Archived: Departmental Performance Report supplemental tables 2013-14, Environment Canada, chapter 5


Status Report on Projects Operating with Specific Treasury Board Approval

Program - Weather and Environmental Services for Canadians
Project Original
estimated
total cost
($ millions)
Revised
estimated
total cost
($ millions)
Actual
cost total
($ millions)
2013-14
Main
estimates
($ millions)
2013-14
Planned
spending
($ millions)
2013-14
Total
authorities
($ millions)
2013-14
Actual
($ millions)
Expected
date of
close-out
Uninterruptible power supply (UPS) replacement - Dorval facility (effective project approval) (project implementation phase) 10.6 15.4 1.9 0.1 0.1 0.1 0.1 Project is complete