Federal contaminated sites annual report 2019-2020

Executive summary

Scattered across Canada are thousands of contaminated sites: dumps, mines, abandoned industrial and military operations, stored or spilled fuel or toxic chemicals, among others. Many of these occurred because individuals, businesses, and sometimes even government did not understand the long-term effects of their presence on the environment or on the health of future generations. Some are the legacy of accidents.

Federal contaminated sites are located on land or in aquatic areas owned or leased by the federal government, or where the federal government has accepted responsibility for the contamination. Growing awareness of the need for long-term stewardship of the environment led to the establishment of the Federal Contaminated Sites Action Plan (FCSAP).

Established by the Government of Canada in 2005, FCSAP provides funding to federal departments, agencies and consolidated Crown corporations (referred to as custodians) to manage the contaminated sites they are responsible for. The first three phases of FCSAP ran for 15 years, from 2005 to 2019, with total federal funding of $4.54 billion. In 2019, FCSAP was renewed for another 15 years (2020 to 2034), with $1.16 billion announced in Budget 2019 for Phase IV (2020 to 2024).

This report describes the progress made in 2019–2020, the last year of Phase III of FCSAP.

Why have an action plan to address federal contaminated sites?

The main objective of FCSAP is to reduce environmental and human-health risks from known federal contaminated sites, along with the related financial liabilities. The program also helps Canadians, communities and businesses, as FCSAP funds projects that:

FCSAP spending in 2019–2020

Nationally in 2019–2020, federal departments, agencies and consolidated Crown corporations involved in FCSAP reported total expenditures of $411.1 million, including the FCSAP funding and the custodian cost share. (Figure 1).

Figure 1: Distribution of expenditures in 2019–2020

Figure 1: Distribution of expenditures in 2019–2020
Long description

This figure shows the distribution of expenditures in 2019–2020. Total expenditures were $411.1 million. Expenditures for program management were $19.9 million, which represented 5% of total expenditures. Expenditures for assessment were $2.7 million, which represented 1% of total expenditures. Expenditures for remediation were $388.5 million, which represented 94% of total expenditures.

Key results

Reporting the results federally

Every year, the main results of the FCSAP program, including expenditures and site status, are reported in the Federal Contaminated Sites Inventory (FCSI), which is maintained by the Treasury Board of Canada Secretariat. At the end of 2019–2020, the FCSI listed 23,714 sites, of which 1,795 are suspected sites, 4,860 sites are being assessed or remediated and 17,059 sites are closed and require no further action.

FCSAP has been the main source of funding for federal contaminated site management, covering about 80% of all site expenditures reported in the FCSI since 2005–2006.

In 2019–2020, about 65% of expenditures reported to the FCSI were attributable to FCSAP sites, which included both FCSAP funding and the custodian cost share. The remaining 35% was for expenditures on non-FCSAP sites and federal organizations that are not part of FCSAP. 

Liability

Contamination of federal sites may translate into liability for the Government of Canada. In 2019–2020, contaminated sites that may be eligible for FCSAP funding accounted for $6.450 billion of the Government of Canada's total 2019–2020 liability for contaminated sites.

Liability is an estimate. The total amount can change because of economic forces such as inflation or changes in project costs. It can also change for specific sites – for example, when an assessment discovers unexpected contamination, or determines that the site does not pose a risk.

Remediation expenditures in 2019–2020 associated with FCSAP reduced the liability by $377 million, but this was offset by $1.396 billion of financial and project-cost adjustments.

Contact

For questions or comments on this report, contact:

FCSAP Secretariat
Contaminated Sites Division
Environmental Protection Operations Directorate
Environment and Climate Change Canada
351 St. Joseph Boulevard, 17th Floor
Gatineau QC  K1A 0H3
Email: FCSAP.PASCF@ec.gc.ca

Abbreviations and acronyms

AAFC
Agriculture and Agri-Food Canada
CCME
Canadian Council of Ministers of the Environment
CIRNAC
Crown-Indigenous Relations and Northern Affairs Canada
CSC
Correctional Service of Canada
DFO
Fisheries and Oceans Canada
DND
Department of National Defence
ECCC
Environment and Climate Change Canada
FCSAP
Federal Contaminated Sites Action Plan
FCSI
Federal Contaminated Sites Inventory
ISC
Indigenous Services Canada
JCCBI
Jacques Cartier and Champlain Bridges Incorporated
NCC
National Capital Commission
NRC
National Research Council of Canada
NRCan
Natural Resources Canada
PCA
Parks Canada Agency
PSPC
Public Services and Procurement Canada
TBS
Treasury Board of Canada Secretariat
TC
Transport Canada

Glossary

Agencies
A government agency is a permanent or semi-permanent organization in the machinery of government that is responsible for the oversight and administration of specific functions, such as Parks Canada. There are a notable variety of types of agencies. Although usage differs, a government agency is normally distinct both from a Department or Ministry, and other types of public bodies established by government. The functions of an agency are normally executive in character, since different types of organizations (such as commissions) are normally used for advisory functions. The autonomy, independence and accountability of government agencies also vary widely. For a listing of Separate Agencies refer to Schedule V of the Financial Administration Act.
Contaminated Site
According to the Treasury Board Policy on Management of Real Property, a contaminated site is “a site at which substances occur at concentrations that: (1) are above background levels and pose, or are likely to pose, an immediate or long-term hazard to human health or the environment, or (2) exceed the levels specified in policies and regulations.”
Consolidated Crown Corporations
Corporations that rely on the Government for most of their financing and are controlled by the Government. Each consolidated Crown corporation is accountable to Parliament through a responsible minister. The number of consolidated Crown corporations can vary from year to year, however a listing can be found in the Public Accounts of Canada. For example refer to Volume 1, Section 4 – Consolidated Accounts of the 2019-2020 Public Accounts of Canada.
Cost Share
FCSAP funding is based on the “polluter pays” principle, which means that those who created the environmental liability are responsible for the costs of the clean-up. Specifically, custodians are responsible for paying 20% of assessment costs and 15% of remediation costs for their contaminated sites, unless the project’s value is $90 million or higher, in which case cost-share for remediation is waived.
Department
The legal definition of a department can be found in the Financial Administration Act (FAA), and includes departments named in Schedule I and I.1 of the FAA, and departmental corporations named in Schedule II of the FAA.
Enterprise Crown Corporation
A corporation that is not dependent on parliamentary appropriations and whose principal activity and source of revenues are the sale of goods and/or services to outside parties. Each enterprise Crown corporation is accountable to Parliament through the responsible minister.
Federal Contaminated Site
Contaminated sites that are located on land or in aquatic areas owned or leased by the federal government, or where the federal government has accepted responsibility for the contamination.
Federal Contaminated Sites Action Plan (FCSAP)
FCSAP is a program established by the Government of Canada that provides funding to federal departments, agencies and consolidated Crown corporations (referred to as custodians) to manage the contaminated sites they are responsible for. The primary objective is to reduce environmental and human-health risks from known federal contaminated sites and their related financial liabilities.
Federal Contaminated Sites Inventory
The Federal Contaminated Sites Inventory is a database with information on all known federal contaminated sites under the custodianship of departments, agencies and consolidated Crown corporations as well as those that are being or have been investigated to determine whether they have contamination arising from past use that could pose a risk to human health or the environment. The inventory also includes non-federal contaminated sites for which the Government of Canada has accepted some or all financial responsibility. 
Federal 10-Step Process
A risk-based approach to contaminated sites management that incorporates several components including site identification and characterization, detailed site investigations and risk assessment, evaluation of different risk management strategies, implementation of a selected management strategy, assessment and monitoring. These components are realized through a 10-step process identified in the Federal Approach to Contaminated Sites, fully detailed in the Federal Contaminated Sites Decision-making Framework. These steps identify scientific tools and documents that are available for use in the management of federal contaminated sites.
Liability
Environmental liabilities are the estimated remaining costs related to the remediation/risk management of contaminated sites. Specifically, where the Government of Canada is obligated, or will likely be obligated, to incur such costs. Liabilities are recorded annually in the Public Accounts of Canada.
Long-Term Monitoring
Periodic inspections, which may include sampling and analyses, undertaken as part of a comprehensive site-specific risk management strategy to ensure that risk management objectives are maintained.
“Polluter Pays” Principle
In Canada, the federal government promotes the “polluter pays” principle: the party responsible for producing pollution should be responsible for paying for damage to the natural environment. Private companies are usually responsible for the costs to clean up (or remediate) the land they contaminate. The provinces, territories and federal government are generally responsible for the costs of dealing with contamination at the sites they own or lease.
Remediation
The improvement of a contaminated site to prevent, minimize or mitigate damage to human health or the environment. Remediation involves the development and application of a planned approach that reduces the exposure of receptors to contaminants of concern. Remediation typically involves removing, destroying or containing contaminants from a site through on-site treatment or off-site disposal.
Remediation Liability
Remediation liabilities are the estimated future costs associated with cleaning up (remediating) federal contaminated sites to ensure that the environment and human health are protected. Specifically, where the Government of Canada is obligated, or will likely be obligated, to incur such costs. Liabilities are recorded annually in the Public Accounts of Canada.
Risk Management
The selection and implementation of a risk-control strategy, followed by monitoring and evaluating the effectiveness of that strategy. Risk management includes strategies that reduce the probability, intensity, frequency or duration of the exposure to contamination. It typically involves managing contaminants in place, using covers and/or administrative controls to block the exposure pathways identified as causing a potential risk.
Site Assessment
A site assessment involves detailed scientific and/or engineering analysis to identify the nature and extent of the contamination. This helps determine the risks to human health and the environment. A full-scale assessment of the severity of contamination for a specific site is a lengthy and complex process (see the federal 10-step process). By assessing contaminated sites, the federal government is able to develop a more accurate estimate of the level of the financial liability it faces.

1. Introduction

Established by the Government of Canada in 2005, FCSAP provides funding to federal departments, agencies and consolidated Crown corporations (referred to as custodians) to manage the contaminated sites they are responsible for. The first three phases of FCSAP ran for 15 years, from 2005 to 2019, with total federal funding of $4.54 billion. In 2019, FCSAP was renewed for another 15 years (2020 to 2034), with $1.16 billion announced in Budget 2019 for Phase IV (2020 to 2024). This report describes the progress made in 2019–2020, the last year of Phase III of FCSAP.

Program objectives

The main objective of FCSAP is to reduce: 1) environmental and human-health risks from known federal contaminated sites and 2) their related financial liabilities. The program also provides socio-economic benefits by supporting brownfield redevelopment, promoting innovative and sustainable remediation technologies, and creating or maintaining jobs and training opportunities in the Canadian environmental remediation industry. These jobs and training opportunities extend to Indigenous people and those living in rural areas.

What is a contaminated site?

According to the Treasury Board Policy on Management of Real Property, a contaminated site is “a site at which substances occur at concentrations that: (1) are above background levels and pose, or are likely to pose, an immediate or long-term hazard to human health or the environment, or (2) exceed the levels specified in policies and regulations.”

Federal contaminated sites are located on land or in aquatic areas owned or leased by the federal government, or where the federal government has accepted responsibility for the contamination. The size and scope of federal contaminated sites vary greatly and include, for example, abandoned mines on Crown land in the north, airports, lighthouse stations, and military bases. Contamination is most often a result of past activities with environmental consequences that were not well understood at the time.

Cleaning up – for now and the future

The Government of Canada has taken action through FCSAP and remains committed to properly managing the contaminated sites for which it is responsible. Canada now has policies and legislation to prevent future contamination of sites. There is also a much better understanding of the effects of government, commercial, and industrial operations on the environment, and of the means to prevent and remediate contamination – as well as a better public appreciation of the need to respect the environment. Federal custodians are responsible for making their operations environmentally sustainable, to protect and safeguard the health of future generations and the environment.

FCSAP also contributes to a global effort to better respect the environment. As part of its Departmental Sustainable Development Strategy, Environment and Climate Change Canada has linked FCSAP to Target 12.4 of the United Nations’ Sustainable Development Goal 12: Responsible Consumption and Production: “By 2020, achieve the environmentally sound management of chemicals and all wastes throughout their life cycle, in accordance with agreed international frameworks, and significantly reduce their release to air, water and soil in order to minimize their adverse impacts on human health and the environment”.

In Canada, the federal government promotes the “polluter pays” principle: the party responsible for producing pollution should be responsible for paying for damage to the natural environment. Private companies are usually responsible for the costs to clean up (or remediate) the land they contaminate. The provinces, territories and federal government are generally responsible for the costs of dealing with contamination at the sites they own or lease.

2. FCSAP funding and activities

Six phases of the Federal Contaminated Sites Action Plan (FCSAP) have been approved so far. Each phase builds on the progress achieved in previous phases.  

Who pays for the program?

The program is based on the “Polluter pays” principle and follows a cost-shared approach where FCSAP provides a portion of the funding and custodians provide the remainder of the funding (known as cost share).

Eligibility

FCSAP provides funding for the assessment and remediation of contaminated sites that federal custodians are responsible for. The program covers only sites that were contaminated by historical activities – that is, the contamination had to occur before April 1, 1998.

In Phase III, FCSAP funded assessment to allow custodians to determine whether a suspected site is contaminated and whether remediation or risk-management activities are required.

Custodians used the CCME National Classification System for Contaminated Sites (PDF; 995.7 kB) and the Aquatic Sites Classification System developed by FCSAP, depending on whether they are on land or water, to classify and prioritize their contaminated sites activities.

In Phase III, FCSAP funded the remediation of two classes of sites:

Treasury Board approves the allocation of FCSAP funding on the basis of federal custodians’ planned assessment and remediation activities.

Federal custodians are accountable for the FCSAP funding they receive. They must ensure that their sites meet funding-eligibility requirements and are managed in accordance to the Treasury Board Policy on Management of Real Property. Custodians must have grounds to suspect that a site is contaminated (normally because of past activities at the site) before environmental site-assessment activities can be funded. Custodians must prioritize which sites they will work on each year, because funds and resources might not be available to assess or remediate all their sites. The FCSAP Secretariat has developed guidance to ensure that custodians spend their funding on eligible assessment and remediation activities.

Key roles

The main players in the program are custodians, FCSAP Secretariat, Treasury Board of Canada Secretariat, and expert support departments:

Custodians

Federal departments, agencies and consolidated Crown corporations responsible for the assessment and remediation of federal contaminated sites

FCSAP Secretariat and Treasury Board of Canada Secretariat

Provide administration, oversight, guidance and support to custodians

Expert support departments

Provide expert advice and technical assistance to custodians, develop guidance documents, deliver training, and promote innovative and sustainable remediation technologies

Several other players have unique roles in the program:

A common approach

To ensure that custodians take a common approach to managing federal contaminated sites, FCSAP has embraced the 10-step process identified in the Federal Approach to Contaminated Sites, fully detailed in the Federal Contaminated Sites Decision-making Framework:

Step 1: Identify suspected sites – Identify potentially contaminated sites on the basis of past or current activities on or near the site.

Step 2: Historical review – Assemble and review all historical information pertaining to the site

Step 3: Initial testing program – Provide a preliminary characterization of contamination and site conditions.

Step 4: Classify contaminated site, using the Canadian Council of Ministers of the Environment (CCME) National Classification System – Prioritize the site for future investigations and remediation or risk-management actions.

Step 5: Detailed testing program – Focus on specific areas of concern identified in step 3 and provide further in-depth investigations and analysis.

Step 6: Reclassify the site, using the CCME National Classification System – Update the ranking in response to the results of the detailed investigations.

Step 7: Develop remediation and risk-management strategy – Develop a site-specific plan to address contamination issues.

Step 8: Implement remediation and risk-management strategy – Implement the site-specific plan that addresses contamination issues.

Step 9: Confirmatory sampling and final reporting – Verify and document the success of the remediation and risk-management strategy.

Step 10: Long-term monitoring – If required, conduct long-term monitoring to ensure that remediation and long-term risk-management goals are achieved.

3. Program results (2019–2020)

Thirteen custodians conducted assessment and remediation activities in the 2019–2020 fiscal yearFootnote 1 and reported on the progress they made at their contaminated sites throughout the year. Their results are brought together in this report to determine how the Federal Contaminated Sites Action Plan (FCSAP) as a whole is performing. Results from these activities were compared against performance measurement targets established for Phase III of FCSAP.

The activities fell into four key program areas:

  1. program management
  2. assessment,
  3. risk reduction, and
  4. liability reduction.

Key results

Each of the following program results for 2019–2020 is further detailed in this section:

3.1 Program management

Program management funding is used to pay for employee salaries and for activities such as program administration, procurement and contract management, and activities related to program planning and reporting. It also allows four expert support departments (Environment and Climate Change Canada, Fisheries and Oceans Canada, Health Canada and Public Services and Procurement Canada) to provide expert advice and technical assistance to custodians in support of the program. See Appendix A for more information on program management activities conducted in 2019–2020.

3.2 Assessment

Custodians may suspect a site of being contaminated as a result of past activities – for example, in places where fuel-storage tanks may have leaked. In such cases, custodians would conduct an environmental site assessment to determine the nature and extent of contamination. An assessment determines whether remediation or risk-management activities would be needed.

An environmental site assessment may involve the collection and analysis of samples to determine levels of contamination. These levels are compared with environmental quality guidelines on the management of contaminants in soils, sediments, freshwater and marine water, as published by the Canadian Council of Ministers of the Environment (CCME). Federal contaminated sites are classified and prioritized in accordance with the CCME National Classification System for Contaminated Sites (PDF; 995.7 kB) and the Aquatic Sites Classification System developed by FCSAP, depending on whether they are on land or water.

In 2019–2020, FCSAP funded assessment activities on 97 sites at a program cost of $2.1 million. An additional $0.6 million was spent as part of the custodian cost-share requirement.

Of the 97 sites where assessments took place in 2019–2020, 12 sites will require remediation or risk management, 12 sites required no further action and 73 sites required further assessment (Figure 2). Assessing a site can take a few months or even a few years – depending on the type and extent of the contamination, scientific knowledge of the contamination, location of the site, and weather conditions.

Figure 2: Results of assessments in 2019–2020

Figure 2: Results of assessments in 2019–2020
Long description

This figure shows the results of assessments in 2019–2020: 12 sites required no further action, 12 sites required remediation/risk management and 73 sites required further assessment.

Indigenous Services Canada (ISC) and the National Capital Commission (NCC) conducted 80% (78 of 97) of all FCSAP-funded site assessments in 2019–2020. The custodians that spent the most on assessments were ISC and the Department of National Defence (DND). These two custodians spent 62% ($1.3 million of $2.1 million) of the FCSAP assessment expenditures reported in 2019–2020. Table B.1 in Appendix B provides a detailed breakdown of the number of sites with assessment activity, assessment funding available and assessment expenditures for each custodian.

Regionally, the largest FCSAP assessment expenditures were in Ontario and Manitoba, accounting for 81% of the total (Figure 3). The provinces with the largest numbers of sites with assessment activity were also Ontario and Manitoba, with 85% of the total.

Figure 3: Distribution of FCSAP assessment expenditures and sites, by province and territory, 2019–2020

Figure 3: Distribution of FCSAP assessment expenditures and sites, by province and territory, 2019–2020
Long description

This figure shows the distribution of FCSAP assessment expenditures and the number of sites, by province and territory, in 2019–2020.

Alberta: $0.01 million of FCSAP assessment expenditures for 1 site

British Columbia: $0.1 million of FCSAP assessment expenditures for 3 sites

Manitoba: $0.3 million of FCSAP assessment expenditures for 15 sites

New Brunswick: $0.08 million of FCSAP assessment expenditures for 1 site

Newfoundland and Labrador: $0 of FCSAP assessment expenditures for 0 sites

Northwest Territories: $0 of FCSAP assessment expenditures for 0 sites

Nova Scotia: $0.04 million of FCSAP assessment expenditures for 1 site

Nunavut: $0.08 million of FCSAP assessment expenditures for 2 sites

Ontario: $1.4 million of FCSAP assessment expenditures for 67 sites

Prince Edward Island: $0 of FCSAP assessment expenditures for 0 sites

Quebec: $0.1 million of FCSAP assessment expenditures for 7 sites

Saskatchewan: $0 of FCSAP assessment expenditures for 0 sites

Yukon: $0 of FCSAP assessment expenditures for 0 sites

3.3 Reduction of risks to human health and the environment

Completed site-assessment activities determine whether the risks to human health or the environment are within established limits for contaminants. If not, custodians may then conduct risk-reduction activities (remediation and risk management) at these sites. The methods used to address the contamination at each site depend on their efficacy, cost and the unique circumstances of the site.

In 2019–2020, FCSAP funded risk-reduction activities at 388 sites, at a program cost of $358.2 million. An additional $30.3 million was spent as part of the custodian cost-share requirement. Risk-reduction activities were completed at 23 sites.

Three custodians (DND, the Department of Fisheries and Oceans and ISC) worked on approximately 60% of the FCSAP-funded remediation sites (228 of 388) in 2019–2020. Table B.2 in Appendix B provides a detailed breakdown of the number of sites with remediation activity, remediation funding available and remediation expenditures for each custodian.

Two custodians accounted for 71% of the FCSAP remediation expenditures ($253 million of $358 million) reported in 2019–2020: Crown-Indigenous Relations and Northern Affairs Canada (CIRNAC) spent $176 million and DND spent $77 million.

Both of these custodians worked on the remediation of large, complex and remote sites. These two custodians spent 54% of the total of $358 million in 2019–2020 FCSAP remediation expenditures at three projects:

Table B.5 in Appendix B provides a complete list of sites with FCSAP remediation expenditures in 2019–2020. Updates on all three projects are provided in Section 8 along with other priority projects.

Regionally, the largest FCSAP remediation expenditures were in British Columbia, Northwest Territories and Yukon, accounting for 79% of the total (Figure 4). The provinces with the largest numbers of sites with remediation activity were Ontario, British Columbia and Quebec (59% of the total).

Figure 4: Distribution of FCSAP remediation expenditures and sites, by province and territory, 2019–2020

Figure 4: Distribution of FCSAP remediation expenditures and sites, by province and territory, 2019–2020
Long description

This figure shows the distribution of FCSAP remediation expenditures and the number of sites, by province and territory, in 2019–2020.

Alberta: $2.4 million of FCSAP remediation expenditures for 13 sites

British Columbia: $100.4 million of FCSAP remediation expenditures for 87 sites

Manitoba: $2.1 million of FCSAP remediation expenditures for 8 sites

New Brunswick: $0.05 million of FCSAP remediation expenditures for 4 sites

Newfoundland and Labrador: $12.9 million of FCSAP remediation expenditures for 34 sites

Northwest Territories: $72.8 million of FCSAP remediation expenditures for 31 sites

Nova Scotia: $1.2 million of FCSAP remediation expenditures for 18 sites

Nunavut: $13.8 million of FCSAP remediation expenditures for 32 sites

Ontario: $24.2 million of FCSAP remediation expenditures for 94 sites

Prince Edward Island: $0 of FCSAP remediation expenditures for 0 sites

Quebec: $14.2 million of FCSAP remediation expenditures for 47 sites

Saskatchewan: $5.7 million of FCSAP remediation expenditures for 3 sites

Yukon: $108.5 million of FCSAP remediation expenditures for 17 sites

3.4 Liability reduction

Remediation liabilities are the estimated future costs associated with cleaning up (remediating) federal contaminated sites to ensure that the environment and human health are protected. Liabilities are recorded annually in the Public Accounts of Canada.

Liability increases and decreases

Liabilities for a given site are usually first reported once an assessment determines that remediation work will be needed. As custodians remediate contaminated sites, the liabilities generally go down, as the remaining risks to people and the environment are reduced or eliminated. However, other factors can change the liability amounts:

Liability reduction is not linear: a decrease in liability in one year may be followed by an increase in the next year.

Total liability vs. liability for FCSAP-funded sites

FCSAP provides funding for only part of the sites that make up the total remediation liability reported in the Public Accounts of Canada. Custodians and other federal organizations also conduct work at contaminated sites that are not eligible for FCSAP funding. Regardless of the funding source, organizations are required to report all remediation expenditures and liabilities to the Public Accounts of Canada. Examples of sites that are not eligible for FCSAP funding in Phase III included:

From March 31, 2019 to March 31, 2020, the total liability for the remediation of contaminated sites, as reported in the Public Accounts of Canada (by twenty-one federal organizations, including FCSAP custodians), increased by $894 million, from $6.455 billion to $7.349 billion. Sites that may be eligible for FCSAP funding accounted for $6.450 billion of the total 2019–2020 liability reported.

The Public Accounts of Canada showed that remediation expenditures reduced the environmental liability by $585 million, of which $377 million was FCSAP.

However, these reductions were offset by $1.428 billion in changes to estimated remediation costs and $54 million in new liability for sites not previously recorded.

A $2.5 million adjustment in expected recoveries was also reported in 2019–2020. An expected recovery is reported when it is likely that a recovery will be received by the Crown and a reasonable estimate of the amount of the recovery can be made. As detailed in Table C.1 in Appendix C, these were factors in the $894 million net increase in liability.

FCSAP funded sites

There were 15 custodians responsible for the portion of remediation liability associated with federal contaminated sites that may be eligible for FCSAP. Two custodians (NRC and VIA Rail) did not report any FCSAP expenditures in 2019–2020, but their liabilities were included in the amount associated with FCSAP-eligible sites. The overall increase in liability by $1.082 billion from $5.368 billion to $6.450 billion during the 2019–2020 fiscal year was mainly due to revised cost estimates, new liability for sites not previously recorded and adjustments for inflation. A more accurate estimate of the impact of FCSAP on the Government of Canada’s total liability can be found in Table C.2 and C.3 in Appendix C, which indicate that the remediation liability associated with federal contaminated sites that may be eligible for FCSAP funding is estimated to be $6.450 billion.

Of the 15 custodians responsible for the portion of remediation liability associated with federal contaminated sites that may be eligible for FCSAP, 11 custodians reported increases in liability in 2019–2020, totalling $1.095 billion. The custodian with the largest increase in liability was CIRNAC, which reported an increase in liability of $589 million. This increase was mainly due to revised cost estimates, adjustments for inflation and net present value calculations. ISC also reported an increase in liability of $379 million. These two custodians accounted for 88% of the $1.095 billion increase in liability. Five other custodians (DFO, DND, PCA, PSPC, TC) reported increases in liability greater than $10 million, accounting for 10% of the overall increase. The remaining four custodians reported increases of less than $10 million each and accounted for less than 2% of the overall increase (Figure 5). Four custodians reported a total decrease in liability of $10.7 million in 2019–2020 (Figure 6).

Figure 5: FCSAP custodians with liability increases

Figure 5: FCSAP custodians with liability increases
Long description

This figure shows the FCSAP custodians that reported an increase in liability in 2019–2020.

Crown-Indigenous Relations and Northern Affairs Canada: $589 million increase in liability

Indigenous Services Canada: $379 million increase in liability

Fisheries and Oceans Canada: $42 million increase in liability

Transport Canada: $22 million increase in liability

Parks Canada Agency: $19 million increase in liability

Department of National Defence: $15 million increase in liability

Public Services and Procurement Canada: $14 million increase in liability

Agriculture and Agri-Food Canada, Jacques Cartier and Champlain Bridges Incorporated, Natural Resources Canada and VIA Rail Canada: $15 million increase in liability

Figure 6: FCSAP custodians with liability decreases

Figure 6: FCSAP custodians with liability decreases
Long description

This figure shows the FCSAP custodians that reported a decrease in liability in 2019–2020.

Environment and Climate Change Canada: $7.6 million decrease in liability

National Capital Commission: $1.5 million decrease in liability

National Research Council of Canada: $1.1 million decrease in liability

Correctional Service Canada: $0.6 million decrease in liability

3.5 Socio-economic benefits

Many FCSAP projects have socio-economic benefits, especially in Indigenous communities and in northern or rural areas. Through joint ventures between custodians and local communities, work conducted on contaminated sites offers opportunities for local residents and contractors to learn and develop skills, and to build careers and businesses. The partnerships forged among workers and businesses, especially at the local level, help foster a sense of ownership of project results.

During the 2019–2020 fiscal year, FCSAP activities led to the creation or maintenance of approximately 2,000 jobs. These jobs provide income and fuel economic growth. FCSAP activities help workers develop skills, which can then be applied at other contaminated sites or other types of construction and engineering projects. For example, FCSAP remediation projects regularly employ northerners and Indigenous people as welders, heavy-duty mechanics, electricians and millwrights.

Through FCSAP, the Canadian remediation industry gains opportunities to advance new solutions when cleaning up federal contaminated sites. The program builds awareness of innovative and sustainable technologies by sharing success stories within the federal community and with the private sector. Case studies are profiled on the federal contaminated sites web portal, as well as in reports and at workshops for federal contaminated-site managers and industry representatives. For example, a case study describing the collaboration between ISC and the Wasauksing First Nation is found in Section 7 of this report.

3.6 Impact on the Federal Contaminated Sites Inventory

The Federal Contaminated Sites Inventory (FCSI), managed by the Treasury Board of Canada Secretariat, includes information on federal contaminated sites under the custodianship of departments, agencies and consolidated Crown corporations, and on non-federal contaminated sites for which the Government of Canada has accepted some or all financial responsibility.

Sites registered in the FCSI move from “suspected” to “active” status once the contamination has been confirmed. Suspected sites may be closed if a desktop review or a Phase I environmental site assessment determines that historical activities would not likely have caused contamination. Sites undergoing assessment are usually closed if the assessment determines that contaminants are not present or do not pose an unacceptable risk to human health or the environment. Sites can also be closed when risks have been reduced to acceptable levels through remediation, risk-management or long-term monitoring.

Suspected: Further assessment work is required to confirm whether the site is considered a federal contaminated site.

Active: Active sites are confirmed as contaminated sites where remedial action is or may be required.

Closed: No further action is required.

As of March 31, 2020, the FCSI contained 23,714 sites, of which 17,059 (72%) have been closed. There are 4,860 active sites (20%), where contamination has been confirmed and remedial action is or may be required. A total of 1,795 sites (8%) may be contaminated but have not yet been assessed (Figure 7).

Figure 7: Status of sites in the FCSI, as of March 31, 2020

Figure 7: Status of sites in the FCSI, as of March 31, 2020
Long description

This figure shows the status of sites in the Federal Contaminated Sites Inventory, as of March 31, 2020.

Suspected: 1,795 sites

Active: 4,860 sites

Closed: 17,059 sites

Progress of sites through the FCSI

Before FCSAP was established in 2005–2006, the FCSI contained approximately 2,000 suspected and 4,200 active federal contaminated sites. Since then, custodians have added sites to the FCSI when they suspected contamination and have conducted assessment and remediation activities at these sites, if required. As of March 31, 2020, the FCSI contained 23,714 sites, of which 47% (11,060 sites) received FCSAP funding to advance their contaminated sites activities since the onset of FCSAP in 2005-2006.

In 2019–2020, about 65% of expenditures reported to the FCSI were attributable to FCSAP sites, which included both FCSAP funding and the custodian cost share. The remaining 35% was for expenditures on non-FCSAP sites and federal organizations that are not part of FCSAP. Over the 2019-2020 fiscal year, this combined investment resulted in a decrease in suspected sites by 3% from 1,842 to 1,795, a decrease in active sites by 2% from 4,980 to 4,860 and an increase in closed sites by 1%, from 16,845 sites to 17,059 sites, as shown in Figure 8.

Figure 8: Status of sites in the FCSI from 2005 to 2020

Figure 8: Status of sites in the FCSI from 2005 to 2020
Long description

This figure shows the status of sites in the Federal Contaminated Sites Inventory, from 2005 to 2020.

In 2005–2006, 4,609 sites were suspected, 5,352 sites were active and 1,129 sites were closed.

In 2006–2007, 11,841 sites were suspected, 6,476 sites were active and 1,630 sites were closed.

In 2007–2008, 11,510 sites were suspected, 6,601 sites were active and 2,505 sites were closed.

In 2008–2009, 10,809 sites were suspected, 5,710 sites were active and 3,825 sites were closed.

In 2009–2010, 7,434 sites were suspected, 6,949 sites were active and 5,215 sites were closed.

In 2010–2011, 6,958 sites were suspected, 7,399 sites were active and 7,660 sites were closed.

In 2011–2012, 4,929 sites were suspected, 6,845 sites were active and 10,480 sites were closed.

In 2012–2013, 4,014 sites were suspected, 6,568 sites were active and 11,800 sites were closed.

In 2013–2014, 3,020 sites were suspected, 6,144 sites were active and 13,427 sites were closed.

In 2014–2015, 2,606 sites were suspected, 5,785 sites were active and 14,429 sites were closed.

In 2015–2016, 2,353 sites were suspected, 5,340 sites were active and 15,381 sites were closed.

In 2016–2017, 2,060 sites were suspected, 5,239 sites were active and 15,980 sites were closed.

In 2017–2018, 1,987 sites were suspected, 5,067 sites were active and 16,436 sites were closed.

In 2018–2019, 1,842 sites were suspected, 4,980 sites were active and 16,845 sites were closed.

In 2019–2020, 1,795 sites were suspected, 4,860 sites were active and 17,059 sites were closed.

4. FCSAP funding, expenditures and variances

FCSAP expenditures in the 2019–2020 fiscal year were $380.2 million. This represents 83% of the FCSAP funding available for the year. Custodians also spent $31.0 million of their own funding to meet the cost-share requirements.

Types of expenditures

In the 2019–2020 fiscal year, 94% of total FCSAP expenditures were for remediation and risk management of contaminated sites, 1% was for assessment of sites, and 5% was for program management (Figure 9). Table B.3 in Appendix B details the allocations for the three types of FCSAP funding.

Figure 9: Distribution of FCSAP expenditures in 2019–2020

Figure 9: Distribution of FCSAP expenditures in 2019–2020
Long description

This figure shows the distribution of FCSAP expenditures in 2019–2020. Total FCSAP expenditures were $380.2 million. Expenditures for program management were $19.9 million, which represented 5% of total FCSAP expenditures. Expenditures for assessment were $2.1 million, which represented 1% of total FCSAP expenditures. Expenditures for remediation were $358.2 million, which represented 94% of total FCSAP expenditures.

What happens to unspent funds?

Custodians did not spend all of the FCSAP funding available to them in 2019–2020. This is mostly because of contracting and project delays. For example, weather conditions might either prevent access to the sites or limit the types of work that could be carried out. The tendering of some projects was also delayed, which led to postponement of the remediation and risk-management work to the next fiscal year. In some cases, rescheduling of planned work into the next fiscal year can lower current year project costs.

Unspent funds can be brought forward for FCSAP activities in future years through three methods:

These processes allow custodians flexibility in their response to unpredictable situations, such as weather. The FCSAP Secretariat promotes and facilitates the transfer of funds among custodians.

Funding that is not brought forward or transferred between custodians is lapsed. This means that the funds will not be available for FCSAP activities in the future.

In 2019–2020, 74% of the FCSAP funding variance was re-profiled, 12% was carried forward, 10% was internally cash-managed and 3% was lapsed (Figure 10). This means that $77.6M (97%) of the $80.3 million of unspent funding in 2019–2020 will be available to custodians in future years. Table B.4 in Appendix B provides a breakdown by funding type of the unspent funding. Of the $80.3M of FCSAP funding that was not spent in 2019–2020, $80.1M (99%) was for remediation, $0.08M (0.1%) was for assessment and $0.1M (0.1%) was for program management.

Figure 10: Distribution of FCSAP variance

Figure 10: Distribution of FCSAP variance
Long description

This figure shows the distribution of FCSAP variance, which is the unspent funding. Total variance was $80.3 million. $59.4 million of funds were re-profiled, which represented 74% of total variance. $9.9 million of funds were carried forward, which represented 12% of total variance. $8.3 million of funds were cash managed, which represented 10% of total variance. $2.7 million of funds were lapsed, which represented 3% of total variance.

5. Phase III results (2016–2019)

This section summarizes the overall results of Phase III of the Federal Contaminated Sites Action Plan (FCSAP), which ran from 2016–2019.

In Phase III, federal custodians continued to assess and remediate high-priority federal contaminated sites and to reduce the related environmental liabilities. The custodians reported total FCSAP expenditures of $1.624 billion for Phase III (this includes $203.6 million of Federal Infrastructure Initiative funding). The breakdown of total FCSAP expenditures is: $48.1 million spent on assessments, $1.485 billion spent on remediation and risk management and $91.4 million for program management activities related to federal contaminated sites (Figure 11). An additional $124.9 million was spent as part of the custodian cost-share requirement for FCSAP.

Figure 11: Distribution of FCSAP expenditures in Phase III

Figure 11: Distribution of FCSAP expenditures in Phase III
Long description

This figure shows the distribution of FCSAP expenditures in Phase III. Total FCSAP expenditures were $1.624 billion. Expenditures for program management were $91.4 million, which represented 6% of total FCSAP expenditures. Expenditures for assessment were $48.1 million, which represented 3% of total FCSAP expenditures. Expenditures for remediation were $1.485 billion, which represented 91% of total FCSAP expenditures

At the end of 2019–2020, $1.624 billion (95%) of total funding available in Phase III was spent, $77.6 million (4.5%) of funding was reprofiled, carried forward or cash managed to Phase IV and $10.0 million (0.6%) of funding was lapsed.

Phase III assessment activities – key results

By the end of Phase III, custodians had conducted assessments at 844 sites, exceeding the 4-year performance target of 569 assessments (Figure 12). The target was based on planning information provided by custodians. Although targets were adjusted to reflect additional funding received through the Federal Infrastructure Initiative, custodians were able to assess more sites than originally planned.

Figure 12: Number of sites where FCSAP-funded assessments were conducted over Phase III

Figure 12: Number of sites where FCSAP-funded assessments were conducted over Phase III
Long description

This figure shows the 4-year target and the result achieved after 2019–2020 for assessment. The 4-year target was that assessment activities would be conducted at 569 FCSAP-funded sites in Phase III. The result after 2019–2020 was that assessment activities were conducted at 844 FCSAP-funded sites in Phase III.

The two custodians that spent the most on assessments were the Department of National Defence and Indigenous Services Canada, which together spent 57% of the FCSAP assessment expenditures reported in Phase III ($27.3 million of $48.1 million). These two custodians also conducted 64% of all FCSAP-funded site assessments in Phase III (539 of 844 sites).

The largest expenditures for assessment occurred in Ontario and British Columbia, accounting for 52% of all FCSAP assessment expenditures in Phase III ($24.9 million of $48.1 million). These two provinces also had the largest number of sites with assessment activity (50%, or 421 of 844 sites), as shown in Figure 13.

Figure 13: Distribution of FCSAP assessment expenditures and sites in Phase III, by province and territory

Figure 13: Distribution of FCSAP assessment expenditures and sites in Phase III, by province and territory
Long description

This figure shows the distribution of FCSAP assessment expenditures and the number of sites, by province and territory, in Phase III.

Alberta: $4.1 million of FCSAP assessment expenditures for 83 sites

British Columbia: $11.0 million of FCSAP assessment expenditures for 226 sites

Manitoba: $3.2 million of FCSAP assessment expenditures for 74 sites

New Brunswick: $0.9 million of FCSAP assessment expenditures for 22 sites

Newfoundland and Labrador: $1.6 million of FCSAP assessment expenditures for 22 sites

Northwest Territories: $0.2 million of FCSAP assessment expenditures for 6 sites

Nova Scotia: $2.7 million of FCSAP assessment expenditures for 51 sites

Nunavut: $2.4 million of FCSAP assessment expenditures for 16 sites

Ontario: $13.9 million of FCSAP assessment expenditures for 195 sites

Prince Edward Island: $0.2 million of FCSAP assessment expenditures for 3 sites

Quebec: $4.2 million of FCSAP assessment expenditures for 96 sites

Saskatchewan: $2.3 million of FCSAP assessment expenditures for 27 sites

Yukon: $1.4 million of FCSAP assessment expenditures for 23 sites

Phase III remediation and risk-management activities – key results

The FCSAP Secretariat tracks two indicators related to risk-reduction activities: the number of FCSAP-funded sites where risk-reduction activities were conducted, and where these activities were completed.

By the end of Phase III, custodians had conducted risk-reduction activities at 1,104 sites, exceeding the 4-year performance target of 974 sites (Figure 14). The target was based on planning information provided by custodians. Although targets were adjusted to reflect the additional funding received through the Federal Infrastructure Initiative, custodians were able to conduct risk-reduction activities at more sites than originally planned.  

Figure 14: Number of FCSAP-funded sites where risk-reduction activities were conducted in Phase III

Figure 14: Number of FCSAP-funded sites where risk-reduction activities were conducted in Phase III
Long description

This figure shows the 4-year target and the result achieved after 2019–2020 for conducting risk-reduction activities. The 4-year target was that risk-reduction activities would be conducted at 974 FCSAP-funded sites in Phase III. The result after 2019–2020 was that risk-reduction activities were conducted at 1,104 FCSAP-funded sites in Phase III.

The number of sites undergoing remediation and risk management varies from year to year. Weather or unanticipated technical issues may cause delays at some sites, especially at remote northern sites. By the end of Phase III, custodians had met 42% of the 4-year target for completing risk-reduction activities (Figure 15). The remediation and risk management of a site is a complex process that can take many years. The duration of remediation activities at a site depends on the type and extent of the contamination, scientific knowledge of the contamination, location of the site and weather conditions.

Figure 15: Number of FCSAP-funded sites where risk-reduction activities were completed, 2019–2020

Figure 15: Number of FCSAP-funded sites where risk-reduction activities were completed, 2019–2020
Long description

This figure shows the 4-year target and the result achieved after 2019–2020 for the completion of risk-reduction activities. The 4-year target was that risk-reduction activities would be completed at 548 FCSAP-funded sites in Phase III. The result after 2019–2020 was that risk-reduction activities were completed at 232 FCSAP-funded sites in Phase III, which represented 42% of the target.

The two custodians that spent the most on remediation and risk management were Crown-Indigenous Relations and Northern Affairs Canada and the Department of National Defence, which together spent 66% of the FCSAP remediation expenditures reported in Phase III ($978 million of the $1.485 billion). Fisheries and Oceans Canada, Indigenous Services Canada and the Department of National Defence conducted 66% of all FCSAP-funded remediation of sites in Phase III (732 of 1,104 sites).

The largest expenditures occurred in British Columbia, Northwest Territories and Yukon, accounting for 70% of all FCSAP remediation expenditures in Phase III ($1.042 billion of $1.485 billion). The provinces with the largest number of sites with remediation activity were British Columbia, Ontario and Quebec (49%, or 538 of 1,104 sites), as shown in Figure 16.

Figure 16: Distribution of FCSAP remediation expenditures and sites in Phase III, by province and territory

Figure 16: Distribution of FCSAP remediation expenditures and sites in Phase III, by province and territory
Long description

This figure shows the distribution of FCSAP remediation expenditures and the number of sites, by province and territory, in Phase III.

Alberta: $11 million of FCSAP remediation expenditures for 59 sites

British Columbia: $397 million of FCSAP remediation expenditures for 198 sites

Manitoba: $39 million of FCSAP remediation expenditures for 46 sites

New Brunswick: $4 million of FCSAP remediation expenditures for 38 sites

Newfoundland and Labrador: $85 million of FCSAP remediation expenditures for 130 sites

Northwest Territories: $353 million of FCSAP remediation expenditures for 53 sites

Nova Scotia: $15 million of FCSAP remediation expenditures for 109 sites

Nunavut: $69 million of FCSAP remediation expenditures for 53 sites

Ontario: $109 million of FCSAP remediation expenditures for 188 sites

Prince Edward Island: $1 million of FCSAP remediation expenditures for 21 sites

Quebec: $102 million of FCSAP remediation expenditures for 152 sites

Saskatchewan: $8 million of FCSAP remediation expenditures for 32 sites

Yukon: $292 million of FCSAP remediation expenditures for 25 sites

Phase III liability – key results

For Phase III, the FCSAP Secretariat tracked two indicators related to the reduction of liability:

For the first indicator, custodians estimated that liability would be reduced at these sites by $574 million by the end of Phase III. At the end of Phase III, custodians had achieved 90% of the 4-year target for liability reduction. Remediation and risk-management activities at these sites decreased the liability by $515 million (Figure 17). However, this reduction was offset by an increase in liability, due to such things as changes in project costs, of $338 million, resulting in a net reduction in liability of $177 million.

Figure 17: Reduction in liability at FCSAP-funded sites, by the end of Phase III

Figure 17: Reduction in liability at FCSAP-funded sites, by the end of Phase III
Long description

This figure shows the 4-year target and the result achieved after 2019–2020 for the reduction in liability of FCSAP-funded sites, by the end of Phase III. The 4-year target was that liability at FCSAP-funded sites would be reduced by $574 million in Phase III. The result after 2019–2020 was that liability at FCSAP-funded sites was reduced by $515 million, which represented 90% of the target.

The second indicator relates to the percentage of remediation expenditures that reduced liability over the four years of Phase III. At the end of Phase III, 95% of FCSAP remediation expenditures ($1.41 billion of $1.48 billion) had led to reductions in liability (Figure 18). This meets the target established for Phase III of 95%.

Figure 18: Percentage of FCSAP remediation expenditures that reduced liability related to FCSAP sites in Phase III

Figure 18: Percentage of FCSAP remediation expenditures that reduced liability related to FCSAP sites in Phase III
Long description

This figure shows the percentage of FCSAP remediation expenditures that reduced liability in Phase III. $1.41 billion or 95% of FCSAP remediation expenditures reduced liability in Phase III. $70 million or 5% of remediation expenditures did not reduce liability.

6. Preparing for FCSAP Phase IV

On July 24, 2019, the Minister of Transport announced, on behalf of the Minister of Environment and Climate Change, that the Government of Canada was renewing FCSAP for another 15 years (2020–2034), and was investing $1.16 billion from 2020–2024, in alignment with Budget 2019. The new investment will allow custodians to continue remediating federal contaminated sites. In turn, this work will improve the health of the environment, fuel economic growth and create jobs, notably for people living in Indigenous and northern communities.

In preparation for FCSAP Phase IV, the FCSAP Secretariat, expert support departments and custodians worked toward the implementation of regional integrated planning boards (RIPBs). The objectives of the RIPBs are to:

7. Case studies

Remediation at the Fort Reliance Former Weather Station

Location: Fort Reliance, Northwest Territories
Custodian:
Environment and Climate Change Canada (ECCC)

The Fort Reliance former weather station lies about 270 km east of Yellowknife on the eastern end of Great Slave Lake, and within the Thaidene Nene National Park Reserve.

Since 1993, the site has been vacant, with the exception of a small automated weather station still operated by ECCC. The site also contained abandoned buildings and infrastructure, remnants of the Department of National Defence’s operations from the 1940s to the early 1970s, as well as the Atmospheric Environment Service’s use from the late 1950s to the early 1990s.

Assessing the contamination

ECCC, Public Services and Procurement Canada and various environmental consultants have conducted investigations since the late 1980s to identify and characterize areas of environmental concern resulting from the site’s past use:

Historical and modern remediation

The only remediation conducted during operations started in 1991, when ECCC installed a hydrocarbon containment and bioremediation system. This system was located parallel to the shoreline of Great Slave Lake and down-gradient of the fuel-tank farm. By 1993, the system had extracted about 19 million litres of groundwater and treated it with a separator, hydrogen peroxide and nutrients – reducing the total PHC concentration in the extraction trench by about 65%.

In 2019–2020, ECCC implemented a three-month physical remediation and risk-management plan to address the remaining contamination. This involved several actions:

This remediation achieved the environmental objectives for the rehabilitation of the site.

Collaboration and next steps

The major contributing factor to the success of the project was the coordination and active participation of significant parties and stakeholders.

ECCC held formal consultations with the Łutsël K’e Dene First Nation, who view Thaidene Nene as a sacred place. The consultations were widely successful, in terms of gathering input on the project and generating acceptance, as well as ensuring that economic, employment and training opportunities would be provided to the community. ECCC also coordinated with the Mackenzie Valley Land and Water Board to obtain permits, and with an environmental consultant and other contractors who played key roles in the success of the project.

As Parks Canada Agency (PCA) has expressed interest in acquiring the site, ECCC coordinated with PCA throughout the project and ensured that the standards for testing would meet those required by PCA within a National Park Reserve. Moreover, although all 16 of the buildings at the site were environmental concerns, five were historically significant, and had been designated federal heritage buildings. Coordination with PCA ensured that ECCC was able to maintain the historical significance of the buildings during decommissioning and remediation.

The involvement of FCSAP Expert Support in providing guidance at various stages throughout the project was an invaluable resource.

The future of the Fort Reliance site is bright. ECCC has committed to monitoring site conditions to ensure that remedial activities continue to benefit future generations of Canadians.

This project was funded through Canada’s Federal Contaminated Sites Action Plan (FCSAP). FCSAP provides funding to assess and remediate federal contaminated sites and to reduce environmental and human-health risks from known federal contaminated sites.

Waste Oil Pit Remediation Project in Wasauksing First Nation

Location: Wasauksing First Nation, Ontario
Custodian:
Indigenous Services Canada (ISC)

The Waste Oil Pit Remediation Project, completed in November 2019, involved the remediation of four waste-oil pits through the removal of 8,855 tonnes of contaminated soil. The project site lies in Wasauksing First Nation on Parry Island on the eastern shore of Georgian Bay. The Wasauksing First Nation encompasses all of Parry Island – which, at 7,800 hectares, is the second-largest island in Lake Huron.

The waste-oil pits were historically used for the disposal of fuel waste removed from Parry Sound harbour between 1951 and 1952, after a large oil spill in 1950. ISC assessed the pits as part of a Phase III environmental site assessment, completed in 2018, that found soil contaminated with petroleum hydrocarbons and polycyclic aromatic hydrocarbons (PAHs). One of the sites also contained miscellaneous waste, such as old cars and scrap metal.

Public Services and Procurement Canada (PSPC) awarded the remediation design work on June 28, 2019 to a consultant specializing in providing environmental services to First Nation, Inuit and northern communities. Once the design work was complete, PSPC initiated a competitive process and awarded remediation work on September 4, 2019 to an environmental contracting company. The project team consisted of members from Wasauksing First Nation, ISC, PSPC, environmental consultants and contractors. The success of the Project was mainly due to the great collaboration between parties.

Completing the remediation

Remediation work was completed by Wasauksing First Nation members under contract with the contractor, and took place at the four oil pits from September 26 to November 26, 2019. Remediation activities included:

Removal of contaminated soil from the waste pits was performed using an excavator that removed soil in lifts. The project team then loaded the soil onto haulage trucks to be transported to an approved off-site facility for disposal. While being filled, the trucks were situated on a decontamination pad located beside each site. At two of the sites, water management was necessary during the remediation work, and the contractor pumped the water into temporary above-ground storage tanks, then removed it with hydrovac equipment and safely disposed of it offsite.

Problem solving

As with any project of this scale, some deviations from the initial plan became necessary:

Next steps

Post-remediation soil samples and groundwater sampling have shown that the Project met all applicable remediation criteria. The project team also conducted well-water quality testing at two of the sites, and showed that samples met drinking-water criteria. Grass seed was placed post-remediation at the four sites on November 2019, which is late in the growing season. However, the project team inspected and assessed the growth in the spring of 2020, and rectified any deficiencies.

The remediation work met the standards for residential land use, allowing the community unrestricted use of these sites.

This project was funded through Canada’s Federal Contaminated Sites Action Plan (FCSAP). FCSAP provides funding to assess and remediate federal contaminated sites and to reduce environmental and human-health risks from known federal contaminated sites.

Remediation and risk management of a former firefighter training area at Ferguson’s Cove, Nova Scotia

Location: Ferguson’s Cove (Halifax Regional Municipality), Nova Scotia
Custodian: Department of National Defence (DND)

DND’s Damage Control Division (DCD) School at Ferguson’s Cove, Nova Scotia conducted firefighter training from 1959 until commissioning a new on-site training facility in 2002.

At the former firefighter training area, firefighter training involved the controlled burning of diesel fuel, stove oil and gasoline, and used water, potassium bicarbonate, carbon dioxide and firefighting foams to extinguish fires. In 1995, DCD School introduced spill control and containment activities to try to contain the foams and minimize potential impacts on the environment as much as possible. 

Decommissioning and initial risk management

After decommissioning the facility in the summer of 2005, DND assessed the condition of the site and the risk to human health and the environment, and implemented a risk-management plan for petroleum hydrocarbons on the property.

Following the assessment, DND installed a gravel and vegetation cap over the site and implemented a groundwater-monitoring program. Groundwater monitoring for petroleum hydrocarbons continued until 2019, when it was determined that the potential risk to the environment and human health was minimal. DND continues to visually inspect the engineered cap annually to ensure its integrity.

The former firefighter training activities had also affected a nearby wetland and beach area on the DCD School property. In the mid-1990s, DND remediated the beach area by excavating the soil and treating it off-site, and conducted bioremediation from 2003 to 2005. However, the bioremediation was not successful at reducing the significant petroleum contamination in the wetland. As a result, DND conducted further excavation work and off-site treatment of contaminated soil and sediment in 2009. After excavation, DND reinstalled the wetland.

A newly identified toxic substance

In December 2006, perflurooctane sulfonate (PFOS), a compound in the poly- and perfluoralkylated substance (PFAS) group of chemicals, was added to the list of toxic substances included in the Canadian Environmental Protection Act.

PFAS are manufactured chemicals used in a variety of consumer and industrial products, including firefighting foams. PFAS are very stable, meaning that they do not break down easily in nature. PFAS are also highly water soluble, so they dissolve into water easily and can move with it over long distances. For these reasons, the understanding of PFAS properties in the environment is still evolving, along with best practices to address it.

Since the DCD School used firefighting foams that contained PFAS as part of its training activities, DND assessed the former firefighter training area for PFAS in 2007. The initial assessment identified PFAS concentrations in groundwater in the former training area which led to other PFAS investigations across the DCD school property from 2007 to 2021. The investigations were completed to assess PFAS in various media (groundwater, soil, surface water and sediments), as well as to better understand the potential risks of off-site migration.

Addressing PFAS

To address potential off-site PFAS migration in groundwater, DND installed two deep monitoring wells in 2017–2018 near the southern property boundary of Ferguson Cove. Groundwater analysis indicated that off-site PFAS migration in groundwater was unlikely, as PFAS concentrations were below laboratory detection limits. This ruled out risks to human health.

Out of an abundance of caution, DND conducted additional soil, groundwater, and surface water sampling as part of an ecological risk assessment to determine if further remediation or risk management measures were required.DND consulted with Expert Support Departments, specifically Environment and Climate Change Canada and Fisheries and Oceans Canada, when planning the ecological risk assessment, which included the review of the initial PFAS site characterization reports, review of the ecological risk assessment problem formulation and work plan, in addition to the proposed toxicity reference values and species at risk considered receptors of concern at the site. DND will continue to engage Expert Support as the ecological risk assessment moves forward.

In 2018–2019, DND completed the additional soil sampling in surrounding areas of the former firefighter training area within the DCD school property, including the previously remediated wetland and beach area. DND also completed the initial stages of the ecological risk assessment, which has helped provide a better understanding of the presence of PFAS in the area and potential risks.

In 2019–2020, planning the ecological risk assessment continued and a site was chosen to sample and analyze soil, sediment, surface water, underwater and land vegetation, small mammals, amphibians and fish, as well as plant health in the area. This analysis is taking place at the former firefighting training facility as well as another chosen off-site property for general background information. This assessment is being carried out in 2020–2021.

DND will use the site-specific ecological risk assessment currently underway to determine if further risk management/remediation is required. DND will also continue to monitor the groundwater for potential off-site migration.

This project was funded through Canada’s Federal Contaminated Sites Action Plan (FCSAP). FCSAP provides funding to assess and remediate federal contaminated sites and to reduce environmental and human-health risks from known federal contaminated sites.

Bathurst Island and High Arctic Remediation Project

Location: Nunavut
Custodian:
Crown-Indigenous Relations and Northern Affairs Canada (CIRNAC)

The Bathurst Island and High Arctic Remediation Project consists of 12 sites located between 120 km and 630 km north of the nearest community,Resolute, Nunavut. All of the sites were former oil and gas exploration and production sites developed by Panarctic Oils Limited from the 1960s to early 1980s. The sites are spread across six islands in the high Arctic, north of the 75th parallel. Some sites are also located within the boundaries of the newly established Qausuittuq National Park and Nanuit ltillinga (Polar Bear Pass) National Wildlife Area on Bathurst Island. The only infrastructure on the sites consists of a few abandoned exploration trailers, well markers, and scattered non-hazardous debris. These are the most northerly sites that CIRNAC’s Northern Contaminated Sites Program has attempted to address.

High Arctic sites
Long description

This map shows the location of the High Arctic contaminated sites.

Crown-Indigenous Relations and Northern Affairs Canada contaminated sites in the high arctic are:

  • Drake Point
  • Rea Point
  • Dale Payne
  • Thor Island
  • Lougheed Island
  • Bent Horn
  • Ile Vanier
  • Stokes Range
  • Young Inlet
  • J-34
  • N-12

The community sites include:

  • Grise Fiord
  • Resolute

Between 2011 and 2015, CIRNAC completed Phase I, II and III environmental site assessments for each site to identify and determine the extent of the contaminants of concern. The identified contaminants were predominately petroleum hydrocarbons and metals; however, soil contaminated by polychlorinated biphenyls (PCBs) was also present at one site. Other hazards included numerous drums containing fuel, compressed-gas cylinders, batteries, and hazardous materials such as mercury thermostats and asbestos in some of the abandoned structures.

An alternative approach

Given the challenges of the remoteness of the sites and the extremely high costs of conventional remediation approaches, CIRNAC explored the alternative of risk management. The initial step in this exploration was the completion of preliminary quantitative risk assessments for each of the sites. These assessments included consideration of potential land use by Inuit hunters and visitors, and of potential environmental effects on food sources. Information gathered during the assessments, along with some conservative assumptions, indicated some risks at the sites – most of them deemed to be low, due to the limited number of receptors and active exposure pathways. With input from the community of Resolute, CIRNAC developed remediation and risk-management plans for each site to address the highest risks and hazards. Because the sites were within a few hundred kilometres of each other and had similar contaminants, CIRNAC grouped them into one project for efficiency and cost-effectiveness.

Remediation and risk management begin

CIRNAC completed the remediation and risk-management activities during July and August 2019, basing operations in Resolute, with daily flights to and from the sites. The site work included:

CIRNAC also assisted Parks Canada Agency with the cleanup of non-hazardous debris at sites within Qausuittuq National Park boundaries, to make the most effective use of the funding for both federal organizations.

Challenges and delays

The field team had to contend with many challenges, including:

Due to the lost time and field conditions, not all of the work was completed in 2019–2020. The remaining work was originally rescheduled for 2020–2021 but due to the COVID-19 outbreak, Project completion has been deferred to 2021–2022. This work will include the collection and containerization of hazardous materials, liquids, drums, and contaminated soil. All waste is to be shipped to southern disposal facilities by sealift in the fall of 2021.

After the Project is completed in 2021, CIRNAC will review the results and develop a long-term monitoring strategy for the sites. The plan will likely consist of monitoring land use in the area and verification of the assumptions of the risk assessment.

Collaboration toward common goals

The Project included requirements for maximizing community involvement and supporting Inuit employment. To those ends, CIRNAC developed working relationships with the community of Resolute throughout the Project, holding community meetings there in 2015, 2016, 2018, and in June 2019 before the start of remediation and risk-management. This meeting was used to introduce the contractor and update the community. The contractor hired several Inuit from Resolute as members of the field team; the Project also used Inuit-owned supplies and local businesses.

A final community presentation will be held once the work is complete, to inform the community of the results.

The Project was carried out with the cooperation and support of Public Services and Procurement Canada, Parks Canada Agency, the Canadian Wildlife Service, the Sulukvaut Area Co-Management Committee, and residents of Resolute.

Significant cost savings and efficiencies were achieved by adopting a risk-management strategy to address these remote sites.

Completion of the project will meet the Northern Contaminated Sites Program objectives to protect the health and safety of Nunavummiut, protect the environment, reduce liability associated with contaminated sites, and fulfill CIRNAC’s custodial obligations.

This project was funded through Canada’s Federal Contaminated Sites Action Plan (FCSAP). FCSAP provides funding to assess and remediate federal contaminated sites and to reduce environmental and human-health risks from known federal contaminated sites.

Indigenous Engagement at the Faro Mine Remediation Project

Location: Faro, Yukon
Custodian: Crown-Indigenous Relations and Northern Affairs Canada (CIRNAC)

With the submission of the Faro Mine Remediation Project proposal to the Yukon Environmental and Socio-economic Board (YESAB) in May 2019, YESAB and the Canadian Northern Economic Development Agency, on behalf of the Government of Canada, engaged the Ross River Dena Council, Liard First Nation and Selkirk First Nation to validate their past involvement in the Project and to share information on the assessment process underway.

As the remediation plan for the Faro Mine site evolves, First Nations and their technical advisors continue to be involved in the technical aspects of the project through participation in the Technical Review Committee. This governance body brings together representatives from CIRNAC, affected First Nations, the Government of Yukon and technical consultants to review and discuss current site conditions, care and maintenance activities, and urgent work and design components. The Committee held 24 bi-weekly meetings during the 2019–2020 fiscal year.

Participation in governance committee meetings provides frequent opportunities for affected First Nations and their representatives to share their views and interests, and to contribute to decisions. CIRNAC provides annual capacity funding to support the involvement of affected First Nations in all aspects of the Project, and the project team will continue to ensure that appropriate governance mechanisms and processes remain in place for effective First Nation participation.

This year saw the establishment of an important partnership with Ross River’s Dena Nezziddi Development Corporation, through the realignment of the north fork of Rose Creek at the site. This partnership generated important socio-economic benefits through training, employment and subcontracting to Ross River businesses and citizens.

As the Project moves forward, important work is being initiated with the Ross River Dena Council to develop community-based land-use objectives that will guide future revegetation trials and, eventually, the revegetation plan for the Faro Mine site.

This project was funded through Canada’s Federal Contaminated Sites Action Plan (FCSAP). FCSAP provides funding to assess and remediate federal contaminated sites and to reduce environmental and human-health risks from known federal contaminated sites. Starting in 2020–2021, this project will be funded through the Northern Abandoned Mine Reclamation Program.

Indigenous Engagement at the Giant Mine Remediation Project

Location: Yellowknife, Northwest Territories
Custodian: Crown-Indigenous Relations and Northern Affairs Canada (CIRNAC)

Giant Mine was once a major economic driver for the Northwest Territories. Operating between 1948 and 2004, the mine produced over 7.5 million ounces of gold from arsenopyrite ore formations on the western shore of Yellowknife Bay. The processing of gold involved roasting the ore, creating a by-product of highly toxic arsenic trioxide dust. Control of the property, as well as the main environmental liabilities, was transferred to CIRNAC after the mine’s closure.

The Giant Mine site lies within the asserted traditional territory of the Akaitcho Territory Dene First Nation, and within the extended Monfwi (Môwhì Gogha Dè Nîîtåèè) boundary, as defined in the Tlicho Land Claim and Self-Government Agreement. The site also lies on the boundary of the Interim Measures Agreement Area of the Northwest Territories Métis Nation. As custodian of the Giant Mine Remediation Project, CIRNAC recognizes the importance of providing opportunities for all stakeholders to engage meaningfully on key issues. The Project team also appreciates the importance of showing how stakeholder input has been gathered and incorporated into decision-making.

Since the responsible Ministers’ decision on the environmental assessment in 2014, the engagement process has matured and become more streamlined. Key activities, such as the engagement on surface design, helped establish momentum and trust with some stakeholder groups, particularly the Yellowknives Dene First Nation and the North Slave Métis Alliance. Through the ongoing consultation activities, the project team has also gained important insight that allowed the planning and execution of engagement sessions and public events to become easier and more effective.

Over the 2019–2020 fiscal year, the Project team undertook or participated in 67 engagement activities or events. These included sessions on the Quantitative Risk Assessment, the Perpetual Care Plan, Borrow Design, the Hoèla Weteèst’eèdeè: Understanding Community Well-being Around Giant Mine Study (as part of Measure 10), and work towards implementing the Socio-Economic Strategy through ongoing meetings with the Socio-economic Working Group and the Socio-Economic Advisory Body. In addition, the Project team was involved in technical sessions and Public Hearings as part of the Mackenzie Valley Land and Water Board Water Licence process. The Project team also conducted outreach to youth with local schools, providing students with hands-on science experiences and classroom visits.

The Giant Mine Remediation Project also recognizes the importance of incorporating traditional knowledge into the planning for final site remediation, and will continue to work with the Yellowknives Dene First Nation and the North Slave Métis Alliance to ensure that the gathering and use of traditional knowledge continues to improve. As the Project moves forward, engagement in the year to come will also focus on engaging on Monitoring and Management Plans required through the Water Licence, as well as engagement through an Aquatics Advisory Committee.

This project was funded through Canada’s Federal Contaminated Sites Action Plan (FCSAP). FCSAP provides funding to assess and remediate federal contaminated sites and to reduce environmental and human-health risks from known federal contaminated sites. Starting in 2020–2021, this project will be funded through the Northern Abandoned Mine Reclamation Program.

8. Updates on priority projects

Faro Mine Remediation Project

Location: Faro, Yukon
Custodian: Crown-Indigenous Relations and Northern Affairs Canada (CIRNAC)

The Faro Mine complex is located in south-central Yukon, 22 km north of the town of Faro and almost 350 km northeast of Whitehorse. From Whitehorse, the mine is a 30-minute charter flight or a four-hour drive away. The mine complex is located in the traditional territory of the Kaska Nation and is upstream from the traditional territory of the Selkirk First Nation.

History

A former open-pit lead and zinc mine, Faro Mine operated for 30 years until its last operator, Anvil Range Mining Corporation, went into receivership in 1998. In 2003, the authority to manage public lands and resources, including abandoned mine sites, was transferred to the Government of Yukon, under the Yukon Northern Affairs Organization Devolution Transfer Agreement and the Yukon Act (2002). The Agreement left the federal government financially liable for remediation of the Faro Mine, with the Government of Yukon responsible for the management of the remediation project. This joint governance model has posed challenges for the management of this complex, high-risk and large-scale project. To align the project management with best practices and effectively manage the risks, the Government of Yukon and the Government of Canada have negotiated an agreement to alter their roles and transition the site to full federal control. The agreement is expected to be signed in 2020–2021.

Contamination

Faro Mine is one of the largest and most contaminated sites in Canada. The site consists of waste-rock dumps, ore-processing facilities, water-treatment plants, tailings-disposal facilities, offices and other buildings. There are approximately 70 million tonnes of tailings and 320 million tonnes of waste rock across the mine complex.

These materials have the potential for both metal release and acid rock drainage, which occurs when sulphide-containing waste rock and tailings are exposed to air and water. This will become more problematic as the acid concentrations reach saturation and begin releasing in high concentrations into the environment. If unchecked, this would make the waters downstream in the Pelly River watershed highly toxic to fish. Orange-red precipitate from sulphide oxidation would coat stream beds, making them inhospitable to aquatic organisms and fish spawning. The tailings are contained behind three impoundments, but these are physically unstable. If the main tailings impoundment fails, the damage downstream could be irreparable.

Maintenance and closure

CIRNAC continues to manage the necessary care and maintenance activities at Faro Mine to protect human health, public safety and the environment. These activities include water pumping and treatment, stream diversions, building maintenance, continuous inspection and monitoring of dams, and site security.

In 2008, CIRNAC, the Government of Yukon and First Nations developed the Faro Mine Preferred Remediation Plan, which involves stabilizing and capping the waste rock and tailings, and instituting a permanent water-management and treatment system.

Notable achievements in the 2019–2020 fiscal year were:

This project was funded through Canada’s Federal Contaminated Sites Action Plan (FCSAP). FCSAP provides funding to assess and remediate federal contaminated sites and to reduce environmental and human-health risks from known federal contaminated sites. Starting in 2020–2021, this project will be funded through the Northern Abandoned Mine Reclamation Program.

Giant Mine Remediation Project

Location: Yellowknife, Northwest Territories
Custodian: Crown-Indigenous Relations and Northern Affairs Canada (CIRNAC)

The Giant Mine site covers approximately 900 hectares within the city limits of Yellowknife. The site lies along the western shore of Yellowknife Bay, an arm of Great Slave Lake. The site is a former gold mine that operated from 1948 to 2004. The operations led to significant contamination, including 237,000 tonnes of arsenic trioxide dust stored in 15 underground chambers. Moreover, 16 million tonnes of arsenic-contaminated tailings are stored in surface tailings ponds. The underground mine water, industrial buildings and surface soil are all contaminated with arsenic. Furthermore, because a creek passes through the mine site, above the arsenic chambers and adjacent to mine openings, there is a potential for the mine to flood.

Giant Mine was operated by private interests until its last operator, Royal Oak Mines Inc., went into receivership in April 1999. The Ontario Superior Court, under the provisions of the Bankruptcy and Insolvency Act (1985), then ordered the transfer of the property, including all environmental liability, from the interim receiver to CIRNAC, on behalf of the federal Crown.

Site stabilization and risk management

Since 2006, CIRNAC has performed or contracted a large amount of work on the site:

Carrying out the Giant Mine Environmental Assessment measures

In August 2014, the responsible Minister (then titled the Minister of Aboriginal Affairs and Northern Development) approved the decision to proceed with the Project. However, this approval was subject to 26 legally binding measures recommended through the environmental assessment, which altered the scope, timelines and cost of the Project. These measures required CIRNAC to perform an in-depth review of the Project, including extensive public and stakeholder scrutiny through numerous consultations. This will also allow the Project team to develop accurate cost estimates and determine the scope, schedule, cost, and risk implications of the measures. Some of the measures are interdependent; so, their integration into the project plan and the collection of site-specific data will continue for the rest of the definition phase of the Project, and will continue to inform the remediation strategy.

Measures completed to date include dealing with the negotiation of an environmental agreement and the creation of the Giant Mine Oversight Board (Measures 3, 4, 7 and 8), a final report on long-term funding options (Measure 6), investigating options for Baker Creek (Measure 11), and setting site-specific water-quality objectives (Measure 12).

The investments required to implement measures, such as the human health and ecological risk assessments and the outcomes of the quantitative risk assessment (Measure 5), are currently being made and will continue over the coming years.

Activities in 2019–2020

The past year’s activities largely focused on work supporting the water-licence process, advancement of several project design plans, advancement of several measures and additional stabilization work. Key activities included the following:

Socio-economic update

As part of CIRNAC’s commitment to promote socio-economic benefits and support reconciliation efforts with Indigenous peoples in Canada, the project team completed the following activities as they relate to the socio-economic aspect of the Project:

In 2020–2021, the Project plans to do the following activities:

The FCSAP Expert Support Departments (Environment and Climate Change Canada, Health Canada, and Fisheries and Oceans Canada) all participate in the Giant Mine Working Group on an ongoing basis.

This project was funded through Canada’s Federal Contaminated Sites Action Plan (FCSAP). FCSAP provides funding to assess and remediate federal contaminated sites and to reduce environmental and human-health risks from known federal contaminated sites. Starting in 2020–2021, this project will be funded through the Northern Abandoned Mine Reclamation Program.

United Keno Hill Mine Remediation Project

Location: Central Yukon
Custodian: Crown-Indigenous Relations and Northern Affairs Canada (CIRNAC)

The United Keno Hill Mines (UKHM) properties cover about 15,000 hectares near the former Elsa town site and the village of Keno City in central Yukon, approximately 350 km north of Whitehorse. An all-weather gravel highway connects the site to the town of Mayo, 60 km to the south. The site is within the traditional territory of the First Nation of Nacho Nyak Dun.

History

For over a century, the property operated under various ownership structures. From 1946 to 1989, 5,340,000 tons of ore were mined and milled, producing mainly silver, as well as lead and zinc. Production ceased in 1989. Attempts to re-open the mine in the 1990s were unsuccessful. On February 18, 2000, UKHM Limited filed for creditor protection. Several creditors tried to sell the assets but were unsuccessful, due to a lack of financing by potential buyers and the lack of a comprehensive plan to address the environmental issues on the site.

Environmental concerns associated with the site include:

Ownership and management

In June 2003, the property was declared abandoned under the Waters Act (Yukon) and Quartz Mining Act (Yukon). As a result, it was classified in April 2003 as a Type II Site under the Yukon Northern Affairs Program Devolution Transfer Agreement, which sets out a cooperative (federal and territorial) approach to managing the site. The Agreement identifies the Government of Canada as financially responsible for historic environmental liabilities, while the Government of Yukon is responsible for the ongoing management.

On April 6, 2004, the Supreme Court of Yukon appointed Pricewaterhouse Coopers Inc. as interim receiver and receiver-manager of the property. It had a mandate to sell the assets and develop a long-term solution to the environmental issues at the mine site. Pricewaterhouse Coopers advertised the property for sale in January 2005. An evaluation process involving Pricewaterhouse Coopers and the federal and territorial governments concluded in July 2005 with the selection of Alexco Resource Corporation as the preferred purchaser.

In December 2007, the Government of Yukon determined that its role as the government project manager and contracting authority was not appropriate. As the site was no longer abandoned, the Government of Yukon requested that CIRNAC assume the role of government project manager and contracting authority. The overall project is now managed through a project team. The team consists of Alexco’s wholly owned subsidiary Elsa Reclamation and Development Corporation (ERDC) and CIRNAC, with the Government of Yukon and the First Nation of Nacho Nyak Dun taking on secondary roles.

Maintenance and closure

To protect human health, public safety and the environment, the project team has undertaken basic care and maintenance activities. These include compliance with the water licence, water management (pumping and treatment), surface and groundwater monitoring, building maintenance, continuous inspection and monitoring of dams, and site security.

To prepare for closure of the site, CIRNAC and ERDC have completed a comprehensive environmental site assessment of the property. They also developed a report that outlines remedial options to address the human-health and environmental risks. Consultations with the Government of Yukon and the First Nation of Nacho Nyak Dun selected preferred closure options, which the governments endorsed in 2014–2015. These preferred closure options involve stabilizing and capping mine openings, waste rock and tailings, and instituting a permanent water-management and treatment system.

Through a collaborative review process, with input from CIRNAC, the Government of Yukon, and the First Nation of Nacho Nyak Dun, ERDC prepared a reclamation plan with costing to an indicative level (approved by the Government of Canada on March 15, 2018). The reclamation plan informed the development and submission of the project proposal on September 28, 2018 to the Yukon Environmental Socio-economic Assessment Board (YESAB) for environmental assessment. YESAB issued an evaluation report on February 24, 2020, recommending that the reclamation project proceed, subject to 29 terms and conditions. The environmental assessment process will conclude in 2020–2021 with a decision document prepared jointly by CIRNAC and the Government of Yukon.

Activities in 2019–2020 included compliance with the renewed care and maintenance water licence, advancing the reclamation plan and costing from the indicative level toward the substantive level, with detailed engineering design activities, and conclusion of the YESAB process.

In 2020–2021, the Project aims to submit a water-use licence application to the Yukon Water Board and finalize detailed engineering design activities, advancing the reclamation plan with costing to a substantive level.

Public Services and Procurement Canada provides support to CIRNAC as a member of the project team and reviews content from a procurement and constructability perspective.

This project was funded through Canada’s Federal Contaminated Sites Action Plan (FCSAP). FCSAP provides funding to assess and remediate federal contaminated sites and to reduce environmental and human-health risks from known federal contaminated sites. Starting in 2020–2021, this project will be funded through the Northern Abandoned Mine Reclamation Program.

Goose Bay Remediation Project

Location: 5 Wing Goose Bay, Happy Valley-Goose Bay, Newfoundland and Labrador
Custodian: Department of National Defence (DND)

DND is committed to environmental sustainability and minimizing the impact of military operations on the environment. In 2009, the Department launched the Goose Bay Remediation Project to reduce potential risks to human health and the environment posed by contamination at the base. Most of the contamination was attributed to the past handling and storage of various substances over decades of military activities. Contaminants identified at the base included:

DND applied lessons learned from its previous remediation projects to the approach for the Goose Bay Remediation Project. DND considered all contaminated areas collectively to understand the overall environmental condition of the site. Through this analysis, 10 areas were identified for remediation and risk management.

The 2019–2020 fiscal year saw the end of the Goose Bay Remediation Project, with the completion of project reports and long-term monitoring plans for sub-projects where they are required. Though the Project itself has ended, the contaminated sites will remain open, as work outside the scope of the initial project continues.

DND used several technologies throughout the project for various contaminants and site characteristics. Fuel-recovery techniques, such as dual-phase and multi-phase vapour extraction, removed free-phase fuel from the subsurface. The Department also used landfarming, chemical oxidation and soil washing to treat contaminated soil. DND also used risk-management approaches at various sites – for example, by implementing a light non-aqueous phase liquid (LNAPL) framework, as numerous sites have free-phase liquid hydrocarbons. DND has also installed containment measures at historic dump sites and capped contaminated sediment.

Since 2004, the Goose Bay Remediation Project has engaged stakeholders in discussions about the causes, effects and remediation of the contamination at Goose Bay. Participants in these discussions included local residents; Indigenous groups (Innu, Métis and Inuit); local environmental organizations; regional, national and international industry representatives and science and engineering experts; and all levels of  government. Engagement has taken place through a variety of public and one-on-one meetings, open houses, public presentations, industry workshops, and more. This engagement has been an important part of the project’s progress and will continue throughout the project.

In addition, a Technical Advisory Group comprised of FCSAP Expert Support Department representatives was established early in the Project. The principal function of the Technical Advisory Group was to provide a technical forum for the Project team to disseminate information on project status and specific activities to members who have an interest in the Project. Throughout the duration of the Project, members participated in annual site visits and meetings as well as providing technical review of various reports (i.e. human health/ecological risk assessments, LNAPL Management Frameworks) when requested by DND.

This project was funded through Canada’s Federal Contaminated Sites Action Plan (FCSAP). FCSAP provides funding to assess and remediate federal contaminated sites and to reduce environmental and human-health risks from known federal contaminated sites.

Esquimalt Harbour Remediation Project

Location: Victoria, British Columbia
Custodian: Department of National Defence (DND)

Launched in 2014, the Esquimalt Harbour Remediation Project is addressing historical contamination that accumulated in the harbour seabed during almost 200 years of commercial, military and industrial use. The Project is primarily funded by FCSAP, and is reducing ecological health risks associated with contaminated sediments in the harbour.

There are over 25 known contaminants in the harbour seabed, all of which exceed the Canadian Environmental Quality Guidelines for sediments. These contaminants include:

Remediation projects in the Esquimalt Harbour are an investment for the future and have resulted in significant economic and environmental benefits for the region. The Esquimalt Harbour remediation work has already reduced ecological risks associated with contaminated sediments, minimized the potential for recontamination, and provided economic development opportunities for surrounding communities. This remediation work has also helped clear the way for vital infrastructure upgrades at Canadian Forces Base Esquimalt, which are providing modern and functional dockyard infrastructure to support the long-term operational success of the Royal Canadian Navy.

Specifically, DND removed contaminated sediments from six areas of the harbour where DND operates: A Jetty, B Jetty, C Jetty, ML Floats, Y Jetty and Lang Cove. In addition to this project, cleanup has progressed at five other areas of Esquimalt Harbour, including: D Jetty, F/G Jetty, Ashe Head, Plumper Bay and Central Constance Cove. A harbour-wide risk-management plan is also being further refined to address any remaining contamination after the remediation of prioritized areas is completed.

During the 2019–2020 fiscal year, the sediment remediation work in Esquimalt Harbour passed several milestones:

This project was funded through Canada’s Federal Contaminated Sites Action Plan (FCSAP). FCSAP provides funding to assess and remediate federal contaminated sites and to reduce environmental and human-health risks from known federal contaminated sites.

Appendix A – Program administration

In the 2019–2020 fiscal year, $19.9 million was spent on program management activities for custodians, the Federal Contaminated Sites Action Plan (FCSAP) Secretariat, Treasury Board of Canada Secretariat, and expert support services. The breakdown of expenditures is shown in Table A.1. For a few departments, salary increases and retroactive payments due to the signature of new collective agreements, and changes to the rate used for employee benefit plans resulted in expenditures that exceeded the funding available. This has been paid by departmental funding not FCSAP.

Table A.1: Summary of FCSAP program management expenditures (2019–2020)
Department Available FCSAP funding ($) FCSAP expenditures ($) Variance ($)*
Agriculture and Agri-Food Canada 70,000 70,000 0
Correctional Service of Canada 149,891 149,891 0
Crown-Indigenous Relations and Northern Affairs Canada 2,675,000 2,675,000 0
Environment and Climate Change Canada - - -
Custodian 436,000 446,844 -10,844
Expert Support 2,534,980 3,131,779 -596,799
Secretariat 2,772,155 2,163,269 608,886
Fisheries and Oceans Canada - - -
Custodian 907,000 902,127 4,873
Expert Support 2,112,846 2,467,026 -354,180
Health Canada (expert support) 2,114,958 2,311,195 -196,237
Indigenous Services Canada 2,222,885 2,222,885 0
Jacques Cartier and Champlain Bridges Incorporated 0 0 0
National Capital Commission 102,000 102,000 0
National Defence 1,138,124 1,124,776 13,348
National Research Council of Canada 0 0 0
Natural Resources Canada 0 0 0
Parks Canada Agency 362,800 243,357 119,443
Public Services and Procurement Canada - - -
Custodian 200,000 192,842 7,158
Expert Support 565,000 564,817 183
Transport Canada 594,909 594,909 0
Treasury Board of Canada Secretariat 535,000 567,787 -32,787
VIA Rail Canada 0 0 0
Adjustments 594,048 0 594,048
Total expenditures 20,087,596 19,930,504 157,092

*Variance = available FCSAP funding - FCSAP expenditures

Key activities

Custodians

In the 2019–2020 fiscal year, custodians continued to manage the federal contaminated sites for which they are responsible. This included activities related to program planning and reporting and responding to information requests from the FCSAP Secretariat. Custodians developed annual and long-term workplans in preparation for Phase IV. 

Federal Contaminated Sites Action Plan Secretariat

In its role as Secretariat of the FCSAP program, Environment and Climate Change Canada (ECCC), with support from the Treasury Board of Canada Secretariat, continued to provide overall program oversight, support and administration.

In the 2019–2020 fiscal year, the FCSAP Secretariat performed activities in the following areas:

Treasury Board of Canada Secretariat

In 2019–2020, the Treasury Board of Canada Secretariat (TBS) supported ECCC in the management of the FCSAP program through the provision of strategic advice and guidance. In this role, TBS:

Expert support departments

In 2019–2020, expert support departments continued to develop guidance documents and deliver training on the management of federal contaminated sites. They also provided advice, conducted reviews of contaminated-site management projects, and promoted innovative and sustainable remediation technologies. Highlights on each of the departments’ activities are provided below.

Fisheries and Oceans Canada (DFO) provided scientific and technical advice to custodians on the management of their contaminated sites in relation to risks and impacts to fish and fish habitat. DFO conducted 115 site-classification reviews to confirm eligibility for FCSAP funding. It also conducted reviews of 34 technical documents in support of site assessment and remediation and risk management, to ensure that the potential impacts to fish and fish habitat were appropriately considered, and to promote compliance with relevant legislation and regulations.

To develop guidance material and provide expert advice and training on the management of FCSAP sites to custodial departments, DFO:

DFO also participated in FCSAP national and regional interdepartmental working groups and site-specific technical committees.

Environment and Climate Change Canada (ECCC) acted as a one-stop shop for all regional expert services to federal custodial departments for the management of their contaminated sites. The Department coordinated expert support activities in regions involving the other expert support departments; this included the important transition from interdepartmental regional working groups to RIPBs, project-update meetings and integrated work planning. ECCC reviewed the site-classification scores and site-specific technical reports submitted by custodians, and provided them with technical advice on the assessment, remediation and risk management of their contaminated sites. ECCC also disseminated information on program tools and guidelines, shared lessons learned, addressed custodians’ needs and oversaw national consistency.

Some specific achievements include the following:

  1. ECCC implemented the regional integrated planning boards.
  2. In collaboration with the other expert support departments, ECCC reviewed 115 site classifications submitted by custodians to confirm eligibility for funding and reviewed 50 technical documents to assist custodians with their assessment and remediation projects and to promote regulatory compliance.
  3. ECCC developed or contributed to the development or the updating of guidance documents on the management of FCSAP sites in the following areas:
    • ecological risk assessment: general guidance, defining background conditions and using background concentrations, ecological risk assessment for amphibians, and default wildlife-toxicity reference values
    • monitored natural attenuation in soil and groundwater
    • management of sites contaminated with light non-aqueous phase liquids
    • implementation of the Canada-wide standard for petroleum hydrocarbons in soil
    • management and treatment of values below the detection or quantification limit
    • provision of consistent expert advice
    • site classification reviews in Phase IV
  4. ECCC provided training to custodians and Expert Support Departments on the following subjects:
    • ecological risk assessment
    • Tiers I and II of the Canadian Council of Ministers of the Environment (CCME) Canada-wide standard for petroleum hydrocarbons in soil
    • the Species at Risk Act
    • ERA Module 5 on defining background conditions and using background concentrations
    • awareness about Indigenous peoples
    • reference values (CCME guidelines and other environmental quality criteria) and the National Classification System for Contaminated Sites and the Aquatic Sites Classification System

Health Canada continued to provide scientific and technical advice to federal custodians. This involved close collaboration with the other expert support departments on addressing current and emerging chemical issues, such as perfluorooctane sulfonate and perfluorooctanoic acid, as they relate to federal contaminated sites.

More specifically, Health Canada’s activities included:

Public Services and Procurement Canada (PSPC) continued to provide project management and procurement advice to federal custodians and developed tools, such as the FCSAP Project Readiness Form, in collaboration with a working group. PSPC collected and shared innovative and sustainable approaches with industry – for example, two new technology profiles are now available along with the existing ones. PSPC also addressed procurement issues and informed the private sector about the federal demand for services. Consequently, PSPC developed the FCSAP Interactive Map Tool to complement the FCSAP Phase IV Contaminated Sites Demand Forecast Analysis Report, which were presented to industry on five occasions across the country to approximately 400 participants. PSPC also organized the RPIC Federal Contaminated Sites Regional Workshop on PFAS and Other Emerging Contaminants, and hosted two short courses on dredging and materials management, both in Halifax. Finally, PSPC supported the integrated planning of FCSAP Phase IV by co-chairing the RIPBs.

Appendix B – Data tables

Table B.1: Available assessment funding and expenditures, by custodian (2019–2020)
Custodian Number of sites with activity Available FCSAP funding ($)* FCSAP assessment expenditure ($) Custodian expenditures (cost share) ($) Total expenditures ($)
AAFC 0 0 0 0 0
CIRNAC 0 0 0 0 0
CSC 0 0 0 0 0
DFO 3 254,590 230,425 57,606 288,031
DND 7 298,327 298,327 74,582 372,909
ECCC 2 128,000 128,000 42,047 170,047
ISC 62 973,826 973,826 279,832 1,253,658
JCCBI 0 0 0 0 0
NCC 16 150,233 150,233 37,558 187,791
NRC 0 0 0 0 0
NRCan 1 53,124 53,124 0 53,124
PCA 6 315,100 262,704 159,296 422,000
PSPC 0 0 0 0 0
TC 0 0 0 0 0
VIA Rail 0 0 0 0 0
Total 97 2,173,200 2,096,639 650,921 2,747,560

* Funding available = funding allocated from TB submission + any funding reprofiled/carried forward/cash managed from previous years + any funding transferred from another custodian (or minus any funding transferred to another custodian)

Table B.2: Available remediation funding and expenditures, by custodian (2019–2020)
Custodian Number of sites with activity Available FCSAP funding ($) FCSAP remediation expenditures ($) Custodian expenditures (cost share) ($) Total expenditures ($)
AAFC 1 92,000 92,000 27,056 119,056
CIRNAC 50 189,813,150 176,418,671 13,714,390 190,133,061
CSC 3 120,000 107,781 19,020 126,801
DFO 76 4,008,780 3,622,925 652,851 4,275,776
DND 83 107,630,753 76,554,161 2,562,984 79,117,145
ECCC 9 37,369,230 22,389,636 1,892,150 24,281,786
ISC 69 24,044,688 24,044,688 5,380,325 29,425,013
JCCBI 2 3,852,911 1,358,494 239,734 1,598,228
NCC 19 9,881,601 3,381,924 593,523 3,975,447
NRC 0 0 0 0 0
NRCan 1 335,721 20,305 0 20,305
PCA 22 4,268,400 2,808,469 377,527 3,185,996
PSPC 20 26,485,757 21,793,372 3,298,595 25,091,967
TC 33 30,375,277 25,560,076 1,555,704 27,115,780
VIA Rail 0 0 0 0 0
Total 388 438,278,268 358,152,502 30,313,859 388,466,361
Table B.3: Program-level summary of available FCSAP funding (2019–2020)
FCSAP funds Program management ($) Assessment ($) Remediation ($) Total ($)
FCSAP funding approved for 2019–2020 19,211,739 1,932,450 281,834,847 302,979,036
FCSAP funding brought forward from previous fiscal years 235,924 652,251 156,077,805 156,965,980
FCSAP funds received from another custodian (+) 0 0 0 0
FCSAP funds given to another custodian (-) 0 0 0 0
FCSAP funds internally transferred to another stream (assessment, remediation, program management) (±) 45,885 -411,501 365,616 0
Adjustments 594,048 0 0 594,048
Total available FCSAP funding 20,087,596 2,173,200 438,278,268 460,539,064
Table B.4: Program-level summary of FCSAP expenditures and variance (2019–2020)
FCSAP funds Program management ($) Assessment ($) Remediation ($) Total ($)
Total available FCSAP funding 20,087,596 2,173,200 438,278,268 460,539,064
FCSAP expenditures 19,930,504 2,096,639 358,152,502 380,179,644
Total variance 157,092 76,561 80,125,766 80,359,420
Explanation of variance: - - - -
FCSAP funds reprofiled to a future year 13,348 0 59,41`0,026 59,423,374
FCSAP funds carried forward to a future year 119,443 75,510 9,662,301 9,857,254
Internal cash-management of FCSAP funds to a future year 0 0 8,334,196 8,334,196
Lapsed FCSAP funds 24,301 1,051 2,719,246 2,744,598
Table B.5: List of remediation sites funded by FCSAP (2019–2020)
Custodian Site name Federal site identifier Province/ Territory FCSAP
remediation expenditures ($)
Custodian expenditures ($)
AAFC The Atlantic Food and Horticulture Research Centre 02731004 NS 92,000 27,056
CIRNAC Arctic Gold and Silver C2506001 YT 987,479 174,261
CIRNAC BAF 5 - Resolution Island C1017001 NU 2,270,789 400,727
CIRNAC Bathurst Island - Bent Horn (Cameron Island) 00024167 NU 329,077 58,072
CIRNAC Bathurst Island - Île Vanier 00000282 NU 476,253 84,045
CIRNAC Bathurst Island - N-12 Allison R 00025589 NU 224,817 39,674
CIRNAC Bathurst Island - Young Inlet (east of Humphries Hill) 00000266 NU 131,414 23,191
CIRNAC Beaulieu Mine (John Lake; Brandy, Irene, Norma, Tungsten and Gold Mines Limited) 00023544 NT 75,115 13,256
CIRNAC Blanchet Island Mine (HRL Claims) 00000402 NT 94,826 16,734
CIRNAC Bullmoose Lake Mine (formerly Mann Lake) 00000068 NT 237,029 41,829
CIRNAC Burnt Island (Ardogo, Good Hope, Goo, Giant Bay, Gordon Lake) 00023547 NT 37,601 6,635
CIRNAC CAM C - Matheson Point C1001001 NU 987,466 174,259
CIRNAC CAM E - Keith Bay C1003001 NU 1,644,350 290,179
CIRNAC Camlaren Mine (Hump Vein) 00000162 NT 376,004 66,354
CIRNAC Canol Trail 00025577 NT 2,682,677 473,414
CIRNAC Cantung Mine (Canada Tungsten Mine, Tungsten Mine) 00000154 NT 8,600,670 0
CIRNAC Chipp Lake Mine (Cliff Lake, Eileen) 00023777 NT 50,471 8,907
CIRNAC Clinton Creek C1052001 YT 1,808,729 319,188
CIRNAC Colomac Mine (Baton Lake, Indin Lake, Goldcrest, Grizzly Bear) C1047001 NT 385,002 67,942
CIRNAC Contact Lake Mine (International Uranium, M Group, Sam, Kayo) C1051001 NT 11,856 0
CIRNAC El Bonanza Mine (Bonanza East, Bonanza Vein, Spud Vein) 00000076 NT 8,169 0
CIRNAC Faro Mine C2503001 YT 96,193,244 10,688,138
CIRNAC FOX D - Kivitoo C1021001 NU 1,364,435 240,783
CIRNAC Giant Mine (Giant Yellowknife Mines; Royal Oak Mines; A, B & C Shafts) C1048001 NT 46,421,077 0
CIRNAC Goodrock Mine (Gordon Lake) 00000351 NT 37,600 6,635
CIRNAC High Arctic - Dale Payne 00000400 NU 105,533 18,623
CIRNAC Joon Mine (Campbell Lake, June Mine, Strike Lake) 00000405 NT 73,656 12,998
CIRNAC Ketza River C2504001 YT 311,353 54,945
CIRNAC Knight Bay (Kidney Pond) 00024120 NT 150,402 26,541
CIRNAC Lougheed Island (L1) 00000288 NU 21,990 3,881
CIRNAC Mount Nansen Mine C2505001 YT 2,501,912 0
CIRNAC North Rankin Inlet C1054001 NU 144,407 25,484
CIRNAC Outpost Island C1038001 NT 142,239 25,101
CIRNAC PIN D - Ross Point C1040001 NU 96,174 16,972
CIRNAC Port Radium Mine / Eldorado Mine (LaBine Point) C1046001 NT 217,650 38,409
CIRNAC Rea Point (1) / Melville Island 00000231 NU 21,991 3,881
CIRNAC Roberts Bay Mine C1056001 NU 100,269 17,694
CIRNAC Romulus - Panarctic C-42 Well Site 00024258 NU 10,996 1,940
CIRNAC Ruth Gold Mine C1033001 NT 203,355 35,886
CIRNAC Sawmill Bay / Great Bear Lake 00000403 NT 34,688 0
CIRNAC Spectrum Lake (AA/BB, Benventum) 00023964 NT 226,530 39,976
CIRNAC Storm Mine (Consolation Lake 2) 00023548 NT 39,423 6,957
CIRNAC Terra #1 (North Mine, Silver Bear Properties) C1010001 NT 947,975 0
CIRNAC Terra #2 (Northrim Mine, Silver Bear Properties, Silver Bay, White Eagle) C1011001 NT 91,589 0
CIRNAC Terra #3 (Norex Mine, Silver Bear Properties, Caeser Silver) C1012001 NT 78,788 0
CIRNAC Terra #4 (Smallwood Mine, Silver Bear Properties) C1013001 NT 32,131 0
CIRNAC Thor Island / Panarctic Oils / H-28 Well 00000230 NU 21,990 3,881
CIRNAC Tundra-Taurcanis Mine (Bulldog Yellowknife Gold Mines, Tamcanis Mines Limited, Tundra Gold Mines) C1035001 NT 1,020,926 0
CIRNAC United Keno Hill Mine C2509001 YT 3,326,886 0
CIRNAC Venus Tailings / Mill Site C2507001 YT 946,868 167,094
CIRNAC West Bay Mine (Black Ridge) (DAF) (MQ) C1037001 NT 112,801 19,906
CSC 441-L02 Collins Bay - Southern Landfill (near Front Road) 00024662 ON 48,953 8,639
CSC 441-L03 Frontenac Institution - Landfill #3 at Quarry Road and Little Cataraqui Creek Tributary 00012990 ON 4,106 725
CSC 530-L01 Drumheller - Former Landfill at South West 00013023 AB 54,721 9,657
DFO Addenbroke Island 67677001 BC 4,218 750
DFO Anchor Point (waterlot - DFRP# 01693) 01693002 NL 56,903 10,700
DFO Bartletts Harbour (waterlot - DFRP# 01660) 00019008 NL 57,728 10,845
DFO Bird Rock - light station and other buildings 05077003 QC 27,171 4,795
DFO Boat Bluff 67678001 BC 4,218 750
DFO Bonilla Island - sector light 19482001 BC 4,218 750
DFO Bragg's Island (waterlot) 00019030 NL 75,391 13,962
DFO Brion Island - light station and concrete slab 05078001 QC 2,191 387
DFO Burin (waterlot - Collins Cove - Parcel 90-1 & Ship Cove 4) 00019039 NL 76,712 14,195
DFO Cabot Head - old lighthouse dwelling, lightkeepers’ dwelling, waste pile 36440002 ON 522,614 92,226
DFO Cape Beale 17809001 BC 4,218 750
DFO Cape Gaspé - light station 05203001 QC 33,048 5,832
DFO Cape Mudge 18225001 BC 4,218 750
DFO Cape Scott - main station 19007001 BC 4,218 750
DFO Carmanah Point 17533001 BC 4,218 750
DFO Champney's West (waterlot property) 01085002 NL 119,454 21,738
DFO Chance Cove (waterlot) 00019054 NL 64,252 11,997
DFO Change Islands (coastal wharf site - waterlot - DFRP# 01376) 00019056 NL 23,487 4,803
DFO Change Islands (fish plant site - waterlot - DFRP# 31346) 00022958 NL 23,487 4,803
DFO Channel-Port aux Basques (waterlot) 00748001 NL 48,010 9,130
DFO Chatham Point 18090001 BC 4,218 750
DFO Chrome Island - range light 18001001 BC 4,218 750
DFO Conception Harbour (tidal zone - DFRP# 26796) 00019062 NL 35,290 6,886
DFO Conception Harbour (waterlot - DFRP# 26796) 00023129 NL 35,290 6,886
DFO Corossol Island - minor shore light 00000877 QC 8,429 1,487
DFO Country Island - hydrocarbons and metals near former oil pump 00013071 NS 219,500 40,000
DFO Cove Island - main dump 00024545 ON 30,618 5,403
DFO Cove Island - soil around lighthouse and associated structures 00000863 ON 91,853 16,220
DFO Cow Head (waterlot) 01633002 NL 58,922 11,056
DFO Discovery Mountain - fuel spill in fuel filling area 72020002 BC 12,953 2,250
DFO Dryad Point 67679001 BC 4,218 750
DFO Egg Island 67680001 BC 4,218 750
DFO Entrance Island 17611001 BC 4,218 750
DFO Estevan Point 17813001 BC 4,218 750
DFO Fair Haven (wharf site - DFRP# 23017 - waterlot) 00019086 NL 65,058 12,139
DFO Fortune (fish plant wharf - DFRP# 00494 - uplands) 00490002 NL 30,544 6,048
DFO Gereaux Island (Britt IRB) - waste dump - south 00024547 ON 64,852 11,445
DFO Great Duck Island – lightstation / engine building / dump - metals, PH, PAH 07503001 ON 124,405 21,954
DFO Green Island 67681001 BC 4,218 750
DFO Griffith Island - vicinity of lighthouse 58231001 ON 29,912 5,279
DFO Heath Point - trailers, light station, heliport and tanks 08028002 QC 1,530 270
DFO Île Rouge - light station 08204001 QC 8,554 1,510
DFO Ivory Island 67682001 BC 4,218 750
DFO Jannacks Narrows - light tower (former and current) 83474001 ON 59,660 10,528
DFO Jerseyside (waterlot) 00013081 NL 58,817 11,037
DFO Kraut Point (Riverport) (hydrocarbon and metal impacts soil and groundwater) 00017804 NS 171,500 30,265
DFO Lamèque (petroleum/PAH impacts in soil/groundwater/sediment - historic fuel spills) 04939001 NB 34,000 6,000
DFO Langara Island 19401001 BC 4,218 750
DFO Lennard Island 17812001 BC 4,218 750
DFO Lucy Islands - hydrocarbon contamination near the lighthouse 84377001 BC 128,048 22,500
DFO Lunenburg - Fishermen's Wharf (impacted sediments - PAHs/cadmium) 00012643 NS 86,500 15,000
DFO Mathers Creek - enhancement 00021003 BC 127,500 22,500
DFO McCoy Cove - sector light 00020345 BC 16,264 3,000
DFO McInnes Island 67683001 BC 4,218 750
DFO Melocheville (rear range light) 82065001 QC 1,501 265
DFO Merry Island 18460001 BC 4,218 750
DFO Minstrel Island - docks and floating docks - waterlot 00021370 BC 37,600 7,500
DFO Nootka Island 18086001 BC 4,218 750
DFO Pachena Point 17810001 BC 4,218 750
DFO Pallant Creek Hatchery 00021044 BC 139,978 22,500
DFO Pine Island 19125001 BC 4,218 750
DFO Pointe des Grondines - upstream, front range light 06155001 QC 1,501 265
DFO Powell River South 00012646 BC 42,500 7,500
DFO Pulteney Point 19084001 BC 4,218 750
DFO Quatsino, Kains Island - assistant keeper's house & engine room 19006001 BC 4,218 750
DFO Red Harbour (waterlot) 00019291 NL 59,356 11,132
DFO Rivière-St-Paul (Esquimaux Island, SCH, waterlot, sediments) 00022172 QC 18,185 3,209
DFO Savage Cove (waterlot) 55767002 NL 57,991 10,892
DFO Scarlett Point 19052001 BC 4,218 750
DFO Steveston (Paramount) - maintenance area (Building 33) 16760001 BC 210,493 37,500
DFO Trial Islands 17330001 BC 4,218 750
DFO Valleyfield (waterlot property) 01261002 NL 61,236 11,464
DFO Wesleyville (main wharf waterlot property) 01267003 NL 54,572 10,288
DFO Whitby (waterlot) 27530001 ON 99,361 17,534
DFO Yellowknife Wharf (parking area) 00016201 NT 60,792 10,728
DFO Zeballos 00021460 BC 37,737 7,500
DND 5 Wing Goose Bay - Canadian Side & Northside 01822018 NL 1,319,007 0
DND 5 Wing Goose Bay - Dome Mountain, RCAF and Camp Sites (5 W) N7075001 NL 2,825,887 0
DND 5 Wing Goose Bay - Lower Tank Farm (LTF 2000 Series) 01822094 NL 4,045,274 0
DND 5 Wing Goose Bay - Main Gate & Hamilton River Road Plume (UPL 16000 series) 5W N7077001 NL 571,688 0
DND 5 Wing Goose Bay - South Escarpment Landfills (SES 1000 Series) 01822087 NL 333,247 0
DND 5 Wing Goose Bay - South Escarpment Stillwaters (SES 1100 series) 00008429 NL 233,707 0
DND 5 Wing Goose Bay - Survival Tank Farm (STF 3000 Series) 01822086 NL 188,552 0
DND 8 W Fire Fighting Training Area / Hazardous Materials Storage 09540012 ON 195,001 34,412
DND Adminstrative Area - Domaine, Lozeau and Bougainville Islands 06294001 QC 74,099 13,076
DND Aerodrome - West of runway 18-36 07930004 QC 127,639 22,525
DND AH-1 Albert Head Barracks - West Central Region 17431004 BC 64,557 11,392
DND Alert B-145 Cat House 20247019 NU 40,104 7,077
DND Alert Baker's Dozen 20247035 NU 34,170 6,030
DND Alert Main Station 20247006 NU 95,200 16,800
DND AMDU Landfill Site 09540010 ON 101,222 17,863
DND Atmosphere simulation (former dump), DRDC - south 29757003 QC 86,611 15,284
DND Cadet Camp Landfill & Firing Range 00008347 ON 138,910 24,514
DND Castor centre PHL T-610 05906059 QC 34,553 6,098
DND Central Heating Plant 07930011 QC 54,531 9,623
DND CFAD Bedford (801) - Ridge Landfill 02859001 NS 37,308 6,584
DND CFAD Bedford (803) - Former Landfill (West of B162) 02859003 NS 25,357 4,475
DND CFB Petawawa RTA - Area 8 (Demolition Range) 00008335 ON 8,602 1,518
DND CFB Shearwater (207) - Former USTs at Hangar 3 02863007 NS 1,774 313
DND CFB Shearwater (211) - Landfill 1 02863011 NS 20,784 3,668
DND CFB Shearwater (213) - Landfill 3 02863013 NS 36,919 6,515
DND CFB Shearwater (214) - Landfill 4 02863014 NS 24,604 4,342
DND CFB Shearwater (216) - Fill Area West of Alpha Taxiway 02863016 NS 162,130 28,611
DND CFB Shearwater (223) - Building 4 and H (POL) 02863023 NS 24,038 4,242
DND CFB Shearwater (229) - Upper Fuel Compound, Upgradient Dumping Area 02863029 NS 10,927 1,928
DND CFB Shearwater (230) - Building 31, 31A, 31B, 32 (Mobl Spprt Maint) 02863030 NS 30,912 5,455
DND CFS St. John's (4710) - Cambrai Rifle Range 00273001 NL 52,636 9,289
DND CFS St. John's (5210) - Shea Heights Tank Farm 32044002 NL 65,402 11,541
DND COL-FOD Colwood Former Fuel Oil Depot (FOD) North Area 00024819 BC 104,550 18,450
DND Comox FFTA 17970012 BC 1,219,072 215,130
DND DCD School (907) - Fire Fighting Training Area 03044007 NS 107,250 18,926
DND DEW Line - CAM-1 Jenny Lind Island C7017001 NU 220,429 38,899
DND DEW Line - DYE-M Cape Dyer C7026001 NU 393,354 0
DND DEW Line - FOX-3 Dewar Lakes C7023001 NU 12,231 2,158
DND DEW Line - FOX-4 Cape Hooper C7024001 NU 2,644 467
DND DEW Line - PIN-3 Lady Franklin Point C7016001 NU 225,720 39,833
DND DEW Line - PIN-4 Byron Bay C7015001 NU 211,823 37,381
DND Dockyard Annex (1101) - Hazardous Storage Area (W45) 03009015 NS 12,820 2,262
DND DRDC (1408) - Waste solvent dumping (east of building 2) 03013004 NS 60,072 10,601
DND Dry material (former dump for), DRDC - south 29757002 QC 210,095 37,076
DND DY-4 Dockyard FMF Consolidation 17403003 BC 824,395 154,034
DND EME Shop, Building 113 and Skeet Range 09540005 ON 362,601 63,988
DND ESQ-1 - Esquimalt Harbour 17403011 BC 52,119,868 0
DND Fire Fighting Training Area #1 11022039 ON 279,869 49,389
DND Firefighter training area 07930007 QC 640,091 112,957
DND Former CFS Moisie - Site Admin N7096001 QC 109,741 19,366
DND Former dump Château Road 05906047 QC 3,825 675
DND Former skeet range 00008337 QC 24,854 4,386
DND Hangar 5 & 6 00024810 ON 106,837 18,854
DND HMCS Champlain - Chicoutimi Naval Reserve 69920001 QC 161,035 28,418
DND Land adjacent to the former well P-2 05906061 QC 3,273 578
DND Le RHIN former demolition area 05906041 QC 4,378 773
DND MA-1a Masset Skeet Range 00008529 BC 55,250 9,750
DND Marsh - North of highway 170 07930017 QC 191,767 33,841
DND MDR (former dump for), DRDC - Trials 29757006 QC 9,041 1,595
DND Moras Island 06872002 QC 40,500 7,147
DND Mountain View - Inner Landfill Site 34476004 ON 489,589 86,398
DND NAD-1 Naden Jr NCM 00000965 BC 51,634 9,112
DND NAD-10 Naden South - East of Admirals 00008616 BC 51,658 9,192
DND New ATESS Refinishing Shop 00008541 ON 1,586,975 280,054
DND Niagara-on-the-Lake Rifle Range 10626002 ON 11,013 1,944
DND Plateau (demolition site), DRDC - Trials 29757009 QC 12,172 2,148
DND POL Compound 04089001 NB 17,680 3,120
DND POL Compound - area of removed tanks 09540020 ON 24,427 4,311
DND POL tank farm 07930009 QC 431,704 76,183
DND Royal Roads Landfill Area 15684029 AB 40,969 7,230
DND RV Compound 11378001 ON 87,942 15,519
DND Saglek Bay Sediments N7040001 NL 4,250 750
DND Sector for Building 307, DRDC - Trials 29757005 QC 20,561 3,628
DND Shirley Rd. Dump 04089010 NB 1,016 179
DND Small calibre (former dump), DRDC - south 29757001 QC 229,343 40,472
DND Stony Point (former Camp Ipperwash) 10829001 ON 622,314 109,820
DND Stream draining former DDT site in Farnham 00008562 QC 138,675 24,472
DND Sudbury Armoury 00008448 ON 25,889 4,569
DND TCE Contamination - Highbury Complex 10868001 ON 3,579,062 631,599
DND TCE Contamination - Valcartier 29757007 QC 263,036 46,418
DND Training areas, former CARPIQUET firing range 05906044 QC 1,288 227
DND Wellington Anti-Tank Range 00008409 NB 527 93
DND Wolseley Barracks 10869001 ON 79,705 14,066
ECCC Eureka High Arctic Weather Station 00002747 NU 159,124 28,081
ECCC Fort Reliance 00002376 NT 4,145,926 731,634
ECCC Iqaluit Canadian Ice Services Building 1082 00011582 NU 25,050 4,421
ECCC Lansdowne House 12204000 ON 46,078 8,131
ECCC Mould Bay (HAWS) 70944001 NT 6,126,515 1,081,150
ECCC Pacific Environmental Centre N/A BC 11,667,453 0
ECCC Sable Island 07610122 NS 59,075 8,323
ECCC Shamattawa River at outlet of Shamattawa Lake 00002361 ON 132,094 23,311
ECCC Wilmer Marsh (dumping area) 16096079 BC 28,321 4,509
ISC 79 - Atikamekw d'Opitciwan - 06105 - OBEDJIWAN 28 - 0301032102 05205004 QC 48,076 8,484
ISC 79 - Atikamekw d'Opitciwan - 06105 - OBEDJIWAN 28 - 0302543305 00005225 QC 8,964 1,582
ISC 126 - Couchiching First Nation - 06241 - COUCHICHING 16A - 3000014095 05152001 ON 422,615 85,000
ISC 128 - Naicatchewenin - 06243 - RAINY LAKE 17A - 3000026995 05178001 ON 25,741 6,435
ISC 136 - Wasauksing First Nation - 06205 - PARRY ISLAND FIRST NATION - 3000075096 00025832 ON 95,500 0
ISC 136 - Wasauksing First Nation - 06205 - PARRY ISLAND FIRST NATION - 3000037495 05175006 ON 2,130,839 50,000
ISC 143 - Attawapiskat - 06259 - ATTAWAPISKAT 91 - 3000051796 00006891 ON 393,098 68,370
ISC 164 - Mohawks of the Bay of Quinte - 06217 - TYENDINAGA MOHAWK TERRITORY - ON04878217 00026491 ON 558,963 32,880
ISC 183 - Eabametoong First Nation - 06296 - FORT HOPE 64 - 3000025795 00000458 ON 125,897 22,217
ISC 183 - Eabametoong First Nation - 06296 - FORT HOPE 64 - 3000025895 00000457 ON 169,720 29,950
ISC 183 - Eabametoong First Nation - 06296 - FORT HOPE 64 - 3000025995 05157001 ON 83,553 14,745
ISC 183 - Eabametoong First Nation - 06296 - FORT HOPE 64 - 3000026095 05157006 ON 56,698 10,005
ISC 183 - Eabametoong First Nation - 06296 - FORT HOPE 64 - 3000026395 05157007 ON 15,366 2,712
ISC 201 - Serpent River - 06185 - SERPENT RIVER 7 - 3000047696 05185001 ON 301,077 82,445
ISC 204 - North Caribou Lake - 06315 - WEAGAMOW LAKE 87 - 0402702806 00006671 ON 57,267 10,106
ISC 204 - North Caribou Lake - 06315 - WEAGAMOW LAKE 87 - 0402705206 00006675 ON 68,720 12,127
ISC 204 - North Caribou Lake - 06315 - WEAGAMOW LAKE 87 - 3000005894 05190003 ON 118,939 20,989
ISC 204 - North Caribou Lake - 06315 - WEAGAMOW LAKE 87 - 3000020095 05190006 ON 48,456 8,552
ISC 204 - North Caribou Lake - 06315 - WEAGAMOW LAKE 87 - 3000020395 05190007 ON 110,128 19,434
ISC 207 - Bearskin Lake - 06319 - BEARSKIN LAKE - 0403509708 00006985 ON 2,671,364 471,417
ISC 207 - Bearskin Lake - 06319 - BEARSKIN LAKE - 0404783610 00007862 ON 5,939 1,048
ISC 207 - Bearskin Lake - 06319 - BEARSKIN LAKE - 3000006994 05147001 ON 11,267 1,989
ISC 207 - Bearskin Lake - 06319 - BEARSKIN LAKE - 3000017495 05147006 ON 6,026 1,064
ISC 207 - Bearskin Lake - 06319 - BEARSKIN LAKE - 3000054196 00007881 ON 33,786 5,962
ISC 207 - Bearskin Lake - 06319 - BEARSKIN LAKE - 3000117000 00007891 ON 6,524 1,151
ISC 208 - Pikangikum - 06320 - PIKANGIKUM 14 - 3000007494 05176001 ON 1,144,919 257,372
ISC 208 - Pikangikum - 06320 - PIKANGIKUM 14 - 3000007994 05176004 ON 143,115 32,172
ISC 208 - Pikangikum - 06320 - PIKANGIKUM 14 - 3000008294 05176006 ON 143,115 32,171
ISC 211 - Sandy Lake - 06323 - SANDY LAKE 88 - 3000036995 05182004 ON 106,823 0
ISC 213 - Muskrat Dam Lake - 06327 - MUSKRAT DAM LAKE - 3000008694 05170001 ON 180,651 189,276
ISC 213 - Muskrat Dam Lake - 06327 - MUSKRAT DAM LAKE - 3000008794 05170002 ON 203,232 212,937
ISC 213 - Muskrat Dam Lake - 06327 - MUSKRAT DAM LAKE - 3000009094 05170004 ON 67,744 70,978
ISC 217 - Wunnumin - 06333 - WUNNUMIN 1 - 3000035695 05194003 ON 25,064 4,423
ISC 217 - Wunnumin - 06333 - WUNNUMIN 1 - 3000035995 05194004 ON 9,270 1,636
ISC 220 - Nipissing First Nation - 06152 - NIPISSING 10 - 3000034495 00006318 ON 170,000 30,000
ISC 239 - Neskantaga First Nation - 06355 - LANSDOWNE HOUSE INDIAN SETTLEMENT - 3000028795 05164002 ON 616,220 96,269
ISC 239 - Neskantaga First Nation - 06355 - LANSDOWNE HOUSE INDIAN SETTLEMENT - 3000029095 05164005 ON 47,163 8,323
ISC 239 - Neskantaga First Nation - 09213 - NESKANTAGA - ON04790610 00007873 ON 95,352 16,827
ISC 239 - Neskantaga First Nation - 09213 - NESKANTAGA - ON04795110 00008212 ON 17,768 3,136
ISC 240 - Webequie - 06337 - WEBIQUI INDIAN SETTLEMENT - 0404167609 00007586 ON 16,616 2,932
ISC 240 - Webequie - 06337 - WEBIQUI INDIAN SETTLEMENT - 0404167709 00007587 ON 193,213 34,096
ISC 240 - Webequie - 06337 - WEBIQUI INDIAN SETTLEMENT - ON04827711 00008210 ON 3,195 564
ISC 270 - Little Grand Rapids - 06376 - LITTLE GRAND RAPIDS 14 - MB04839112 19118041 MB 247,350 43,650
ISC 293 - Swan Lake - 06412 - SWAN LAKE 7 - MB04789710 00007866 MB 10,990 1,939
ISC 297 - Garden Hill First Nations - 06448 - GARDEN HILL FIRST NATION - 4000018696 00025923 MB 211,443 37,313
ISC 298 - St. Theresa Point - 09147 - ST THERESA POINT - 0503606908 00007045 MB 910,452 160,668
ISC 298 - St. Theresa Point - 09147 - ST THERESA POINT - 4000038700 00006601 MB 40,375 7,125
ISC 306 - Tataskweyak Cree Nation - 06461 - SPLIT LAKE 171 - 0502224705 00000532 MB 560,720 80,346
ISC 308 - Barren Lands - 06458 - BROCHET 197 - 0501870404 05260005 MB 61,200 10,800
ISC 311 - Mathias Colomb - 06456 - PUKATAWAGAN 198 - 4000002393 00006814 MB 36,542 5,459
ISC 351 - Fond du Lac - 00178 - FOND DU LAC 231 - 0603056806 00006788 SK 1,897,827 398,970
ISC 395 - Flying Dust First Nation - 06584 - FLYING DUST FIRST NATION 105 - SK04876417 00026013 SK 3,603,688 635,945
ISC 448 - Dene Tha' - 06671 - HAY LAKE 209 - AB04884218 00026543 AB 1,697,123 297,718
ISC 471 - Stoney - 06642 - STONEY 142-143-144 - 6000004094 05131002 AB 24,127 6,032
ISC 531 - Gitanmaax - 06755 - GITANMAAX 1 - 7000099898 00006404 BC 15,300 2,700
ISC 540 - Kitasoo - 07886 - KITASOO 1 - BC04825611 00008201 BC 90,012 9,300
ISC 554 - Tla'amin Nation - 07961 - SLIAMMON 1 - 7000055295 05379001 BC 60,350 10,650
ISC 555 - Squamish - 07969 - CAPILANO 5 - BC04886418 00026582 BC 255,000 45,000
ISC 558 - Aitchelitz - 08006 - AITCHELITCH 9 - BC04847813 00025861 BC 116,450 20,550
ISC 562 - Skatin Nations - 08015 - SKOOKUMCHUCK 4 - 0904500209 00007708 BC 29,920 9,530
ISC 562 - Skatin Nations - 08015 - SKOOKUMCHUCK 4 - 0904500309 00007709 BC 29,920 9,530
ISC 562 - Skatin Nations - 08015 - SKOOKUMCHUCK 4 - 0904501609 00007711 BC 29,920 9,530
ISC 562 - Skatin Nations - 08015 - SKOOKUMCHUCK 4 - 7000081096 05092008 BC 29,920 9,530
ISC 562 - Skatin Nations - 08016 - SKOOKUMCHUCK 4A - 0904501809 00007713 BC 29,920 9,530
ISC 564 - Kwantlen First Nation - 08029 - WHONNOCK 1 - BC04791810 00008251 BC 212,500 37,500
ISC 569 - Semiahmoo - 08047 - SEMIAHMOO - 0903374908 00006932 BC 1,545,000 255,000
ISC 584 - Cheam - 08081 - CHEAM 1 - BC04898819 00026637 BC 42,500 7,500
ISC 648 - Snuneymuxw First Nation - 06817 - NANAIMO RIVER 3 - 0903801608 00007210 BC 1,470,106 1,291,784
ISC 688 - Tk'emlúps te Secwépemc - 07173 - KAMLOOPS 1 - BC04879817 00026493 BC 28,050 4,950
JCCBI Parcel 1 00000903 QC 941,155 166,086
JCCBI Parcel 3 00002327 QC 417,338 73,648
NCC 150 Middle Street 00024007 ON 148,307 26,172
NCC 160 Middle Street 00023977 ON 607 107
NCC 160 Middle Street 00027601 ON 607 107
NCC 161 Middle Street 00027616 ON 607 107
NCC Bayview 00022831 ON 90,224 15,922
NCC Hurdman North 00022822 ON 18,753 3,309
NCC Hurdman West 00022836 ON 15,755 2,780
NCC Hurdman West 00023354 ON 2,630 465
NCC Kingsview Park, Ottawa 00023326 ON 653,315 115,291
NCC Middle Street 00027602 ON 1,711,343 302,002
NCC Middle Street 00027617 ON 607 107
NCC Middle Street to Booth Street 00027615 ON 607 107
NCC Montcalm 00022813 QC 56,013 9,884
NCC Montcalm 00022815 QC 7,330 1,293
NCC Ottawa River 00027614 ON 516,079 91,073
NCC Pine Grove, Ottawa 00023325 ON 18,629 0
NCC Ridge Road Former Landfill 00000001 ON 22,270 3,930
NCC Victoria Island 00023306 ON 64,640 11,407
NCC Victoria Island 00023990 ON 53,602 9,459
NRCan 555 Booth Street 58475001 ON 20,305 0
PCA A1 Waste Transfer Station 15412001 AB 11,178 6,009
PCA Abandoned Light Station 00023460 BC 8,018 65
PCA Active Pass 00023457 BC 138,723 5,875
PCA B1 Trade Waste Pit 15412015 AB 10,818 4,181
PCA C2 JNP Tangle Creek Compound 15412017 AB 10,909 4,719
PCA Cascade Landfill 15404013 AB 25,891 3,444
PCA D26 Little Lake to Rice Lake 09731004 ON 85,236 6,692
PCA Fort Conger Historic Site 00008328 NU 14,771 6,287
PCA Forty Mile Creek Landfill 15404044 AB 4,665 8,194
PCA Garage 20106005 YT 384,000 62,626
PCA Garden River Old Dump 15841002 AB 117,137 7,453
PCA Kingston Inner Harbour Marsh 00023391 ON 121,275 21,539
PCA Maintenance Compound 10667002 ON 77,727 19,201
PCA Major Shore Light 00023458 BC 18,149 0
PCA McLean's Point 17800008 BC 114,667 8,381
PCA Rogers Pass Maintenance Compound 18752001 BC 495,189 29,047
PCA Russell Island Homestead 00024299 BC 4,000 65
PCA Saturna Island Light Tower 00023462 BC 89,063 65
PCA Site 13.3 06959007 QC 495,100 93,891
PCA Walker Acquisition 00024680 SK 246,128 22,354
PCA Waste Disposal Midden (East) 56488005 AB 167,913 5,277
PCA Waste Disposal Midden (West) 56488004 AB 167,913 10,192
PSPC 98 Manitoba St. 11181001 ON 149,898 0
PSPC Alaska Highway - 202 Road NWSC Maintenance Camp K-19 09401180 BC 2,194,953 387,429
PSPC Alaska Highway - Fireside Maintenance Camp 09401080 BC 966,988 170,636
PSPC Alaska Highway - Former Military Establishment (Ft Nelson Rec Centre) P-08I 09401270 BC 8,500 1,500
PSPC Alaska Highway - Fort Nelson Gravel Pit 09401030 BC 53,478 9,437
PSPC Alaska Highway - Iron Creek Maintenance Camp 09401090 YT 603,292 106,372
PSPC Alaska Highway - Liard Maintenance Camp 09401070 BC 485,008 85,590
PSPC Alaska Highway - Muncho Lake Maintenance Camp 09401060 BC 575,895 103,031
PSPC Alaska Highway - Sikanni Maintenance Camp 09401020 BC 256,521 45,268
PSPC Alaska Highway - Steamboat Maintenance Camp 09401040 BC 510,201 90,064
PSPC Alaska Highway - Toad River Maintenance Camp 09401050 BC 1,427,321 253,548
PSPC Alaska Highway - Wonowon Maintenance Camp 09401010 BC 2,727,745 481,410
PSPC Contrecoeur Landfill 23148001 QC 1,768,911 311,965
PSPC Esquimalt Graving Dock - Canadian Forces Sailing Association (CFSA) Waterlot 17410014 BC 380,563 67,040
PSPC Esquimalt Graving Dock Uplands AEC's 6,7,8,9,10,21 17410002 BC 1,499,897 0
PSPC Esquimalt Graving Dock Waterlot - AEC's 11,15 17410007 BC 1,159,774 0
PSPC Former Sambault Garbage Dump 20625001 QC 2,513,747 443,426
PSPC Former St-Germain Foundry inc. 20624001 QC 423,427 74,710
PSPC Northside Landfill B (NLFB) 55793012 NL 1,728,000 250,894
PSPC Unused Land (Prophet River) 22208001 BC 2,359,255 416,273
TC Air Terminal Building APEC 20A Parking Lot 20146001 YT 25,079 21,154
TC Airside Operations and Maintenance Centre 15473005 AB 26,547 4,685
TC Cambridge Bay Apron 00024301 NU 90,900 16,041
TC Disposal Site 2 and Fire Training Area 00339002 NL 64,084 11,309
TC Drums in Watson Lake - APEC 5 N0281007 YT 21,250 3,750
TC Esquimalt Harbour Fill Sites 00025820 BC 84,198 14,858
TC Fire Training Area N0010002 NU 60,230 10,629
TC Fire Training Area N0014002 NT 26,854 4,739
TC Former fire training area (PFAS) 00026104 QC 38,344 6,767
TC Former Remote Radar Site 00967016 NL 22,289 3,933
TC Former Tenant Air Fuelling Facility - APEC 6 20146003 YT 132,272 23,342
TC Former USTs (Maintenance Garage and Hangar) - APEC 6 N0281008 YT 347,271 61,283
TC Historic 6 Bay Garage - APEC 11 20146012 YT 169,990 29,998
TC Historic Military Base - APEC 22 N0281012 YT 73,069 12,895
TC Historic Military Base West of Runways - APEC 20C 00024670 YT 267,128 47,140
TC Inner Harbour 22905009 ON 151,957 26,816
TC Landfill / Scrap Metal Dump N0015006 NU 31,205 5,507
TC London Airport - Former Firefighting Training Areas 10855002 ON 89,613 15,814
TC Lot 2A: Middle Harbour Fill Site; Harbour Floor 17348003 BC 10,706,925 0
TC Lot 6A: Barclay Point; Rock Bay East Fill; Rock Bay North Fill; Bay Street East Fill; J-15 Bay Street Centre Fill; J-16 Bay Street 17348008 BC 198,958 0
TC Lot 17: Victoria Harbour Floor; Point Ellice (Bay Street); Johnson Street; Point Ellice (Bay Street); East Selkirk; Macaulay 17348020 BC 2,018,397 0
TC Marine Fire Training Area 00339015 NL 8,500 1,500
TC Mont Louis - material in wharf and sediments 30458001 QC 4,156,399 733,482
TC Nitchequon N0285001 QC 83,366 14,712
TC Old Landfill / Main Drum Cache N0017003 NU 4,276,920 80,608
TC Otter Creek Former Landfill / Asphalt Plant 01831001 NL 397,988 70,233
TC Parcels in the village of Kuujjuaq 08389003 QC 161,628 28,523
TC Port Stanley - Land Lots 10611002 ON 99,387 17,539
TC Reay Creek and Reay Creek Pond 00026091 BC 844,894 149,099
TC Regional Fire Depot - APEC 8 20146004 YT 371,543 65,566
TC Sediments - Gaspé wharf 72064003 QC 80,993 93,265
TC Thunder Bay International Airport - Former Firefighting Training Area 11943001 ON 398,233 70,276
TC Williams Lake Airport Former Fire Training Areas N0033001 BC 33,665 5,941

Appendix C – Environmental liability for Federal Contaminated Sites

Environmental liabilities are the estimated costs related to the remediation or risk management of contaminated sites for which the Government of Canada is obligated, or will likely be obligated, to incur costs. FCSAP is aimed to address specifically remediation liability. A contingent liability is disclosed when the Government’s obligation to a contaminated site is unknown and where future events are expected to resolve the uncertainty. Recording environmental liability is a requirement of the Treasury Board Directive on Accounting Standards; liabilities are reported annually in the Public Accounts of Canada.Footnote 2

According to Treasury Board of Canada Secretariat guidance, an environmental liability for the remediation of contaminated sites is recognized when all of the following criteria are satisfied:

The Government has identified 6,860 sites where contamination may exist and where assessment, remediation and monitoring may be required. Of these, the Government has identified 2,444 sites where action is required and for which a gross liability of $7.117 billion has been recorded. This liability estimate was based on site assessments performed by environmental experts. Moreover, to estimate the liability for a group of unassessed sites, the Government uses a statistical model based on a projection of the number of sites that will proceed to remediation and on current and historical costs. This group includes 3,562 unassessed sites, of which 1,464 sites are projected to proceed to remediation and for which an estimated liability of $258 million has been recorded. These two estimates, based on information available on March 31, 2020, total $7.375 billion, the Government’s best estimate of the costs required to remediate sites to the current minimum environmental standard.

For the remaining 854 sites, the Government has recognized no liability for remediation. Some of these sites are at various stages of testing and evaluation; if remediation is required, liabilities will be reported as soon as a reasonable estimate can be determined. For other sites, the Government does not expect to give up any future economic benefits, as there is likely no significant environmental impact or human-health threats. These sites will be re-examined and a liability for remediation will be recognized if future economic benefits will be given up.

Table C.1: Changes in total liability for remediation of contaminated sites (2019–2020)
- March 31, 2019 ($) March 31, 2020 ($) Difference
($)
Opening balance 5,710,488,358 6,478,074,737 767,586,379
Less: expenditures reducing opening liabilities 583,549,885 585,673,239 2,123,354
Add: changes in estimated remediation costs 1,127,718,946 1,428,328,494 300,609,548
Add: new liability for sites not previously recorded 223,417,318 54,418,978 -168,998,340
Closing balance (gross) 6,478,074,737 7,375,148,970 897,074,233
Less: Expected recoveriesa 23,161,964 25,655,597 2,493,633
Closing balance (net) 6,454,912,773 7,349,493,373 894,580,600

a An expected recovery is reported when it is likely that a recovery will be received by the Crown and a reasonable estimate of the amount of the recovery can be made.

Table C.2: Estimated remediation liability for federal contaminated sites that may be eligible for FCSAP (2019–2020)
- March 31, 2019 ($) March 31, 2020 ($) Difference
($)
Total liability for remediation of contaminated sitesa 6,478,074,737 7,375,148,970 897,074,233
Lessb: Atomic Energy of Canada Limited 1,054,978,000 877,196,000 -177,782,000
Lessb: Canada Border Services Agency 1,317,794 1,770,812 453,018
Lessb: Canadian Broadcasting Corporation 352,000 273,000 -79,000
Lessb: Global Affairs Canada 15,934 16,253 319
Lessb: Royal Canadian Mounted Police 11,088,614 11,260,019 171,405
Lessb: Windsor-Detroit Bridge Authority 19,523,000 9,088,000 -10,435,000
Lessb: Expected recoveries 23,161,964 25,655,597 2,493,633
Estimated remediation liability for federal contaminated sites that may be eligible for FCSAP 5,367,637,431 6,449,889,289 1,082,251,858

a Total liability for remediation of contaminated sites, as reported in the Public Accounts of Canada, 2020.

b Some organizations are not part of FCSAP, as they have their own funding sources or their sites do not meet the eligibility requirements of FCSAP.

Table C.3: Estimated remediation liability for federal contaminated sites that may be eligible for FCSAP, by participating custodian (2019–2020)
Custodian March 31, 2019 ($) March 31, 2020 ($) Difference
($)
Agriculture and Agri-Food Canada 5,978,858 9,284,096 3,305,238
Correctional Service of Canada 3,211,004 2,649,382 -561,622
Crown-Indigenous Relations and Northern Affairs Canada 3,772,146,710 4,361,394,318 589,247,608
Environment and Climate Change Canada 213,611,159 206,021,558 -7,589,601
Fisheries and Oceans Canada 226,345,681 268,022,078 41,676,397
Indigenous Services Canada 38,534 379,387,007 379,348,473
Jacques Cartier and Champlain Bridges Incorporated 26,592,000 34,396,000 7,804,000
National Capital Commission 65,354,000 63,901,000 -1,453,000
National Defence 526,425,304 541,307,536 14,882,232
National Research Council of Canada 3,458,402 2,358,615 -1,099,787
Natural Resources Canada 1,800,845 1,866,717 65,872
Parks Canada Agency 76,892,665 96,177,742 19,285,077
Public Services and Procurement Canada 239,334,375 253,480,574 14,146,199
Transport Canada 228,297,858 250,208,263 21,910,405
VIA Rail Canada Inc. 1,312,000 5,090,000 3,778,000
Less: Expected recoveries 23,161,964 25,655,597 2,493,633
Estimated remediation liability for federal contaminated sites that may be eligible for FCSAP 5,367,637,431 6,449,889,289 1,082,251,858

Source: Public Accounts of Canada, 2020

Page details

Date modified: