, and participate in security operations anywhere in the world.
- Significant progress has been made on each of the naval shipbuilding projects for the Royal Canadian Navy, namely the Joint Support Ships, Arctic and Offshore Patrol Ships, and the Canadian Surface Combatants (CSC).
- The Department of National Defence remains committed to the NSS as we continue to see progress on our shipbuilding projects.
Cost and time estimates (need common response across departments)
- Shipbuilding is a complex and highly specialized undertaking that requires significant time, effort, and financial investment, particularly for first-of-class vessels. As with any large-scale procurement, it is not uncommon for the estimated value and timelines to change throughout the duration of the project.
- Initial cost and time estimates are developed before a ship design is selected or a build contract is awarded. A number of factors that impact the cost and time required to build ships are therefore not known when these early estimates are established. As such, project offices must rely on industry norms and existing, available data from similar projects to establish these estimates, while also accounting for uncertainty/risk.
- Some of the data that is unknown at the time of initial estimates includes costs and timelines related to design work, material, inflation, equipment and systems, as well as labour costs required to build, test, and integrate ships into the Royal Canadian Navy’s (RCN) fleet. As work moves forward and more of these unknown items are clarified, our estimates become more refined and certain.
- As such, evolving cost and time estimates are natural. However, we continue to work closely with Government, industry, and Allied partners to share more complete data, and better understand, predict, and mitigate risks.
- When comparing costs, it is important to recognize that Canada is currently in the process of revitalizing its shipbuilding industry through the National Shipbuilding Strategy. Canadian shipyards may have less recent experience than other long- standing, international shipyards. As Canadian shipyards are working to adapt their facilities and workforces to support the construction of a new class of ships, there may be differences in production rates, construction practices, and supply chains, which can have an impact on costs.
- We are happy to continue working with the PBO, the OAG, and other similar organizations as we continue to improve our practices.
Capability gaps
- Shipbuilding schedules have been carefully developed to ensure the RCN has the required fleet capacity it requires to accomplish its important missions.
- While we cannot guarantee there will be no capability gaps, any gaps that may arise are not expected to be significant.
- In the unlikely event that new ships are not delivered before current ships are retired, a number of mitigation measures are available to the RCN to ensure continued service. These include mutual service agreements with other countries, smart scheduling, and leasing of services.
- We continue to closely monitor the progress of our shipbuilding progress to ensure timely delivery.
Improvements
The OAG Report highlighted a number of corrective actions and key decisions made, which have placed the NSS on a more viable path. These actions included:
- The review of a corrective action plan from Seaspan in response to a 2018 assessment prepared by a third party expert was completed. This allowed the NSS team to identify risks to reaching objectives. A similar assessment is underway for Irving.
- A number of decisions were made to address risks, following considerable analysis, discussions with third parties, and interdepartmental collaboration. This has resulted in new delivery schedules based on more realistic assumptions. For example:
- Measures, such as a longer construction period for the Arctic and Offshore Patrol Ship (AOPS), have been established in order to maintain shipyard activity and workforce skills.
- The construction schedule at Seaspan’s Vancouver Shipyards has been reordered to better match work capacity within the yard.
- PSPC has launched a competition for a third shipyard to help meet workload requirements.
- Measures were also taken to help ensure continued operations until new ships are delivered.
COVID-19
- The global COVID-19 pandemic has resulted in an unprecedented situation, with impacts that are far reaching and difficult to define at this time.
- Work has continued where possible, and we are closely monitoring the COVID- 19 situation while working with industry to ensure projects remain on track.
- A full impact assessment of the potential effects on all project schedules under the NSS will be completed once the situation has stabilized and the local and global impacts of COVID-19 are better understood.
- Updates to project timelines will be shared once available.
Questions and Answers (full project lines are available separately)
Canadian Surface Combatant
Timeline:
- construction start: the 2023/2024 timeframe
- first delivery: early 2030s
- close-out: late 2040s
Cost: $56-60B
Q1. What are the current timelines for the CSC project?
A1. The CSC project entered the design phase in 2019. This phase is expected to take four to five years. Once the design work is sufficiently mature, the Government of Canada will award an implementation contract to Irving Shipbuilding Inc. to build the ships. We expect to begin construction of the simpler zones [parts] of the ship while the design work on the more complex sections continues, similar to what we have done for the Joint Support Ship.
The construction of the first ship is expected to begin in the 2023/2024 timeframe, with delivery of the first ship expected in the early 2030s. We are working closely with our industry partners to find efficiencies and accelerate these new timelines.
Q2. When will the Halifax-class fleet be retired? Will you start receiving the CSC before Halifax-class ships are retired or will there be a capability gap?
A2. Following the recent Halifax-class frigate life extension, no firm timeline has been identified for the retirement of the fleet. We continue to maintain the ships in order to ensure they remain operational until the CSC is transitioned into service.
Q3. The initial estimate for the CSC project was $26.2 billion in 2008, and is now between $56-60 billion. How did you calculate your cost estimate?
A3. The initial cost of the CSC project in 2008 was an early estimate that was calculated based on the generic warship design of a similar size and capability. This early estimate used historical and available market data from previous domestic shipbuilding projects, as well as recent industry benchmarks from other countries building comparable warships, such as labour, material costs, and inflation. This initial cost estimate was based on the available data at the time, and did not account for future changes to economic conditions, the costs of goods and services, or industry capacity.
Since the initial project estimate was made, the Government of Canada implemented the National Shipbuilding Strategy, which included the selection of Irving Shipbuilding Inc. to build the CSC, and the development and release of a competitive procurement process to select the design contractor team and the basis for the ship design– the Type 26. With the release of Canada’s defence policy, Strong, Secure, Engaged in 2017, a cost analysis for the CSC project was completed, and the project cost was updated to $56-60 billion. This revised value reflects costs related to building modern ships with current technology and resources; improvements to the rate of production as the shipyard gains efficiencies during construction; and additional contingency funding. The updated project cost was also independently verified by external organizations to ensure validity and consistency, and will continue to be monitored by an independent third-party to ensure its accuracy throughout the duration of this project.
Joint Support Ships
Timeline:
- first delivery: 2023
- second delivery: 2025
Cost: $4.1B
Q1. The current interim services contract expires before the first JSS is scheduled to be delivered. What will you do about this capability gap?
A1. The RCN has a variety of options available to ensure it remains able to deliver on the missions laid out in Strong, Secure, Engaged. This includes the use of commercial Auxiliary Oiler Replenishment capabilities, as well as the implementation of strategies such as smart scheduling (sailing with and leveraging allies and partners who have support ship capabilities). As there are approximately two years remaining before the end of the interim contract, no decision has been made by the Government of Canada on an extension of the contract yet and all options are still possible.
Q2. You’ve changed the cost of the JSS twice while the Parliamentary Budget Officer successfully predicted this new cost several years ago. Why didn’t you get it right the first time?
A2. As with any large-scale procurement project, all project values are best estimates that are based on the data and figures available at the time. Following the beginning of construction in June 2018, the cost was updated with a better understanding of project risks, the remaining work required to build the ship, as well as the details of the associated construction contract. Based on this understanding, the total project cost estimate was updated from $3.4 billion to $4.1 billion for the design, construction, project and contract management, and contingency costs associated with the acquisition of these ships. We will continue working closely with all our partners to actively manage and monitor this budget over the duration of the JSS project. As the cost to build a ship is based on engineering specifications, production plans, and schedules developed during the design phase, the full budget continues to be further refined as the design is finalized. As a result, it is not uncommon for the cost estimate to change throughout the duration of a project, especially for a first-of-class ship.
If pressed about not waiting for completion of full design before announcing these changes:
Based on our latest estimates, we needed to seek additional funds for this project. These funds needed to be secured before a final contract was signed. In order to avoid any delays to the project, we have proceeded to secure funds based on our advanced estimates and before completion of the design work. As this has had an impact on the overall project budget, updated figures were shared with the public.
Arctic and Offshore Patrol Ships
Timeline:
- Ship 1 delivered: July 2020
- Ship 2 delivery: 2021
- Ship 3 delivery: 2022
- Ship 4 delivery: 2023
- Ship 5 delivery: 2024
- Ship 6 delivery: 2024
Cost: $4.3B
Q1. Will additional work on the Halifax-class ships be required to continue their role as a result of delivery delays? Will the Halifax-class be retired before the AOPS are delivered, creating a capability gap?
A1. The decision to keep the Halifax-class ships in service was made several years ago, and was not based on delays to the AOPS project. As a result, ongoing maintenance of the Halifax-class will continue to ensure the RCN has the fleet capacity required to support its operational needs until the transition to its future fleet is complete in the early 2040s.
Q2. The original delivery date for the first AOPS was spring 2018, which was progressively delayed to spring 2020. This date was then further delayed as a result of COVID-19. Why have there been so many delays and why are you incapable of providing an accurate delivery timeline?
A2. Building a new class of ships is very complex, and we acknowledge there have been delays to our original delivery timelines for the first and second AOPS. Our foremost priority is ensuring that a quality ship is delivered to the Royal Canadian Navy, and we will take the time needed to ensure this.
The schedules were difficult to predict mainly because the AOPS is a new design, and is being built with largely new facilities, workforces, and processes. The ship is also a complex military platform (for example, there is over 300 kilometers of cabling and various weapons systems), which makes sequencing work, anticipating potential integration issues, and forecasting schedules very challenging. Additionally, as the shipbuilder must adapt and modify several construction processes to establish the best way to build these ships, construction of a first-of-class ship will not be as efficient as the following ships.
The timelines for the first ship had shifted in order to ensure required work was completed before delivery. This included completing rigorous inspections, tests and trials (including sea trials), and correcting any defects. Lessons continue to be learned throughout the construction process, and are benefitting the construction of the subsequent ships. However, as resources were focused on delivery of the first ship, and some inefficiencies were still being resolved, delivery of the second ship was delayed. Unfortunately, these timelines have been further delayed as a result of the ongoing COVID-19 pandemic. We continue to work closely with Irving Shipbuilding Inc. to mitigate potential impacts, and will provide an update on timelines once the local and global impacts of COVID-19 are better understood.
Overall, the project is progressing successfully. The first ship has been delivered, and construction of the second ship is moving forward, with various inspections, tests, and trials concurrently underway to ensure the ship meets technical design requirements at the time of delivery. Construction of the third and fourth ships is progressing on-land, and construction of the fifth ship is expected to begin later this year. Additionally, hundreds of new jobs have been created at the Halifax Shipyard.
2021 Parliamentary Budget Officer (PBO) Report on CSC
Context:
- The PBO now estimates the cost of the CSC project at $77.3 billion
- This is an increase of 11% from the 2019 report on CSC ($69.8 billion à $77.3 billion)
- Main reasons for the difference between our cost and the PBO’s are the inclusion of provincial taxes, and the PBO emphasis on a weight-based costing model.
- The PBO also provided cost forecasts for alternative procurement scenarios:
- One scenario abandoning the current plan and starting with a new design based on the FREMM
- One scenario abandoning the current plan and starting with a new design based on the United Kingdom T31e
- A hybrid scenario of building three CSC and 12 FREMM
- A hybrid scenario of building three CSC and 12 T31e
- In providing these scenario options, the PBO acknowledges that there are several cost risks to these scenarios that have not been factored into their estimates such as the cost to extend the life of the Halifax-class, the cost to train sailors for multiple vessels, and the costs for spare parts for multiple vessels.
- The PBO assumes a 4 year delay to the overall project should a new design be selected to replace the Type 26
- PBO has calculated that future delays could increase costs as follows:
- One-year stoppage of work: increase of $2.3 billion
- Two-year stoppage of work: increase of $4.4 billion
Key Messages:
- We welcome the report of the Parliamentary Budget Officer (PBO) on the Canadian Surface Combatant (CSC).
- We find that the key difference in our cost estimates can be primarily attributed to the PBO including provincial sales tax and the emphasis put on weight as a cost factor. The PBO used a weight-based costing model, any increase in ship weight translates into an increase in cost. Comparatively, while DND considers weight as a factor in its cost analysis, it also incorporates the information received from industry, such as the actual known prices for the equipment required to build the ships.
- Since the selection of the Type 26 design, we have made significant progress on adapting the design to meet Canada’s operational requirements. This progress has allowed us to refine our estimated costs and timelines as we gain better certainty about the required combat and support systems.
- We remain confident that our current estimate of $56 billion to $60 billion accurately reflects the value of this project, and is based on information learned through the procurement process, the design phase, and ongoing work with industry.
- After extensive analysis and progress, we remain confident that basing the Canadian Surface Combatant on the selected Type 26 design will provide the required capability for the 15 surface combatants needed to support RCN operations over the next 50 years. As a result, we will not be re-opening the procurement process or selecting a new design, and will continue with design work in order to support the start of construction in 2023/2024.
Questions and Answers:
Q1. How do you explain the difference between your costs and the PBO’s costs?
A1. After reviewing the report, we find that the key difference in our cost estimates can be primarily attributed to the PBO including provincial sales tax and the emphasis put on weight as a cost factor. As the PBO used a weight-based costing model, any increase in ship weight translates into an increase in cost. Comparatively, while DND considers weight as a factor in its cost analysis, it also incorporates the information received from industry, such as the actual known prices for the equipment required to build the ships.
Our cost estimate also includes all components required to build and bring these ships into service, and is not just the cost for the ships themselves. In addition, our estimate includes contingency funding to account for project risks, which continues to be refined as we progress with design work and gain greater certainty about the complexity and required space for the ship’s combat and support systems.
While we recognize the differences in our calculations, we remain confident that our current estimate of $56 billion to $60 billion accurately reflects the value of this project. Additionally, available data confirms that our estimated project costs are in alignment with estimates for other comparable shipbuilding projects when the scope of the projects, life of the vessels, and full capabilities are considered.
Q2. So, are you saying the PBO’s numbers are wrong?
A2. No, we are not saying that the PBO is wrong, but we do recognize differences in the assumptions and models used for the calculations. With a project of this size and complexity, subtle differences in assumptions early in the project can result in significant differences to cost estimates over the duration of a project. The work of independent third parties such as the PBO and the Office of the Auditor General provides critical validation and accountability in support of our important procurement projects. We welcome their assessments and are happy to cooperate with them in the work they do.
Q3. Why didn’t you include taxes in your estimate?
A3. Our current estimate for the CSC project is $56 to $60 billion (before taxes). As a federal department, our practice is to not include taxes in our budget or cost estimates, since taxes do not have an impact on the department’s expenditures.
For provincial sales taxes, the department does claim an exemption in accordance with the Summary of Reciprocal Taxation Agreements with Provinces and Territories (Section 6). For federal sales taxes paid (e.g. GST&HST) are returned to the federal government through the Canada Revenue Agency.
In the case of CSC costs, DND follows the same financial reporting methodology.
Q4. The PBO report highlighted a significant increase in weight for the CSC. Why has the weight increased and how is this being managed?
A4. Canada’s requirements for the CSC outlined in the RFP did not specify weight. Instead, we included specifications that would enable the ship to perform its assigned missions during its operational service life. As the CSC are upgrading and replacing the capabilities of the Halifax and Iroquois classes of ships, it was expected that its overall size and displacement would be larger than that of either of these two classes of ships, but the exact weight couldn’t be known until a design was finalized.
Following selection of the design, we have gained a better understanding of ship. As a result, the weight of the CSC has increased from 6,900 tonnes to 7,800 tonnes. Increases to the weight of a ship are not uncommon during the design phase, and are managed by using design margins to accommodate changes. We are still in the early stages of the design phase, and we are examining options to mitigate and rationalize weight increases.
The overall weight, stability, and available margin for change of the CSC continue to be closely tracked by Canada as this is an important metric for supporting the design phase. This information is also being shared and discussed with other members of the Global Combat Ship User Group (the U.K. and Australia) to ensure the design and build of the CSC benefits from the successes and lessons learned from our allied partners building variants of BAE’s Type 26 warship.
Q5. Are there any costs the PBO didn’t include in their estimates?
A5. As noted in the report, the PBO cost estimate related to the scenario of starting with a new design does not include some key cost risks associated with the selection of a new design to replace the Type 26. A key cost risk relates to the assumption that the FREMM or the T31 would be proposed in response to a RFP based on Canadian requirements, and, if they were proposed, that assumptions used in the PBO costing model would remain consistent. Other cost risks include the associated costs of further extending the life of the RCN’s Halifax-class ships to mitigate gaps and ensure they have the required operational support until the arrival of the CSC.
In the case of the PBO’s second scenario where two different designs are built, there could be increased through-life costs for operating and maintaining two different classes of ships, including in-service support, training, spare parts, infrastructure, etc.
Additionally, selecting a second design and starting a new design phase required to meet the RCN’s operational requirements would challenge the capacity of both the Government of Canada and industry to manage two large concurrent procurement processes.
Finally, the PBO estimate did not account for additional costs associated with the interruption and inefficient re-starting of work at shipyards, their sub-contractors, and in the supply chain. Cost efficiencies generated by lessons learned after construction of the first ships are also included in our costs and would be lost should we build two classes instead of one.
Q6. The PBO has stated that every single year of delay could result in an additional cost of $2.3 billion. What steps are you taking to mitigate potential project delays?
A6. We recognize the impacts that changes to design and construction timelines can have on project costs, and acknowledge the PBO’s data on this issue. However, it’s important to note that this cost increase would only be a result of fully stopping all related work on the CSC project. Work on the CSC project has progressed well since February 2019, in spite of the ongoing COVID-19 pandemic.
Our project management practices ensure that timelines are updated and validated as the project progresses. Risks and uncertainty will continue to be reduced as more concrete information becomes available through the design and beginning of construction. Like any large-scale procurement project, project schedules will remain under close review, and we will continue working with our partners to actively manage timelines and find efficiencies to ensure this critical platform is delivered to the RCN in a timely manner, while also providing the best value to Canadians.
Q7. The PBO suggested a scenario where work on the Type 26 design be terminated in favour of launching a new competition to select an alternative, cheaper design. Would you consider this scenario a possibility?
A7. No. The CSC design was selected through an open, fair, and transparent competitive procurement process, in which performance against the RCN’s requirements was a key selection criteria. Following the selection of the design in February 2019, significant progress has been made in adapting the design to meet Canada’s mission-specific requirements to enable the start of construction in 2023/2024. Changing the design at this stage in the project would also undo all of the current progress to support the start of construction, further delaying the delivery of this critical platform to the RCN, and requiring an extension of the Halifax-class.
While other allied warships could potentially be built at a lower cost, most do not provide the level of capability required for the CSC, and are therefore not an acceptable alternative to meet the RCN’s unique operational needs and required fleet capabilities. Alternative designs that could meet the RCN’S requirements would still require significant changes to meet Canadian specifications, and could result in a cost on-par with the current CSC budget. Additionally, changing the design as a way to reduce costs could have the opposite effect, as it would result in hundreds of millions of dollars in economic loss and a reduction in Canadian jobs due to work stoppage, increased costs due to lost productivity at the shipyard, expensive litigation costs, and significant operational impacts to the RCN due to associated project delays. Finally, the selection of a new design would lead to new costs to start the design process over.
After extensive analysis of the above factors, we remain confident that the inherent warfare capability and versatility of the selected CSC design will equip the RCN with the modern, capable, and effective fleet of warships it needs to defend Canada at home and abroad for decades to come, while also providing the best value to Canadians. As a result, we will not be re-opening the procurement process or selecting a new design, and will continue with ongoing design work to support the start of construction in 2023/2024.
Q8. The PBO has suggested a hybrid scenario that involves building the first batch of three Type 26 vessels, while simultaneously re-competing the design for the remaining 12 vessels. Would you consider this as a possibility?
A8. No. It is important to note that selecting one of the scenario designs (the T31e) would result in a significant reduction in operational capability for the RCN. While other allied warships could potentially be built at a lower cost, most do not provide the level of capability required for the CSC, and are therefore not an acceptable alternative to meet the RCN’s unique operational needs and required fleet capabilities.
Other scenarios with alternative designs that could meet the RCN’S requirements would still require significant changes to meet Canadian specifications, and would likely result in a cost on-par with the current CSC budget. Any savings in this case would quickly be eroded through additional in-service support costs of supporting two different classes of ships. As the CSC will upgrade and replace the capabilities of two classes of RCN ships in a single, combat-capable vessel, the Type 26 design was selected as the best option to meet the full spectrum of Canada’s operational requirements.
Additionally, selecting a second design and starting a new design phase required to meet the RCN’s operational requirements would challenge the capacity of both the Government of Canada and industry to manage two large concurrent procurement processes.
It’s also important to note that there are no guarantee that the recommended designs would submit a bid during a new competition, or that they would be selected as the winning bidder upon completion of the competition.
Q9. Why are you building ships in Canada when the PBO estimates that it’s more than 50% more expensive to do so?
A9. We recognize that building ships in Canada requires significant investments into our shipbuilding capabilities and workforce, which is at the core of the Government of Canada’s commitment to revitalizing the industry through the National Shipbuilding Strategy (NSS). While it’s difficult to accurately determine if it would be more cost effective to build the ships outside of Canada due to various differences in exchange rates, material costs, and supply chains, there are significant benefits to building the ships in Canada. This includes the strategic capability to maintain the ships in Canada once they are built. Past experience, such as our mission in Afghanistan, have demonstrated the importance of being able to maintain, repair and modify equipment within the country.
In addition to growing Canada’s domestic shipbuilding expertise, the CSC project will provide significant and long-standing economic investments into communities from coast-to-coast-to-coast. Through Industry and Science, and Economic Development Canada’s (ISED) Industrial and Technological Benefits Policy, 100% of the design and build contract values will be invested in Canada. Additionally, this project is estimated to create or maintain an estimated 2,500 Canadian jobs during the 4-5 year design period, and more than 10,000 Canadian jobs throughout the 25-year construction period. This project is also estimated to generate at least $40 billion in GDP. The CSC project will also continue to benefit from the expertise of Canada’s marine industry with ongoing sustainment work throughout its operational life.
Q10. Why do you need 15 ships? Will you consider acquiring fewer to reduce project costs? (RCN lead)
A10. As outlined in Canada’s Defence Policy, Strong Secure Engaged, Canada needs a navy with 15 Canadian Surface Combatants, complemented by two Joint Support Ships and four Victoria-class submarines to provide the necessary fleet mix and capacity to deploy forces responsively, prepare follow-on forces effectively, and conduct maintenance efficiently. This will provide a naval fleet that is built around the ability to deploy and sustain two naval task groups, each composed of up to four combatants and a joint support ship, and supplemented where warranted by a submarine, bringing the full breadth of combat capability, force enablers, specialized teams, maritime helicopters, and remotely piloted systems.
The CSC is Canada’s next generation warship that will replace and update the capabilities found in both the retired Iroquois-class destroyers (three) and the Halifax- class frigates (12) with a single, more capable combat ship, to meet multiple threats on both the open ocean and in the highly complex coastal (littoral) environment. Where Canada would have required multiple classes of ships for this range of missions in years past, the CSC is leveraging the latest technology, digitization and miniaturization, to enable a multi-role capability in a single class.
As the CSC project was fully costed, we remain confident in our current budget estimates, and are still planning to acquire 15 new ships.
Q11. What is the estimated cost breakdown for the CSC project?
A11. The current estimated project value includes all components required to build and bring these ships into service, and is not just the cost for the ships themselves. We are still within the $56-$60 billion estimate for the project, thanks to a contingency that was set aside for the project since the beginning.
Based on our current cost estimates, the estimated breakdown for the CSC project budget is as follows:
- Approximately 65% for the ship itself (higher for warships due to combat systems)
- 5-10% for design and project management costs
- Approximately 10% for weapons and infrastructure to support bringing the ships into service (e.g. Jetties, training facilities, test and integration facilities)
- 15-20% for contingency
We don’t calculate the cost per ship, as the project value includes all components required to build and bring these ships into service, and is not just the cost for the ships themselves. We remain confident that we’ll be able to deliver the 15 ships, the integrated logistics and support, as well as the supporting infrastructure within that budget.
Exact costs for personnel, operations, and maintenance needed throughout the full lifecycle of the CSC ships will be greatly influenced by the ship design, and will therefore only be available later in the process.
Q12. The PBO report shows that delivery of the first CSC has been delayed to the early 2030s. Why has delivery been delayed, and what measures are being implemented to prevent further delays?
A12. Ongoing work to adapt the selected CSC design to meet Canadian requirements has provided us with greater clarity about the complexity of the design and time required to build these ships. As a result, industry has proposed revised project timelines for the CSC project as follows:
- The design phase is now expected to take four to five years, with construction beginning in 2023/2024.
- Delivery of the first ship is now expected in the early 2030s, approximately 2-3 years later than previous estimates.
It’s important to note that the date for the start of construction hasn’t changed, but the expected length of the construction period has been updated to correspond to industry experience in the United Kingdom. We continue working closely with our allies and industry that are building variants of BAE’s Type 26 design in order to find efficiencies, accelerate delivery, apply best practices, and include updated industry benchmarks.
We are also working to implement measures to reduce risks of further delays. One of the ways we are doing this is with the construction of a Land Based Test Facility. Due to the complexity and highly integrated nature of the CSC combat systems, these systems must be tested to ensure they function correctly before they’re installed on the ships.
Since there are no existing facilities capable of supporting this type of testing for CSC, a new, purpose-built land-based test facility will be built in Halifax, Nova Scotia to carry out this work as part of the CSC’s rigorous tests and trials program. This facility will reduce the time required to test and certify functionality of the new combat systems for operational use, helping to reduce the risk of delays due to integration challenges, while also enabling the ships to enter into service quicker.
Like any large-scale procurement project, these timelines will remain under close review, and we will continue working closely with our industry partners to identify and implement appropriate mitigation measures, as needed. This active risk mitigation of the build schedule will continue for the entirety of the project to help ensure we are delivering the right ship for Canada to the RCN as quickly as possible.
Note: please see CSC-timeline specific media lines for more messaging on changes to delivery dates.
Q13. There have been multiple changes to this project, including the ship’s weight, timeline, and cost. Is this because you chose a design that was not yet proven and has never been fully built?
A13. The CSC project is the largest and most complex shipbuilding initiative in Canada since World War II. These ships will equip the RCN for decades to come. It’s also important to note that the changes to the schedule and design are a result of better understanding the complexity of the design and associated work prior to the start of construction. As a result, any warship with this capability would involve changes to its inherently complex design in order to ensure it meets RCN requirements. The changes to the design and project timelines are a normal part of any large-scale shipbuilding project, and would likely have occurred regardless of which design was selected.
The Type 26 design was selected through an open, fair, and transparent competitive procurement process, in which performance against the RCN’s requirements was a key selection criteria, and which was overseen by a fairness monitor. Despite the changes to date, this design remains the right choice for the RCN, and for Canada.
Q14. What is the benefit to having a single class of 15-ships, vice three ships that offer more specialized capability, and 12 that are more general purpose?
A14. The CSC is being designed as a single class with multi-role capability, which will enable it to be re-rolled from one mission to another while remaining deployed. This means, for example, that a CSC operating in the Asia-Pacific region as an air-defence platform for an allied amphibious task group, could quickly respond to a requirement to hunt an adversary’s submarine, or to lead an international task group providing humanitarian and disaster relief.
Where Canada would have required multiple classes of ships for this range of missions in years past, the CSC is leveraging the latest technology, digitization and miniaturization, to enable a multi-role capability in a single class:
- Digitization & Miniaturization: The CSC’s multi-role capability is enabled by leveraging widespread digitization and the use of solid state electronics onboard the CSC, resulting in an overall miniaturization of equipment and the freeing-up of square footage for additional capabilities, and to improve working and habitability conditions, including making accommodations and personal living spaces better for the crew; and
- Multi-function Equipment: The CSC will also incorporate equipment with multi-role capability wherever practical, enabling, for example, a single digital beam-forming radar to replace multiple traditional radars, and software-defined radios to be setup to support different communications requirements on the fly. Multi-functionality even extends to the CSC’s modular mission bay: a reconfigurable space able to accommodate and integrate any container payload imaginable.
Having a single class with multi-role capability will result in:
- Increased Operational Agility: It will provide greater speed and flexibility when assigning forces to operational requirements, which is crucial for a country like Canada, where its two naval bases are a continent apart and its ships are often deployed half-way around the world;
- Increased Operational Readiness: It means that when the RCN is assembling a national naval task group of several multi-role CSCs to respond to a crisis, it will be able to draw from the entire surface combat fleet to assign ships at different readiness levels, resulting a higher rate of operational availability, which is especially important given the RCN’s relatively modest fleet size;
- Increased Supply-Chain Efficiencies: Having a single class with multi-role capability results in a dedicated supply chain with more efficiency and equipment availability (especially given that two allies are procuring ships based on the common Type 26 design);
- Increased Labour Efficiencies: A single-class will also result in labour specialization efficiencies, and more efficient repair training and use of required ship repair facilities; and
- Increased Training Efficiencies: It will also mean common training modules can be provided to larger student cohorts, while simultaneously enabling deeper knowledge and specialist personnel development amongst a greater pool of available crew with common qualifications.
When taken as a whole, the technological advancements that will be incorporated into the CSC result in a single-class, single variant choice, with an inherent multi-role capability, which will serve Canadian interests for decades to come.
Approved:
- Cmdre Gray, CSC PM
- Vrenti Ghergari, DCA
- Tina Raymond, A/Manager Mat PA
- Wayne Rockwell, DGMPD(Sea)
- RAdm Donovan, DGFSC
- VAdm Baines, CRCN
- Troy Crosby, ADM(Mat)
- Cheri Crosby, ADM(Fin)/CFO
- Quinn Watson, A/DPAPI
- Elizabeth McKelvey, A/DGPASP
- Laurie Kempton, ADM(PA)
- MNDO
Issue: Joint Support Ship (JSS) project status
Date: April 2021
Overview
The Royal Canadian Navy (RCN) is replacing its surface fleets with new, modern, and versatile ships. Through the National Shipbuilding Strategy (NSS), Seaspan Shipyards in Vancouver B.C. will be building two new Joint Support Ships (JSS) for the RCN. Known as the new Protecteur- class, these large support ships will be replacing the RCN’s former auxiliary oiler replenishment (AOR) vessels that were decommissioned after reaching the end of their operational lives. In addition to providing critical at-sea replenishment, these multi-purpose warships will also be capable of seamlessly integrating with any Canadian or allied naval task group, and will significantly extend the range and endurance of these groups through the provision of fuel, ammunition, aviation support, food, spare parts, and medical and dental care. The project is currently valued at $4.1 billion.
Construction of the ships early blocks began in June 2018, and a contract award to progress with full-rate construction was awarded on June 10, 2020. The first ship is expected to be delivered in 2023, with the second ship expected to be delivered in 2025.
Key Messages
- New ships are necessary to maintain the capability and effectiveness of Royal Canadian Navy (RCN) operations, and are an important investment into maintaining naval defence and security at home, and abroad.
- Together with the Canadian Surface Combatants and the Arctic and Offshore Patrol Ships, the Joint Support Ships (JSS) will form the core of the future RCN surface fleet, and will surpass the operational capabilities of our former auxiliary oiler replenishment vessels.
- A $2.4 billion contract (including taxes) was awarded to Seaspan Vancouver Shipyards on June 10, 2020 to progress with full-rate construction. 3,900 jobs will be supported annually from 2020 to 2026.
- The joint decision to sequence the full construction of the first JSS ahead of the Offshore Oceanographic Science Vessel (OOSV) was made to allow for uninterrupted construction of the first JSS, while also helping to maintain the shipyard’s highly-skilled Canadian jobs.
- Both the government of Canada and Canadian industry continue to apply lessons learned from the National Shipbuilding Strategy and the first-of-class builds to ensure the best value for money. Costs may change as we finalize the construction contract.
On welding issues
- We are aware of the additional work required to the Canadian Coast Guard vessels.
- The welding processes are being reviewed to address the different certification requirements that apply to the Joint Support Ships. Any lessons learned from the construction of the Coast Guard vessels will also be implemented in the JSS build.
- We have full confidence in Seaspan’s ability to build these ships.
- Please refer to CCG for any questions regarding the OFSV.
Questions and Answers
Q1. What is the Joint Support Ship (JSS) project?
A1. As part of the National Shipbuilding Strategy (NSS), the Joint Support Ships (JSS) will replace the Royal Canadian Navy’s (RCN) former fleet of Protecteur-class Auxiliary Oiler Replenishment (AOR) vessels, the last of which was paid off (decommissioned) in late 2016.
The new JSS (to be known as the new Protecteur-class) will be built by Seaspan’s Vancouver Shipyards Co. Ltd. This company was competitively selected in October 2011 as the prime contractor to build the NSS program’s non-combat vessels.
Q2. What is the purpose of AOR vessels?
A2. The purpose of AOR vessels is to re-supply deployed ships at sea. This extends the amount of time a task group can remain at sea, eliminating the need to leave an operational area or return to port for resupply. This greatly increases the task group’s effectiveness, flexibility and endurance. This capability ensures that the RCN is better positioned to succeed across a range of mission sets, including combat operations, humanitarian assistance, disaster relief, and diplomacy. An AOR capacity also improves our collaboration with other Canadian government departments and agencies, as well as our interoperability with our allies.
Q3. How will the new JSS benefit the RCN?
A3. The JSS is critical to the future of the RCN, and constitutes a vital and strategic national asset. The presence of replenishment ships increases the range and endurance of a Naval Task Group, permitting it to remain at sea for significant periods of time without returning to port for replenishment. The new JSS will have capabilities such as:
- Underway support to Naval Task Groups: Underway support is best described as:
- the re-supply of fuel, ammunition, spare parts and other supplies between ships at sea;
- the operation and maintenance of helicopters;
- the task group medical and dental facilities.
- Sealift: JSS will be capable of transporting and delivering cargo both in support of task group operations and in support to operations ashore; and
- Support to operations ashore: To meet a range of possibilities in an uncertain future security environment, the JSS will leverage its onboard facilities to support operations ashore, including anything from combat to humanitarian and disaster relief.
The JSS will provide Canada with a modern, task tailored, globally deployable, naval support capability that can provide support to the ships and aircraft of a naval task group at sea. It will be crewed by CAF personnel and meet the RCN’s operational requirements for this role.
Q4. How many ships will be delivered?
A4. As outlined in Strong, Secure, Engaged, the JSS project will deliver two ships.
Q5. The RCN has previously indicated that they need three, even four ships for support purposes. Why are only two being purchased?
A5. As outlined in Strong, Secure, Engaged, the Government of Canada has determined that a fleet of 15 Canadian Surface Combatants, complemented by two Joint Support Ships, and four Victoria-class submarines, will provide the necessary fleet mix and capacity to meet the needs of the future maritime security environment.
Ensuring that our women and men in uniform have the equipment they need to complete their work is essential to the Department of National Defence (DND). Through Strong, Secure, Engaged, DND will deliver the capabilities the RCN needs to meet future defence and security challenges, both at home and abroad, and to carry out the tasks required of a modern navy.
Q6. Will purchasing only two ships create a capability gap?
A6. No. The RCN has a variety of options available that will ensure they will be able to deliver on the missions as laid out in Strong, Secure, Engaged. This includes the contracting of services from a commercial AOR capability (like what was done with MV Astérix), as well as the implementation of strategies such as smart scheduling (sailing with and leveraging allies and partners who have support ship capabilities).
Q7. Why can’t you just use MV Astérix and convert another commercial ship? It would be quicker, cheaper, and easier than building the JSS.
A7. While MV Astérix is meeting the RCN’s short-term requirements for basic at-sea replenishment duties, it is a commercial vessel that is not built to the same standards as a military ship. As a result, it is not equipped to conduct the full spectrum of military activities required by the RCN, including those required in high-threat environments.
Additionally, as MV Astérix is manned by a civilian crew, who has the right to refuse to undertake any missions or tasks for reasons of safety or commercial interests, the vessel may not be deployed for all missions or tasks required by the RCN. Finally, the cost of Astérix only covers the provision of service over a limited number of years, and does not represent the cost of purchasing the ship outright.
In comparison, the JSS will be able to carry out at-sea replenishment capabilities as well as the full spectrum of military activities required for RCN operations, with a design that includes improved survivability, lifespan, and effectiveness. The JSS will also provide added flexibility and range to Canadian and allied warships in high threat environments by serving as supply vessels providing fuel, ammunition, aviation support, spare parts, food, medical and dental care, and cargo space. Together with the Canadian Surface Combatants and Arctic and Offshore Patrol Ships, the JSS will form the core of the future RCN fleet, and will provide the best value for Canadians.
Costs and Benefits
Q8. What is the total cost of the project?
A8. The cost of this project is currently valued at $4.1 billion. This includes the funding for the two brand new ships, as well as all of the equipment, tools, and project oversight needed to build and bring them into service. This total cost estimate for the project remains under review as the design effort finalizes and the construction of the ships progresses.
Q9. Why has the Joint Support Ship project budget increased again from $3.4 billion in 2018 to $4.1 billion in 2020?
A9. As with any large-scale procurement project, all project values are best estimates that are based on the data and figures available at the time. In the case of the first JSS, construction of the early build blocks was able to begin ahead of schedule in June 2018 as their design was sufficiently mature to enable production, while the design of the remainder of the ship continued to progress. We now have a better understanding of project risks, the remaining work required to build the ship, as well as the details of the associated construction contract. This has allowed us to update our total project cost estimate from $3.4 billion to $4.1 billion for the design, construction, project and contract management, and contingency costs associated with the acquisition of these ships. We will continue working closely with all our partners to actively manage and monitor this budget over the duration of the JSS project. As the cost to build a ship is based on engineering specifications, production plans, and schedules developed during the design phase, the full budget continues to be further refined as the design is finalized. As a result, it’s not uncommon for the cost estimate to change throughout the duration of a project, especially for a first-of-class ship.
Note: Questions regarding the cost increase are answered in separate media lines.
Q10. Germany built the same ship at a much cheaper cost. Why is the cost of the JSS significantly higher than the German version?
A10. In addition to the costs required to design and build the JSS (material, equipment, labour, contingency, and project and contract management costs), our estimated project budget includes all the costs associated with bringing a ship into service. This includes spare parts, technical data, training, and many other components required to support and maintain these ships over their lifetime.
Comparatively, the cost of Germany’s Type-702 Berlin-class ship may seem significantly lower than the JSS, but it is solely for the construction of the ships and does not include all the associated project components. For example, it does not include the cost of required changes to meet current Canadian standards or costs associated with inflation as the first German ship was commissioned in 2001. As a result, it’s not a fair “apples-to- apples” comparison between the costs of the two projects as they do not include the same elements. Comparing the project budget of the JSS to other countries building supply ships presents the same problem as other countries do not calculate budgets the same way we do, where different project components may be included or excluded.
Q11. Will the Industrial and Regional Benefits policy apply?
A11. Through this design work Seaspan’s Vancouver Shipyards Co. Ltd. will be expected to demonstrate value to Canada including meeting its commitment to provide Industrial and Regional Benefits equal to 100 per cent of the value of the design and build contracts.
Build and Design
Q12. What work has been done to date on the project?
A12. A number of key tasks have already been accomplished on this project:
- A proven, off-the-shelf design by ThyssenKrupp Marine Systems Canada was selected as the ship design for the future JSS. This design offered the best value and overall combination of benefits in terms of capability, risk and affordability.
- An Initial Design Review was completed in 2017, providing Seaspan’s Vancouver Shipyards Co. Ltd the opportunity to fully review and analyze the proven off-the- shelf design.
- In 2015, Seaspan’s Vancouver Shipyards was awarded the Long Lead Items contract and has since been engaging suppliers and selecting the equipment, including items such as the propulsion systems and generators, needed to finalize the design to build JSS.
- In December 2016 the shipyard was awarded the JSS Design & Production Engineering contract to bring the JSS design to production readiness to enable the start of ship construction
- The JSS construction started in June 2018 on areas where the design was mature.
- In August 2018, an initial $66.6 million contract (including taxes) was awarded for the construction of up to 52 early blocks for the JSS. This was possible due to the maturity of the ships blocks’ design, which allowed us to progress with early construction and the acquisition of long lead items while design work on the more complex blocks continued at the same time. This contract was amended to approximately $120 million (including taxes) to sustain construction until the full- rate construction contract could be awarded.
- In June 2020, a $2.4 billion contract (including taxes) was awarded to Seaspan Vancouver Shipyards to progress with full-rate construction. This new contract will absorb the costs from the previous contract and its amendment, and will cover all construction activities for both ships going forward.
- In January 2020, a ceremonial keel laying for the first JSS, the future HMCS Protecteur, was held at Seaspan’s Vancouver Shipyards. During this ceremony, a newly minted coin was placed near the ship’s keel, where it will remain for the duration of the ship’s life, and is said to bring good luck for the builders and all who sail in the vessel.
- At the end of October 2020, the new bulbous bow of the first JSS arrived at Seaspan Vancouver Shipyards. Assembled by a local Canadian company, Ideal Welders, the bulbous bow is being integrated into the ongoing construction of the first JSS, and marks another exciting milestone in the construction of our future JSS.
Q13. What are the next steps for the JSS project?
A13. Construction of the JSS continues, and was able to make significant progress despite the COVID-19 pandemic. To date, more than 110 of the 123 blocks that make up the first JSS are substantially complete, with 16 of the remaining blocks under construction. The design of the remaining few blocks will be finalized and released for construction in the next few months, with the final design review expected to be completed in summer 2021.
The main engines for the JSS are expected to arrive at Seaspan’s Vancouver Shipyards in May 2021. These engines were manufactured by Mann Diesel in Augsburg, Germany, and were acquired by Seaspan through a long-lead item sub-contract. Integration of the engines into the ship blocks during will begin in summer 2021 during the “main engine load-out”. These timelines are tentative and may change as a result of the ongoing COVID-19 pandemic.
In spring 2021, we expect to take delivery of four new sea-to-shore connector systems. Manufactured by Navamar Inc. of Montreal, Quebec, these modular, self-propelled barge units will provide the JSS with an enhanced ability to transfer cargo and equipment from the ship to shore in areas with inadequate docking facilities.
Following the delivery of the JSS by Seaspan’s Vancouver Shipyards, the RCN will conduct a series of trials to confirm that the ship meets the criteria for Initial Operating Capability (IOC) and will subsequently enable Full Operational Capability (FOC). Each JSS is expected to be operational within one year of delivery to the RCN.
Q14. Why has completion of the final design review been delayed from April to summer 2021?
A14. As with any large-scale procurement project, internal project milestones are established as best estimates based on the data available at the time, and are revised as progress is made. Design work has continued since the completion of the Preliminary Design Review for the JSS project in 2017, with construction of the early blocks beginning in June 2018. While construction was able to transition from early block build to full build in summer 2021, the ongoing COVID-19 pandemic has had an impact on project timelines. As a result, the timeline for the completion of the Final Design Review is now expected to be completed in summer 2021. Building a ship is very complex – especially for a first-of-class vessel, so taking the extra time to complete design work will ensure project success. The full impacts related specifically to COVID-19 continue to be assessed, with mitigation strategies being developed to address areas such as the global supply chain and production.
Q15. What are the key features of the selected design for the future JSS?
A15. Key distinctions of the selected proven off-the-shelf design for the future JSS include the following:
- Mission versatility: The JSS will be based on an existing ship that was designed and built for operations as a support ship. It also offers mission flexibility and the ability to carry containerized payloads such as disaster relief supplies or portable headquarters modules.
- Environmental standards: The JSS will meet current and forecasted international and Canadian environmental standards in the areas of air emissions and double-hulled construction. The former Protecteur-class was single-hulled and did not meet current shipbuilding standards.
- Useable fuel: The selected design will have the ability to deliver a similar amount of useable fuel for the Task Group as the former Protecteur-class
- Helicopter: The selected design option can carry two CH-148 Cyclone helicopters.
Q15. Why are we going through a design phase if we are buying an “off-the-shelf” design, and why is it taking so long?
A15. While the ThyssenKrupp Marine Systems Canada off-the-shelf design was selected as the baseline design for the JSS, it needed to be modified to ensure the ship could be built in Seaspan’s Vancouver Shipyards production facilities. This included incorporating changes to German equipment and material in favour of a Canadian supply chain (where possible), and to meet essential Canadian requirements. Examples of these changes include adapting to Canadian and North American electrical standards, better insulation and HVAC to support Canadian climate requirements, enabling operation of a different helicopter type, and fitting the RCN self-defence weaponry and boats.
Design work is critical for ensuring that a ship is built to the required standards – especially a first of class ship – and it takes time to get it right. The first part of the design phase, the initial design review, was completed in 2017, and the final design review is expected to be completed in summer 2021.
The changes as a result of this design phase are not only supporting the production of the RCN’s new ships, but are also helping to rebuild the Canadian shipbuilding industry by creating jobs and economic prosperity for communities across the country.
Q16. How could you start construction before the ship design was finalized?
A16. The JSS project took a hybrid design-then-build approach. This means that, as the design of each block reaches a sufficient point of maturity, construction on that block can begin. So rather than waiting for the 123rd block to be designed, we’re able to begin the construction of the more simple blocks, enabling the ship to be delivered on schedule.
This hybrid design-then-build approach was particularly successful in enabling VSY to move out on the construction of simpler blocks well in advance of finalization of the full design.
This approach also allowed us to progress with the acquisition of long lead items and the planned schedule for the first ship while design work on the more complex blocks continued in parallel. This design-then-build approach is standard for all NSS shipbuilding projects, and allows for reduced risk and improved efficiency as design and construction work are able to progress at an appropriate rate.
Q16. When is the first delivery expected?
A16. Based on the February 2019 revised schedule, which include the change of sequencing of the construction of ships, the first JSS is now expected to be delivered by the shipyard in 2023. However, the ongoing COVID-19 pandemic may have impacts on these timelines.
Q17. With JSS 2 being pushed back, does this change the need for a second interim supply ship? (DND lead)
A17. No, while the interim AOR vessel is providing necessary replenishment capabilities, it cannot do what the new Protecteur-class ships are being built for. The RCN needs a ship that can conduct a full-spectrum military operations in high-threat environments.
Mitigation measures including the leasing of the interim Auxiliary Oiler Replenishment vessel and collaboration with ally countries will help support the RCN’s operations until both Joint Support Ships are delivered
Q18. How will the change in the build sequencing affect the operations of the RCN?
A18. There will be no direct change to operational schedules as the JSS have yet to be scheduled for any operations. The sequencing change strengthens the earliest possible delivery schedule for the first JSS, allowing the RCN to integrate this renewed capability back into the fleet and in service more quickly than last anticipated.
Mitigation measures will continue to be assessed to ensure the RCN has the tools it needs to do its job. The RCN has a variety of options available to ensure it will be able to deliver on the missions as laid out in Strong, Secure, Engaged.
Q19. When will the JSS actually be fully operational?
A19. Following the delivery of the JSS by Seaspan’s Vancouver Shipyards Co. Ltd, the RCN will conduct a series of trials to confirm that the ship meets the criteria for Initial Operational Capability (IOC) and subsequently to enable Full Operational Capability (FOC). Each JSS is expected to be operational within one year of its delivery to the RCN.
Ship Name
Q20. What will the future JSS be named?
A20. On September 12, 2017, the RCN announced the future JSS ships will be renamed as the Protecteur-class as a tribute to the dedication and sacrifices of the generations of sailors who have served in the past ships of the former Protecteur-class.
Q21. Weren’t the ships previously named the Queenston-class?
A21. In October 2013, the Government of Canada had announced that the JSS ships would be named the Queenston-class. Since that announcement, the original purpose-built AORs, the former HMC Ships Protecteur and Preserver, were paid off and are no longer part of the RCN’s fleet.
This fact presented the RCN, through its Ships Naming Committee, an opportunity to consider reusing the names of the original AORs, an option that was not available when the JSS were originally named in 2013.
Steel Issues
Q22. Will the Joint Support Ship being constructed be made from Canadian steel?
A22. As part of its contract with the Government of Canada, Vancouver Shipyards sources its steel through a Canadian distributor. This shipyard supplier, Samuel Custom Plate and Profiles, acquires steel from a variety of mills based on best value and availability of the types and dimensions of steel that is required. In the case of our JSS warships, we require the use of Det Norske Veritas - Germanischer Lloyd (DNV-GL) certified steel (DNV-GL being the Classification Society to which JSS is being designed and built.) This certification ensures we obtain material of the highest quality that has been manufactured under strict controls and standards.
Canadian mills have and will be considered to fulfill the requirement for the construction of the Joint Support Ships if such mills are able to provide the necessary grades, size and quantities of steel required. Algoma Steel Inc. has already won a contract for an initial supply of steel for Canada’s new Joint Support Ships. This award follows an open and competitive procurement process conducted by BC’s Samuel Custom Plate and Profiles. As parts of the Joint Support Ship are made ready for construction, new steel orders will be sent to the shipyard supplier to fulfill.
Q23. Why can’t you use Canadian steel anyway? Steel is steel, isn’t it?
A23. There are a variety of factors considered when sourcing steel for building a warship.
Considerations such as best value, certification, and the in-mill availability of steel with the required dimensions and specifications determines where it is acquired. Canadian steel is always part of the consideration.
Coast Guard Welding Issues
Q24. Given current issues with the Coast Guard’s ships, why do you believe Seaspan will be able to build the JSS correctly?
A24. First ships out of the production line often have aspects that need some refinements or adjustments, as was the case with the OFSV. We are pleased to see that issues have been actively detected and managed, and that corrections are both being made on current ships and being implemented for future builds.
Seaspan is currently implementing new initiatives that will benefit the JSS construction:
- re-writing and requalifying weld procedures to incorporate lessons from the OFSV experience;
- increasing the weld-engineering team within the shipyard and ensuring it is led by senior and qualified weld engineering staff;
- working with a new classification society to oversee the qualification of weld procedures and weld quality during JSS production;
- increasing rigour for inspection, including increasing non-destructive testing on welds; and
- establishing protocols that allows for better documenting of weld information as required by the Classification society.
We are confident in these initiatives and in our inspection process that help ensure all equipment meets our standards.
Q25. There was recently a new sequence for the construction of JSS, why is the schedule identified as having risks?
A25. The schedule indicated in the quad chart reflects the new sequence announced in February 2019 and is reflected in the updated JSS 1 planned milestones. Due to the complexity of the undertaking, risks still remain on the dates for the construction of JSS 2, as it will be dependent on both the progress of construction of JSS 1 and the Coast Guard ship construction.
Q26. The construction sequence of JSS and OOSV was recently changed because Seaspan was unable to build several vessels simultaneously. This delayed the delivery of JSS 2. With the announcement, the Seaspan shipyard will now build Multi-Purpose Vessels in addition to its current work package. How will DND ensure that the Joint Support Ships will not be further delayed?
A26. As both the engineering and production capacity of the shipyard has matured and deepened, there is growing confidence in Seaspan’s ability to manage the simultaneous design and construction of more than one class of vessel at a time. Canada will also continue to ensure that the contractor adheres to the integrated production schedule by regularly monitoring the progress of build modules through various production facilities. These numerous worksites allow the contractor to assemble several sections of different ships simultaneously. Additionally, Canada will ensure that appropriate priorities are applied to the construction of the JSS as the project progresses.
- Updated:
- April 2021
- Drafted by:
- Stephanie Poulin; ADM PA
- Consulted:
- Jacques Arsenault, JSS PCSM
- Wayne Rockwell, PM JSS
- Approved by:
- Geoff Simpson, DGMPD(Sea)
- Patrick Finn, ADM Mat
- Véronique Duhamel, DPAPI
Issue: JSS project budget update
Media Query: Produced in anticipation of media queries
Date: 15 June 2020
Overview
In October 2019, Seaspan Shipyards of Vancouver B.C., provided an updated build proposal outlining the cost to start full construction of the future Joint Support Ships (JSS). After reviewing the build proposal and overall project components, the total project budget has increased from the previous estimate of $3.4 billion to $4.1 billion, and now accounts for increased costs associated with ship production, establishing supply chains, material costs, and design work. This is the second major increase to the estimated project budget, the first occurring in 2018 when the original cost estimate rose from $2.3 billion to $3.4 billion. This estimate has been risk-adjusted based on government and industry experience to arrive at the current budget.
In February 2020, we received project implementation approval and full authorities for the current total project value of $4.1 billion. As the previous budget increase for this project received significant media and public scrutiny, it is anticipated that the latest increase will garner the same attention.
Approach: The approach is proactive. The below messaging will be used to address related media queries. A briefing with media and interested stakeholders will be proposed to provide an update and explanation on the change in project budget with participation from DND, PSPC, and ISED SMEs (TBC).
Key Messages
- New ships are necessary to maintain the capability and effectiveness of Royal Canadian Navy (RCN) operations and are an important investment into maintaining naval defence and security at home, and abroad.
- Together with the Canadian Surface Combatants and the Arctic and Offshore Patrol Ships, the Joint Support Ships (JSS) will form the core of the future RCN surface fleet, and will surpass the operational capabilities of our former auxiliary oiler replenishment vessels.
- Lessons learned from Canada’s previous shipbuilding projects have been applied to the latest contract to ensure the best value for these ships.
- A $2.4 billion contract (including taxes) was awarded to Seaspan Vancouver Shipyards on June 10, 2020 to progress with full-rate construction. 3,900 jobs will be supported annually from 2020 to 2026.
On why the cost has increased:
- As with any large-scale shipbuilding project, the final cost for a project may evolve during the design phase as construction and engineering specifications are finalized and the construction contract is negotiated.
- While the estimated cost to purchase the two JSS and initial spares is approximately $3.1 billion, there is additional production engineering work for the ships, project management and associated contingency costs, and design work,that has resulted in a total of $4.1 billion for this project.
- The refined total project budget is based on significant progress of the ship design, a thorough cost-risk analysis, and shipyard experience. We are confident this updated project budget accurately reflects the current value for the construction of these ships, as well as all the equipment, tools, and project management needed to build and bring them into service.
- While the estimated construction costs for these new ships is significant, they will provide an invaluable operational capability to the RCN, significant investments into local economies from coast to coast, and the best value to Canadians.
Note: Questions about the contract structure, the National Shipbuilding Strategy, or associated funding, should be directed to PSPC.
Questions and answers
Q1. In 2018, you said you completed a more informed cost analysis, resulting in the increase to $3.4 billion, yet the project cost is increasing again. How is it possible that you underestimated the cost twice while the Parliamentary Budget Officer successfully predicted this new cost several years ago?
A1. As with any large-scale procurement project, all project values are best estimates that are based on the data and figures available at the time. In the case of the first JSS, construction of the early build blocks was able to begin ahead of schedule in June 2018 as their design was sufficiently mature to enable production, while the design of the remainder of the ship continued to progress. We now have a better understanding of project risks, the remaining work required to build the ship, as well as the details of the associated construction contract. This has allowed us to update our total project cost estimate from $3.4 billion to $4.1 billion for the design, construction, project and contract management, and contingency costs associated with the acquisition of these ships. We will continue working closely with all our partners to actively manage and monitor this budget over the duration of the JSS project. As the cost to build a ship is based on engineering specifications, production plans, and schedules developed during the design phase, the full budget continues to be further refined as the design is finalized. As a result, it’s not uncommon for the cost estimate to change throughout the duration of a project, especially for a first-of-class ship.
If pressed about not waiting for completion of full design before announcing these changes:
Based on our latest estimates, we needed to seek additional funds for this project. These funds must be secured before a final contract is signed. In order to avoid any delays to the project, we have moved forward with securing funds based on our advanced estimates and before completion of the design work. As this has an impact on the overall project budget, updated figures are now being shared with the public.
Q2. So, the PBO was right in 2013 when they said the ships would cost $4 billion?
A2. While our current project budget is aligned with the PBO’s 2013 estimate, the figures leading to this estimate are different. We remain confident in our costing process and budget based on our latest information.
Q3. Is the cost of the project going to increase again?
A3. While we remain confident in our current project estimate, it’s possible that the figure could change in the future. As with any large-scale procurement project, all project values are best estimates that are based on the data and figures available at the time. For example, the recent COVID-19 pandemic has resulted in the weakening of the Canadian dollar, which may result in increased material and supply chain costs in the future, impacting the overall project cost. While the total project budget includes contingency funding for these types of reasons, their implications can only be addressed as they happen. As a result, it’s possible that cost estimates may change for a variety of reasons that can’t be controlled or predicted. It’s also important to note that while the construction contract may continue to be amended throughout the duration of the project, it does not necessarily mean that the project budget will increase.
Like any large-scale procurement project, the estimated project budget will remain under ongoing review, and we will continue working with all our partners to actively manage and monitor this budget over the duration of the project.
Q4. Will construction of the ship be delayed due to COVID-19?
A4. Under normal circumstances, we would expect the delivery of the first ship within three years from the start of full-rate construction. Currently, construction of the JSS continues at Seaspan Vancouver Shipyards under the health restrictions and guidelines directed by the provincial government. We will continue working closely with our partners to monitor progress. Further questions about the shipbuilder’s current operations should be directed to Seaspan.
Q5. Germany built the same ship at a much cheaper cost. Why is the cost of the JSS significantly higher than the German version?
A5. In addition to the costs required to design and build the JSS (material, equipment, labour, contingency, and project and contract management costs), our estimated project budget includes all the costs associated with bringing a ship into service. This includes spare parts, technical data, training, and many other components required to support and maintain these ships over their lifetime.
Comparatively, the cost of Germany’s Type-702 Berlin-class ship may seem significantly lower than the JSS, but it is solely for the construction of the ships and does not include all the associated project components. For example, it does not include the cost of required changes to meet current Canadian standards or costs associated with inflation as the first German ship was commissioned in 2001. As a result, it’s not a fair “apples-to- apples” comparison between the costs of the two projects as they do not include the same elements. Comparing the project budget of the JSS to other countries building supply ships presents the same problem as other countries do not calculate budgets the same way we do, where different project components may be included or excluded.
Q6. What is the estimated total cost breakdown for the JSS project over its lifetime?
A6. The contract for construction of the two JSS is currently valued at $2.4 billion. This includes the cost for construction of the early build blocks that began in June 2018, as well as ongoing construction of the ship, which will progress to full-rate construction in summer 2020. This new contract is funded out of the broader $3.1 billion budget for the construction of the two JSS and initial spares, which also includes all of the material, equipment and labour costs. The remaining design, project management and associated contingency costs for this project are valued at $1 billion. Together, this represents a total estimated project budget of $4.1 billion for acquiring two new ships and bringing them into service.
Additionally, the AJISS contract will provide in-service support for both the RCN’s Arctic and Offshore Patrol Ships (AOPS) and the Joint Support Ships for 35 years. The contract for in-service support is valued at up to $5.2 billion, and is being managed as part of a separate project.
Q7. Why are you awarding another construction contract when you already awarded one in 2018?
A7. This new contract is essentially a continuation of the first construction contract. In August 2018, an initial $66.6 million contract (including taxes) was awarded for the construction of up to 52 early blocks for the JSS. This was possible due to the maturity of the ships blocks’ design, which allowed us to progress with early construction and the acquisition of long lead items while design work on the more complex blocks continued at the same time. This contract was amended to approximately $120 million (including taxes) to sustain construction until the full-rate construction contract could be awarded. This new $2.4 billion contract (including taxes) will absorb the costs from the previous contract and its amendment, and will cover all construction activities for both ships going forward.
Q8. Why can’t you just use the MV Asterix and convert another commercial ship? It would be quicker, cheaper, and easier than building the JSS.
A8. While the MV Asterix is meeting the RCN’s short-term requirements for basic at-sea replenishment duties, it is a commercial vessel that is not built to the same standards as a military ship. As a result, it is not equipped to conduct the full spectrum of military activities required by the RCN, including those required in high-threat environments.
Additionally, as the MV Asterix is manned by a civilian crew, who has the right to refuse to undertake any missions or tasks for reasons of safety or commercial interests, the vessel may not be deployed for all missions or tasks required by the RCN. Finally, the cost of the Asterix only covers the provision of service over a limited number of years, and does not represent the cost of purchasing the ship outright.
In comparison, the JSS will be able to carry out at-sea replenishment capabilities as well as the full spectrum of military activities required for RCN operations, with a design that includes improved survivability, lifespan, and effectiveness. The JSS will also provide added flexibility and range to Canadian and allied warships in high threat environments by serving as supply vessels providing fuel, ammunition, aviation support, spare parts, food, medical and dental care, and cargo space. Together with the Canadian Surface Combatants and Arctic and Offshore Patrol Ships, the JSS will form the core of the future RCN fleet, and will provide the best value for Canadians.
Q9. Is the cost increasing because Seaspan lost money building the Coast Guard’s Offshore Fisheries Science Vessels and needs to remain profitable by building the JSS?
A9. We recognize that building ships in Canada requires significant investments into the capabilities and workforce of our shipbuilders, which is at the core of the Government of Canada’s commitment to revitalizing the industry through the National Shipbuilding Strategy (NSS). We are proud to have our new ships built in Canada and remain confident in Seaspan’s abilities to effectively and affordably deliver our new support ships.
The increased project budget is a result of a better understanding of project risks, the remaining work required to build the ship, as well as the details of the associated construction contract. We also have greater certainty in identifying what infrastructure, labour, and material is required to effectively build these ships. This includes the establishment of shipyard production norms, such as welding quality and efficiency rates, rates of construction re-work based on the lessons learned.
Note: Questions regarding the increase from $2.3 billion to $3.4 billion are answered in separate lines.
Q10. What is the impact of COVID-19 on Canada’s defence policy, Strong, Secure, Engaged?
A10. The overall impact of the pandemic on individual departments is not yet known. However, in this current context, it is now more advantageous than ever that Canada’s defence policy is based on a long-term vision and features the flexibility to respond to a changing world. We are committed to the significant and strategic long-term investments that will ensure the Canadian Armed Forces continues to function as an agile, and combat-ready force, capable of making tangible contributions and delivering on its commitments.
Q11. What’s included in the $2.4 billion contract out of the broader $3.1 billion budget for the acquisition of the JSS?
A11. The $2.4 billion (including taxes) contract awarded to Seaspan Vancouver Shipyards is primarily for the material and production effort associated with constructing the two JSS in the shipyard. This cost also includes such items as tests and trials, as well as financial incentives based on achieving predetermined milestones.
This contract also includes the cost for construction of the early build blocks that began in June 2018 and has since substantially completed work on 30 large blocks and progressed work on another 34. This has positioned Seapsan to quickly transition to a more aggressive production rate under this recently awarded contract.
The remainder of the $3.1 billion is primarily for the acquisition of the major equipment and sub-systems that must be ordered well in advance of being installed in the shipyard (known as Long Lead Items). This effort is essential in order to acquire the information necessary to advance the detailed design of JSS and also to support the shipyard’s production schedule. Seaspan is executing this work under a Long Lead Items contract which was initially awarded in December 2015 and will be completed during the construction period of the ships.
Q12. What is an "initial spare"?
A12. A number of spare parts will be delivered with each ship, to facilitate their transition to in- service support. These would include items that would normally be expected to be replaced due to regular operations within the first year or so, post-delivery. While this aspect will undergo further review as the project progresses and the list of items is refined, it would include items ranging from air filters to spare engine components.
Q13. How much of the $1 billion in supporting costs (design and production engineering, project management, contingency, etc.) has already been awarded to Seaspan?
A13. Besides the ongoing design work that is in its final stages, this component of the budget includes all of the historical costs associated with the JSS project:
- A Design and Production Engineering contract, currently valued at approximately $395 million (taxes included) was awarded to VSY in 2016 and will be finalized over the next few months.
- Earlier in the project, (2014) VSY completed an Initial Design Review contract valued at $94,400,000 (taxes included). This was a task based contract issued to review the design provided by ThyssenKrupp Marine Systems Canada and to initiate some design effort to construct the Joint Support Ship design in Vancouver Shipyards facilities.
This $1 billion (taxes excluded) also includes all costs associated with running the JSS Project Management Office, such as travel and salaries, and costs leading up to completion of options analysis.
Altogether, this represents a total estimated project budget of $4.1 billion for acquiring two new ships and bringing them into service.
- Updated:
- 15 June 2020
- Drafted by:
- Sarah Kleinhempel, Communications Advisor
- Consulted:
- Commander Bagga, COS, PMO JSS
- Jacques Arsenault, PCS, PMO JSS
- Kevin Fitzpatrick, DMEPM(NC)
- Vrenti Ghergari, DCA, ADM(Fin)
- Approved by:
- Blaine Duffley, PM, JSS
- Wayne Rockwell, DGMPD(Sea)
- Troy Crosby, ADM(Mat)
- Cheri Crosby, ADM(Fin) and CFO
- Vice-Admiral McDonald, CRCN
- Tina Raymond, A/Manager, Mat/IE PA
- Véronique Duhamel, DPAPI, A/DGPASP
- Joe De Mora, A/ADM(PA)
- MNDO
- PCO
Issue: Arctic and Offshore Patrol Ship (AOPS)
Date: April 2021
Overview
Canada is acquiring six Arctic and Offshore Patrol Ships (AOPS) for the Canadian Armed Forces (CAF).
In May 2019, the Government of Canada announced a decision to move ahead with the acquisition of a seventh and eighth AOPS, which will be modified for the Canadian Coast Guard. The construction of two additional ships will mitigate the potential production gap between the AOPS and the Canadian Surface Combatant.
Irving Shipbuilding Inc. has been contracted to build the ships. The first ship was launched in September 2018 and delivered on July 31, 2020. The second ship was launched in November 2019, and is expected to be delivered in summer 2021. The third and fourth ships are also currently in production, with construction of the fifth ship expected to begin later in 2021, however, timelines are tentative and may change as a result of the ongoing COVID-19 pandemic.
The project also includes the construction of the Nanisivik Naval Facility, a berthing and fueling facility, and the newly constructed Halifax NJ Jetty to support the AOPS. The project will also provide funding to the Esquimalt A/B Jetty project.
As this project is part of the National Shipbuilding Strategy, and due to the multiple delays and changes experienced thus far, the media remains heavily interested in this work.
Related Information
- Please refer any questions regarding the contract or procurement process to PSPC.
- Please refer any question on operations of the AOPS to the Royal Canadian Navy.
- Please refer to the AJISS lines for any information regarding in-service support.
- Please refer any questions regarding AOPS 7 and 8 to the Canadian Coast Guard.
Key Messages
- Under Canada’s defence policy, Strong, Secure, Engaged, the Government of Canada is investing in the Royal Canadian Navy (RCN) to ensure it can respond to current and future defence challenges.
- The Arctic and Offshore Patrol Ships (AOPS) will significantly enhance the CAF’s capabilities and presence in the Arctic, better enabling the RCN to assert and uphold Arctic sovereignty. The AOPS will also augment Canada’s presence on the Atlantic and Pacific oceans, and will conduct a wide variety of operations abroad.
- The first AOPS was launched in fall 2018, and was delivered to the RCN on July 31, 2020.
- Three additional ships are currently in production, with delivery of the second ship expected in summer 2021, and construction of the fifth ship is also expected to begin later in 2021.
- The AOPS represent an important investment into the future capability of the RCN, and we will take as long as needed to ensure a quality ship is delivered to meet their needs.
- The decision to build the seventh and eighth ships for the Canadian Coast Guard will help to close the production gap between the construction of the AOPS and the Canadian Surface Combatant, enabling Canada to retain highly skilled workers in the shipbuilding industry.
Questions and Answers
Cost and Schedule
Q1. What is the estimated cost breakdown for the acquisition budget?
A1. The Arctic and Offshore Patrol Ship (AOPS) acquisition budget for the Royal Canadian Navy (RCN) is $4.3 billion. This includes ship design, project management, materials and labour needed to build all the ships, jetty and fueling infrastructure, initial spare parts, technical data, crew training, and contingency costs. This budget does not include costs for the two AOPS intended for the Canadian Coast Guard (CCG).
Additionally, the AJISS contract will provide in-service support for both the RCN’s AOPS and the Joint Support Ships for 35 years, and is valued at $5.2 billion.
Q2. What is the delivery schedule for the ships?
A2. The current delivery schedule is as follows:
Ship | Planned Delivery Date |
---|---|
AOPS 1 | July 2020 – completed |
AOPS 2 | Summer 2021 |
AOPS 3 | 2022 |
AOPS 4 | 2023 |
AOPS 5 | 2024 |
AOPS 6 | 2025 |
AOPS 7 | 2026 |
AOPS 8 | 2027 |
Note all delivery dates are tentative and subject to change due to anticipated delays as a result of the ongoing COVID-19 pandemic. At this time, it is too early to determine the possible length of delays as the situation continues to evolve. An update on timelines will be provided once the full extent of COVID-related impacts are better understood and schedules are reviewed.
Q3. Will the construction of ships 6, 7, and 8 close the production gap between AOPS and CSC?
A3. The construction of a sixth AOPS for the RCN and two additional ships for the CCG was intended to help mitigate the production gap between AOPS and CSC, enabling Canada to retain highly skilled workers in the shipbuilding industry. While the ongoing COVID-19 pandemic is impacting timelines for the AOPS project, it is too early to determine how this may impact the construction of the Canadian Surface Combatant (CSC) and Canadian Coast Guard vessels. A full evaluation of potential impacts to project schedules under the National Shipbuilding Strategy will be completed once the situation has stabilized and the full extent of COVID-related impacts are better understood.
Q4. Will the ships built for the CCG be the same as the ones being built for the RCN?
A4. The ships for the RCN and the CCG will largely be the same, although there will be slight modifications to the CCG ships to support their unique operational and regulatory requirements. For example, the ships will share the same hull form and the majority of key systems. Further questions about the design of the CCG ships should be directed to the CCG.
Q5. The original delivery date for the first AOPS was spring 2018 which has been progressively delayed to spring 2020, and was then further delayed as a result of COVID-19. Why have there been so many delays and why are you incapable of providing an accurate delivery timeline? Will there be delays to the other ships?
A5. Building a new class of ships is very complex, and we acknowledge there have been delays to our original delivery timelines for the first and second AOPS. Our foremost priority is ensuring that a quality ship gets delivered to the RCN, and we will take the time needed to ensure this.
The schedules were difficult to predict mainly because the AOPS is a new design, and is being built with largely new facilities, workforces, and processes. The ship is also a complex military platform (for example, there is over 300 kilometers of cabling and various weapons systems), which makes sequencing work, anticipating potential integration issues, and forecasting schedules very challenging. Additionally, as the shipbuilder must adapt and modify several construction processes to establish the best way to build these ships, construction of a first-of-class ship will not be as efficient as the following ships.
The timelines for the first ship shifted in order to ensure required work was completed before delivery. This included completing rigorous inspections, tests and trials (including sea trials), and correcting any defects. Lessons continue to be learned from the construction of the first ship, and are benefiting the construction of the subsequent ships. However, as resources were focused on delivery of the first ship, and some inefficiencies were still being resolved, delivery of the second ship has been delayed. Unfortunately, these timelines were further delayed as a result of the ongoing COVID-19 pandemic.
Overall, the project is progressing successfully with the first ship delivered, and construction of the second AOPS progressing, with various inspections, tests, and trials concurrently underway to ensure the ship meets technical design requirements at the time of delivery in summer 2021. Despite the ongoing COVID-19 pandemic, construction of the third and fourth ships is progressing on-land, and construction of the firth ship is expected to begin later in 2021. Additionally, hundreds of new jobs have been created at the Halifax Shipyard.
Q6. What is the current status of AOPS 2?
A6. Construction of the second AOPS is progressing, with various inspections, tests, and trials concurrently underway to ensure the ship meets technical design requirements at the time of delivery. Sea trials for the ship are expected to begin in May 2021 to test the functionality of certain systems at sea. After sea trials, remaining production work will be completed, and deficiencies noted during the inspection, test, and trials program will be addressed. Following reviews and final inspections by National Defence, Irving Shipbuilding Inc. will deliver the ship.
Based on the current schedule, we expect the second AOPS, the future HMCS Margaret Brooke, to be delivered in summer 2021, noting that these timelines are tentative and may change as a result of the ongoing COVID-19 pandemic.
Upon delivery and acceptance by Canada, HMCS Margaret Brooke’s program will be similar to that of HMCS Harry DeWolf, with an anticipated twelve-week post-delivery work period that is necessary to install and set to work the ship’s communication systems, conduct physical configuration audits, and necessary preventative maintenance. Once completed, a readiness evaluation program will be conducted for a period of approximately ten days. At that point, HMCS Margaret Brooke will be considered “safe to proceed to sea,” and a basic ship readiness employment program will be executed. The RCN will then assume operational control and use of the ship. A formal commissioning ceremony is expected to occur in the summer of 2022.
Q7. How will the new schedule impact the RCN’s planned operations for these ships? (RCN Lead)
A7. As these ships have not been put into service yet and represent a new operational capability for the RCN, there are no impacts to current RCN operations. As the AOPS are delivered and transitioned into service, the RCN will incorporate them into its operational schedule, which is routinely adjusted based on fleet capacity and available resources in order to respond effectively to operational requirements.
Q8. What are the different steps in the shipbuilding process?
A8. Shipbuilding is a complex, non-linear process that includes many steps and simultaneous activities.
Generally, a ship’s construction progresses through various stages of production, with each stage resulting in a greater level of ship completion. Construction starts in Irving Shipbuilding’s Inc.’s state-of-the-art Assembly and Ultra Hall, where ship units are assembled, joined into larger blocks, and then joined together to form a mega-block. Each AOPS consists of 64 units, 21 blocks, and three mega-blocks. Once each mega- block is complete, it is then moved to the outdoor land-level production area, where the three mega-blocks are joined together to form one complete ship hull. Once the ship reaches an appropriate level of completion, it is then launched into water, where it stays for the remainder of production.
Major milestones in the construction of the AOPS include:
- the steel cutting, where full construction of the ship begins;
- moving the mega-blocks to the land-level production area;
- joining the mega-blocks;
- the ship launch, where the ship is put in water for the first time; and
- sea trials, where the ship is tested at sea.
Throughout the construction process, a testing and trials program is carried out by Irving Shipbuilding Inc. and Government of Canada representatives to ensure that design and quality requirements are being met. This program takes place starting from the steel cutting until the delivery of the ship, and includes thousands of planned verification activities. Some of these activities include inspections to verify weld quality during assembly of the ship units and blocks, as well as sea trials, where the ship is taken to sea to test various key systems before delivery to the RCN. Some ships may include a builder’s trial, where the ship is taken to sea for a first informal “test-drive” before formal sea trials begin. These will be conducted on an as-required basis.
Once the ship is complete, the Government of Canada has approved the final inspection, and all criteria laid out in the construction contract have been met, the ship will then be delivered and accepted by the RCN. It will then be moved from the Halifax Shipyard to the CFB Halifax Dockyard, where it will be berthed at the new Jetty NJ. The ship will then undergo final preparations and outfitting, including the completion of communications systems. The crew of the ship will then begin operational readiness activities and training over the following months.
During the first year after the delivery, post-delivery trials will be completed by Irving Shipbuilding Inc. to confirm final elements of the ship’s design, with the RCN operating the ship. These trials may be done concurrently with operational readiness activities.
Q9. Why was the start of construction for AOPS 5 delayed?
A9. While the steel cutting for AOPS 5 was originally delayed to allow for more focused efforts on the first four ships, the ongoing COVID-19 pandemic has resulted in additional delays to project timelines for all ships. As a result, the start of construction for the fifth ship is currently expected to begin later in 2021, noting that timelines remain tentative.
We continue to work closely with Irving Shipbuilding Inc. to mitigate potential impacts, and will provide an update on timelines once the full extent of COVID-related impacts are better understood and schedules are reviewed.
Capabilities
Q10. What kind of tasks will the AOPS be able to accomplish? (RCN Lead)
A10. The Harry DeWolf-class patrol ships’ tasks include, and are not limited to:
- conduct presence and surveillance operations throughout Canada’s waters, including in the Arctic;
- support CAF sovereignty operations;
- operate worldwide, in any non-combat zone;
- participate in a wide variety of international operations, such as anti-smuggling, anti- piracy or international security and stability;
- contribute to humanitarian assistance, emergency response and disaster relief domestically or internationally;
- conduct Search and Rescue (SAR) and provide communications relay to other units, as required;
- support CAF core missions including capacity building in support of other nations; and
- support Other Government Departments (OGD) in their ability to enforce their respective mandates.
Q11. Why are landing craft being acquired for the AOPS?
A11. To support RCN operations and activities while deployed, each AOPS will be equipped with one landing craft onboard. These landing craft were acquired as part of the AOPS project, and represent a new capability for the RCN. With a range of more than 200 nautical miles, these landing craft will be used to transfer and deploy personnel, equipment, and small vehicles such as ATVs and snowmobiles from the ship’s vehicle bay to shore. The landing craft will also be equipped with a crane to load and unload cargo, as well as equipment enabling them to deliver cargo to shore and/or connect to berthing infrastructure or deliver cargo to shore.
As the designated shipbuilder for the AOPS project, Irving Shipbuilding Inc. was responsible for selecting and awarding a subcontract to ABCO Industries Ltd. for these landing craft, which was included in the overall project budget. The informal first look of this landing craft provided to the RCN was very positive, given their potential for a wide range of capabilities to support RCN requirements.
Q12. What rescue boats will be used on the AOPS?
A12. Each AOPS will be equipped with two multi-role rescue boats. A $7.3 million sub- contract was awarded by Irving Shipbuilding Inc. to Rosborough Boats of Halifax, Nova Scotia for the acquisition of 12 Rough Water™ rescue boats. These 8.5 metre Rigid Hull Inflatable Boats (RHIB) will act as a rescue boat for marshalling and towing lifeboats, and deploying and supporting the RCN’s Enhanced Naval Boarding Party during operations. These boats are also highly adaptable and seaworthy, and can be used in multiple operating environments, including harsh sea conditions.
Q13. The Government announced in November 2018 that it will purchase a sixth ship. How will a sixth ship support the RCN?
A13. The ships are well suited to execute several essential missions assigned to the RCN, such as assisting civil authorities, law enforcement, and non-governmental partners in support of national security, responding to domestic and international emergencies, conducting search and rescue operations, and capacity building in support of Government of Canada objectives.
The acquisition of a sixth ship will also greatly increase the availability of vessels to the RCN. With six AOPS, the RCN will be able to deploy up to four AOPS simultaneously – two in the Arctic, and two available for domestic tasks (one each coast). Additionally, the great versatility of the AOPS will allow the RCN to have its combatants, the Halifax- class, and the future CSC, to focus on higher intensity operations.
Q14. How long will AOPS be able to operate in the Arctic compared to existing naval vessels? Will they be able to operate without CCG escorts? (RCN Lead)
A14. These ships will be able to sustain operations for extended periods of time, and will be capable of operating in the Arctic during the navigable Arctic season, which is between June and October.
The Nanisivik Naval Facility, the northernmost Canadian naval facility, will provide refueling and replenishing services for the vessels, helping to further extend RCN operations. Unlike the existing RCN fleet, the AOPS will be capable of operating in medium first-year ice, allowing unescorted access to portions of the Arctic that were previously inaccessible to the RCN. The AOPS will enable a greater CAF presence and operational capability in the north.
While the AOPS will be able to navigate without escorts, we will continue our close collaboration with the CCG in the development of joint operations, procedures, and patrols to ensure an optimal and effective presence in the Arctic.
Infrastructure
Q15. What jetty infrastructure is required?
A15. To ensure that we are able to berth these new ships, jetty infrastructure is being upgraded on the east and west coats, as well as in the Arctic. Construction of the new NJ jetty was successfully completed at CFB Halifax in summer 2019, and construction of the new B jetty at CFB Esquimalt is expected to be completed in 2023. Additionally, work to establish a docking, replenishing, and refuelling facility in Nanisivik, Nunavut is underway, and is expected to be operational in summer 2022.
Q16. When will construction of the Nanisivik Naval Facility be completed, and how long will it be able to operate? (IE lead)
A16. Construction work in the Arctic presents unique challenges given the climate and significant logistics planning. Work has to be planned a year ahead of time in order to get the material to this remote site, and the department counts on sea and air transport to be on time. Most recently, the COVID-19 pandemic has brought further challenges. Due to the pandemic, most of the on-site work originally scheduled for 2020 had to be postponed, which has impacted the project schedule. We now forecast the fueling facility to be completed by September 2021, with initial operational capability targeted for summer 2022. However, there remains significant schedule uncertainty due to the COVID-19 pandemic and how this may impact the 2021 construction season in the Arctic. NNF will operate during the navigable season of the year, which is approximately July through October
Steel Issues
Q17. Are the AOPS made of Canadian steel? If not, why not?
A17. The steel used for the construction of the AOPS originates from several countries, including Canada. As part of its contract with the Government of Canada, Irving Shipbuilding Inc. is responsible for the procurement of steel used for the construction of the Arctic and Offshore Patrol Ships. Irving Shipbuilding Inc. procured the majority of steel from a foreign supplier who sourced it from Europe and, to a lesser extent, from China. A small amount of steel was procured in Canada.
The Industrial and Regional Benefits Policy requires that Irving Shipbuilding Inc. invest in Canadian business activities as much value as they are receiving in the contract. This ensures a dollar-for-dollar investment into the Canadian economy and the off-setting of foreign content.
Q18. Why can’t you use Canadian steel anyway?
A18. There are a variety of factors considered by the shipyard when sourcing steel, such as: best value, delivery timelines, certification, compatibility with shipyard equipment, and whether the current availability of steel meets the required dimensions, tolerances, and specifications for the ships. The assessment and decision for procuring steel lies with the shipyard and Canadian steel would always be considered.
- Updated:
- April 2021
- Revised by:
- Sarah Kleinhempel, Communications Advisor
- Consulted:
- Cdr Guillaume Côté, PD AOPS
- Stéphane Cormier, PMO AOPS
- Jason Kaddatz, PMO AOPS
- Navy Public Affairs
- Approved by:
- Andrea Andrachuk, PM AOPS
- Wayne Rockwell, DGMPD(Sea)
- Troy Crosby, ADM(Mat)
- Tina Raymond, A/Manager, Mat/IE PA
- Véronique Duhamel, DPAPI
- Joe DeMora, DGPASP + A/ADM(PA)
AOPS 1 Delivery
Strategic Considerations
[REDACTED]
Narrative
As outlined in Canada’s defence policy, Strong, Secure, Engaged, the Government of Canada is investing in six new Arctic and Offshore Patrol Ships (AOPS) to support the current and future needs of the Royal Canadian Navy (RCN). On July 31, 2020, we formally accepted delivery of our first new AOPS, HMCS Harry DeWolf. Built by Irving Shipbuilding Inc. under the National Shipbuilding Strategy (NSS), the delivery of this new class of ship represents a historic milestone for the RCN.
These modern and multifunctional ships will be at the core of an enhanced Arctic presence, and will effectively and strategically complement the capabilities of our current and future warships through critical reconnaissance and surveillance operations. Designated the Harry DeWolf-class in honour of Vice-Admiral Harry DeWolf, a Canadian wartime naval hero, the AOPS were designed with a thick and robust hull that will allow them to operate in up to 120 cm of first-year sea ice. With its considerable space to efficiently transport cargo, the AOPS will also be able to accommodate a Cyclone helicopter as well as small vehicles, deployable boats, and cargo containers. The ship’s modern facilities include gender-inclusive washrooms, individual crew accommodations, and the flexible use of common spaces, such as the briefing room, wardroom, and boarding party room, to serve as a silent space for prayer or meditation required for various religious practices. These modern accommodations on-board the ship will significantly improve the comfort and quality of life for its crew, which underscores our commitment to improved inclusivity and well-being for our personnel.
With the ship officially delivered to the Government of Canada, it will remain berthed at NJ Jetty in the CFB Halifax Dockyard while it undergoes post-acceptance work. This post-acceptance work is a normal part of the shipbuilding process, and is used to address outstanding work including deficiencies that may have come up during formal sea trials, but were deemed acceptable to be completed after delivery. It is also used to prepare the ship and its crew for the first time a ship goes to sea under RCN command, which includes RCN sea trials to allow verification of major ship systems and overall ship performance.
The crew of HMCS Harry DeWolf began their operational readiness activities and collective training in October 2020, and successfully completed various training operations, as well as cold weather and ice trials, in Canadian waters. As this ship represents a new capability for the RCN, this period of training is required to ensure the crew is familiar with how the ship functions. To support the operationalization of this ship, Irving Shipbuilding Inc. is also conducting post- acceptance trials to verify final elements of the ship’s design while the RCN operates the ship. Following participation in the maritime portion of Operation NANOOK in August 2021, HMCS Harry DeWolf is expected to circumnavigate the Arctic throughout fall 2021.
This new class of ship is built for a real and clear purpose, and will provide the RCN with a modern, effective, and high-quality ship to patrol Canada’s three coasts. The delivery of this ship marks an exciting new chapter in Canada’s long and proud naval history, and we look forward to welcoming the first new AOPS into RCN service in summer 2021.
Questions and Answers
Q1. Will Irving Shipbuilding be charged a penalty for this late delivery?
A1. As delays to the delivery of the first ship were further impacted by the ongoing COVID- 19 pandemic and could not have been foreseen by the shipbuilder, Public Services and Procurement Canada has allowed a period of excusable delay, as outlined in the construction contract. As further details about the contract are protected by commercial confidence, we are unable to comment further on this matter.
Q2. How are timelines for the remaining ships being impacted by COVID?
A2. The ongoing COVID-19 pandemic has created an unprecedented situation. While the first ship was delivered on July 31, 2020, and the second ship is expected to be delivered in summer 2021, we are anticipating delays to the timelines for the remaining AOPS. At this time, it is too early to determine the possible length of delays as the COVID-19 situation continues to evolve. We will continue working closely with Irving Shipbuilding Inc. and our industry partners to mitigate potential impacts and continue work on the remaining ships while keeping our respective workforces safe. An update on timelines will be provided once the full extent of COVID-related impacts are better understood and schedules are reviewed.
Q3. Will delays to the AOPS result in delays to the Canadian Surface Combatant and the Canadian Coast Guard vessels?
A3. At this time, it is too early to determine how delays to the AOPS project may impact the construction of the Canadian Surface Combatant (CSC) and Canadian Coast Guard vessels. Despite the ongoing COVID-19 pandemic, progress on the CSC design has been maintained, and will continue under its current design phase. A full evaluation of potential impacts to project schedules under the NSS will be completed once the situation has stabilized and the full extent of COVID-related impacts are better understood.
Q4. The delivery of the AOPS was already delayed before COVID-19. Could these additional delays have been mitigated if you had stayed on schedule?
A4. The global COVID-19 pandemic has resulted in an unprecedented situation, and its impacts are far reaching and difficult to define at this time. While we are unable to accurately assess how COVID-19-related delays could have impacted early project timelines, public health guidance to adjust industrial operations for large-scale construction projects would have inevitably resulted in some form of delays to the project.
Q5. The original delivery date for the first AOPS was spring 2018, which was progressively delayed to spring 2020, and was then further delayed as a result of COVID-19. Why have there been so many delays and why are you incapable of providing an accurate delivery timeline?
A5. Building a new class of ships is very complex, and we acknowledge there have been delays to our original delivery timelines for the first and second AOPS. Our foremost priority is ensuring that a quality ship gets delivered to the Royal Canadian Navy, and we will take the time needed to ensure this.
The schedules were difficult to predict mainly because the AOPS is a new design, and is being built with largely new facilities, workforces, and processes. The ship is also a complex military platform (for example, there is over 300 kilometers of cabling and various weapons systems), which makes sequencing work, anticipating potential integration issues, and forecasting schedules very challenging. Additionally, as the shipbuilder must adapt and modify several construction processes to establish the best way to build these ships, construction of a first-of-class ship will not be as efficient as the following ships.
The timelines for the first ship had shifted in order to ensure required work was completed before delivery in July 2020. This included completing rigorous inspections, tests and trials (including sea trials), and correcting any defects. Lessons continue to be learned from the construction of the first ship, and are benefiting the construction of the subsequent ships. However, as resources were focused on delivery of the first ship, and some inefficiencies were still being resolved, delivery of the second ship was delayed.
Unfortunately, these timelines were further delayed as a result of the ongoing COVID-19 pandemic. We continue to work working closely with Irving Shipbuilding Inc. to mitigate potential impacts, and will provide an update on timelines once the local and global impacts of COVID-19 are better understood.
Overall, the project is progressing successfully with the first ship delivered, and construction of the second AOPS progressing, with various inspections, tests, and trials concurrently underway to ensure the ship meets technical design requirements at the time of delivery in summer 2021. Despite the ongoing COVID-19 pandemic, construction of the third and fourth ships is progressing on-land, and construction of the fifth ship is expected to begin later in 2021. Additionally, hundreds of new jobs have been created at the Halifax Shipyard.
Q6. Will work be required for the Halifax-class ships to continue their role as a result of these delays?
A6. The decision to keep the Halifax-class ships in service was made several years ago, and was not based on delays to the AOPS project. As a result, ongoing maintenance of the Halifax-class will continue to ensure the RCN has the fleet capacity required to support its operational needs until the transition to its future fleet is complete in the early 2040s.
Q7. How will delays as a result of COVID-19 impact costs?
A7. We are working through the contractual and financial implications of the COVID-19 pandemic to find resolutions that are acceptable to both Canada and suppliers, and to mitigate any budgetary and schedule impacts. At this time, it is too early to determine what impacts COVID-19-related delays may have on the project cost. However, like any large-scale procurement project, the estimated project budget will remain under close review, and we will continue working with all our partners to actively manage and monitor this budget over the duration of the project.
Q8. When will the in-service support contract for the AOPS come into effect?
A8 A long term In-Service Support contract for the Arctic and Offshore Patrol Ships and the Joint Support Ships (AJISS) was awarded to Thales Canada in 2017. Once the ship was accepted by Canada on July 31, 2020, the responsibility for the management of in- service support was assumed by Thales Canada.
Q9. When will the ship deploy to the Arctic? (RCN lead)
A9. The crew of HMCS Harry DeWolf began its Basic Single Ship Readiness Training (BSSRT) in October 2020 to to familiarize themselves with the ship and how it functions. Following this training, the ship successfully navigated the waters off the coast of Newfoundland and Labrador, and ice off the coast of Nunavut, crossing the 60th parallel, in February 2021. Cold weather and ice trials were also conducted as part of its Post Acceptance Trials program off the coast of Baffin Island. HMCS Harry DeWolf is currently scheduled to participate in the maritime portion of Operation NANOOK in August 2021, and will be followed by circumnavigating the Arctic throughout fall 2021. Further details about the ship’s deployment plans will be shared over the coming months.
Q10. When will Harry DeWolf officially enter into RCN service? (RCN lead)
A10. HMCS Harry DeWolf is expected to enter into RCN service in summer 2021 once the crew has completed all of their required operational training. This event will be marked by an official commissioning ceremony.
Q11. How will this delay impact the RCN’s planned operations for these ships (RCN lead)
A11. As these ships have not been put into service yet and represent a new operational capability for the RCN, there are no impacts to current RCN operations. As the AOPS are delivered and transitioned into service, the RCN will incorporate them into its operational schedule, which is routinely adjusted based on fleet capacity and available resources in order to respond effectively to operational requirements.
Post-Delivery Work Period
Q12. How could you accept a ship that had defects at the time of delivery?
A12. Delivery of a ship does not mean it is complete and ready to enter into service. Ship delivery occurs when the ship has reached a point of construction that meets detailed design, quality, and functionality criteria outlined in the construction contract and agreed to by Canada and the shipyard. These requirements are verified by the Government of Canada and the shipbuilder during a pre-delivery inspection.
Prior to delivery of HMCS Harry DeWolf, a number of construction deficiencies were identified and documented as part of a rigorous quality assurance program. Both the Government of Canada and the shipbuilder agreed that certain deficiencies could be corrected after delivery. Identifying and correcting some deficiencies following delivery is a normal part of the shipbuilding process – especially for a first-of-class ship – and was agreed to as it would allow the RCN to begin their training and operations.
While the shipbuilder has corrected most remaining deficiencies, a few remain to be completed during the following months. In the meantime, appropriate mitigation measures have been put in place where necessary. Following detailed assessment and review of all deficiencies, HMCS Harry DeWolf has been deemed as safe to proceed to sea.
If pressed on whether the ship is safe for sea:
We take the safety and security of our sailors very seriously, and no ship will go to sea if any potential safety risks are identified. We will continue to monitor the state of the ship, and are taking the appropriate actions to ensure both the safety of our sailors and the operational capability of the ship.
Q13. Why is post-delivery work needed?
A13. Besides rectifying deficiencies, other post-acceptance work was always planned for the AOPS in order to finalize construction and operationalize the platform. During this stage, the ship has and will continue to undergo final preparations, including the outfitting and integration of onboard systems to meet RCN operational requirements. As this type of work involves sensitive or classified information, or trade-specific expertise, it can only be completed by the RCN once it has been delivered.
As the Harry DeWolf-class represents a new capability for the RCN, these work periods will also be used to prepare the ship and its crew for the first time it goes to sea under RCN command. During the first year after delivery, post-acceptance trials will be completed by Irving Shipbuilding Inc. to confirm final elements of the ship’s design while the RCN operates the ship. These trials may be done concurrently with operational readiness activities.
Q14. What work has been done on the ship since delivery?
A14. Since the delivery of HMCS Harry DeWolf, over the fall of 2020, the ship’s crew and Thales Canada Inc. have equipped the ship, familiarized themselves with the systems, conducting maintenance, and generally prepared to operate and support the ship. These activities were performed to ensure the ship was safe and ready for RCN sea training.
The first short work period for HMCS Harry DeWolf began on November 30, 2020, and was completed on February 5, 2021. During this work period, Thales Canada, the in- service support contractor, conducted additional corrective and preventative maintenance. A few engineering changes were also incorporated by various organizations, and the shipbuilder, Irving Shipbuilding Inc., corrected outstanding deficiencies and warranty work
The ship underwent a second short work period from the period of March 8 to April 1, 2021.
The work conducted during these periods is a result of strong collaboration between the in-service support contractor, Thales Canada, the shipbuilder, Irving Shipbuilding Inc., RCN and DND Fleet Maintenance Facility (FMF) crews, and other Government of Canada stakeholders.
Q15. Will further work be required?
A15. Similar to a car, ongoing work will be required to ensure the ship remains safe and effective to support operations.
An additional short work period is scheduled for HMCS Harry DeWolf from July 5th to August 2, 2021, prior to its planned Arctic deployment. Outstanding work from the shipbuilding contract will also continue, and will ensure the ship fully meets its operational and technical requirements. This includes the finalization of outstanding deficiencies and warranty items, inspections, post-acceptance trials, change requests, validation of the ship’s technical requirements, approval of change requests, and the analysis of various technical and program documentation.
Q16. What new deficiencies or issues have been identified since the ship was delivered?
A16. During readiness at sea training in October 2020, a few new technical issues arose. This included:
- Issues with the military communications systems. While the crew was able to communicate ashore using wireless communication systems, the issue was resolved while the ship was alongside and sufficient military communications were returned. The plan was always to complete the assembly and set-up of communications systems after the ship had been delivered, since the majority of that work is not completed by the shipbuilder. While most issues have been resolved and the communications systems are currently functional, final work and testing of the systems functionality is expected to be completed by the end of July 2021.
- Issues with the ability to produce freshwater. This system was repaired and returned to service overnight.
- Mechanical issues with the Main Diesel Generator (MDG) cooling systems. Two of the four generators had a mechanical seal fail for their high temperature coolant pumps. The ship has four MDG that provide electrical power and ship propulsion. System redundancy is part of the Harry DeWolf-class design – all generators do not need to be operating for the ship to remain operational. The two pumps that failed were changed out and the system deemed serviceable. There was also a minor leak in one of the fuel return lines of a MDG, which was repaired. These issues did not pose a safety risk to either the crew or the ship, nor does it create risk of damage to or jeopardize the future operation of the MDG system. While the crew was able to resume normal operations, the cause of this issue is still under investigation, and various corrective actions are underway. DND and RCN personnel, in coordination with the shipbuilder and MDG Original Equipment Manufacturer, continue to work together to fully understand the causes of this issue and will make further adjustments as necessary to ensure the systems perform at full capacity.
- Following these issues being addressed, HDW returned to sea after one day alongside to continue progressing their Basic Single Ship Readiness Training (BSSRT) program. It’s important to note that issues of this nature are to be expected and are part of the process, especially a first-of-class ship.
- Any further deficiencies noted during operations and training, will be addressed either by coming alongside (as was the case in October) or where possible, by waiting for a convenient opportunity such as the next work period. Lessons learned from this corrective work are also being incorporated into the build and testing of the subsequent AOPS, helping to mitigate similar issues in the future.
Quick Facts (Background Information)
- The AOPS project will provide the RCN with six new ice-capable patrol ships, as well as two variants for the Canadian Coast Guard.
- The AOPS will operate in the Arctic between July and October, providing a greater and longer CAF presence in the north. They will also support a range of domestic and international operations including anti-piracy, emergency response, and disaster relief.
- The project is valued at $4.3 billion, and falls under SSE initiative #30.
- The ships are being built under the National Shipbuilding Strategy by Irving Shipbuilding Inc. in Halifax, Nova Scotia.
- Construction of the first ship, HMCS Harry DeWolf began in 2015, and was delivered to Canada on July 31, 2020.
- Following delivery, the ship will continue to undergo work, tests, and trials to finalize construction and operationalize the platform before it enters into RCN service in summer 2021. The second ship is expected to be delivered in summer 2021, although timelines remain tentative given the ongoing COVID-19 pandemic.
- Three ships are currently in various stages of production, with the start of construction for the fifth ship expected to begin later in 2021.
- Due to the ongoing COVID-19 pandemic, construction timelines for the remaining ships are currently delayed by a minimum of 6-9 months. Timelines will be reassessed and updated once the impacts of COVID-19 are better understood.
- Update:
- April 2021
- Drafted by:
- Sarah Kleinhempel, A/Senior Communications Advisor, Mat PA
- Consulted:
- Karen Watson, AJISS PM
- Kevin Fitzpatrick, DMEPM(NC)
- Approved by:
- Andrea Andrachuk, PM, AOPS
- Wayne Rockwell, DGMPD(Sea)
- Cmdre Carosielli, DGMEPM
- Troy Crosby, ADM(Mat)
- Tina Raymond, Manager, Mat PA
- Veronique Duhamel, DPAPI/DGPASP
- Joe De Mora, A/ADM(PA)
- MNDO
- PCO
Page details
- Date modified: