Backgrounder: Canada and British Columbia reach agreement to fund $450 million in water and wastewater upgrades

Backgrounder

Initial 35 projects approved for funding

The Government of Canada is providing $225,067,721 for projects under the new Clean Water and Wastewater Fund to rehabilitate and improve community water and wastewater systems across the Province of British Columbia. Combined with provincial, municipal and other contributions, $450,135,442 will provide B.C. families with clean and reliable water and wastewater services. The federal government is providing up to 50% of this funding.

As part of the bilateral agreement with British Columbia, an initial list of 35 projects has been approved to date for funding amounting to over $36.1 million in federal funding and over $23.8 million in provincial funding. Additional projects will be identified following an intake process that will open on September 30, 2016. The intake will close on Wednesday, November 23, 2016.

Location Project Name Federal Funding Provincial Funding Municipal
Funding
Anticipated Start Date

Burns Lake

5th Avenue Water Tower Replacement

$1,261,741

$832,749

$428,993

December 15, 2016

Central Kootenay RD

Arrow Creek Water Main Replacement and System Improvements - Final Phase

$2,507,417

$1,654,895

$852,522

January 1, 2017

Central Saanich

Brentwood Bay Water Main- Phase 1

$425,000

$280,500

$144,500

December 15, 2016

Dawson Creek

Water Treatment Plant Upgrades

$2,249,000

$1,484,340

$764,660

December 15, 2016

Elkford

District of Elkford - Water Loss Management Implementation

$625,000

$412,500

$212,500

December 15, 2016

Fort St. James

Fort St. James Water Looping Project - Simon Fraser Ave.

$188,500

$124,410

$64,090

December 15, 2016

Fraser Valley RD

Electoral Area D - Area D Integrated Water System Upgrade

$106,250

$70,125

$36,125

June 28, 2017

Fraser Valley RD

Electoral Area E - Baker Trails Estate Wastewater Treatment System Replacement

$823,175

$543,295

$279,880

January 28, 2017

Fraser Valley RD

Electoral Area B - Dogwood Valley Water System Upgrade

$99,762

$65,843

$33,920

February 28, 2017

Fruitvale

Fruitvale Sewer Treatment Plant and  Sewer Upgrades

$932,500

$615,450

$317,050

December 15, 2016

Golden

Community Wastewater System Improvements

$375,000

$247,500

$127,500

December 15, 2016

Hope

Hope Pollution Control Center Upgrade (Sewage Treatment Plant)

$1,466,750

$968,055

$498,695

January 7, 2017

Invermere

Paddy Ryan Water Treatment Plant UV Disinfection Upgrade

$908,481

$599,597

$308,885

December 15, 2016

Kaslo

Kaslo River Intake Upgrades

$174,538

$115,195

$59,343

December 15, 2016

Kent

Agassiz Avenue Infrastructure Improvements Project

$652,500

$430,650

$221,850

December 15, 2016

Kimberley

Kimberley Drinking Water Loss Management

$500,000

$330,000

$170,000

April 17, 2017

Ladysmith

Ladysmith Drinking Water Filtration Project

$5,306,764

$3,502,464

$1,804,300

December 15, 2016

Lake Cowichan

Lake Cowichan Water Main Upgrades

$680,177

$448,916

$231,261

December 15, 2016

Langley - C

Utilities Works Project

$1,811,640

$1,195,682

$615,958

October 15, 2016

Merritt

Coldwater Avenue Infrastructure  Improvements

$1,384,517

$913,781

$470,736

October 15, 2016

Montrose

Montrose Wastewater Treatment Plant Upgrades

$395,000

$260,700

$134,300

December 15, 2016

Nanaimo RD

Greater Nanaimo Pollution Control Centre: Centrifuge and Polymer System

$654,500

$431,970

$222,530

December 15, 2016

Nanaimo RD

San Pareil Water System - Treatment Upgrades

$420,000

$277,200

$142,800

December 15, 2016

Port Alice

Port Alice Wastewater Treatment Plant Upgrade

$525,210

$346,638

$178,572

December 15, 2016

Port McNeill

Water Distribution Replacement and Upgrade

$965,000

$636,900

$328,100

December 15, 2016

Powell River - C

Haslam Water Supply Main Replacement

$2,110,000

$1,392,600

$717,400

December 15, 2016

Radium Hot Springs

Water Reservoir Replacement Project

$600,000

$396,000

$204,000

October 15, 2016

Salmon Arm

Foreshore Sanitary Sewer Main Rehabilitation

$858,000

$566,280

$291,720

December 15, 2016

Squamish

Water Metering & Water Distribution System Improvements

$970,090

$640,259

$329,831

May 1, 2017

Strathcona RD

Quathiaski Cove Sewage Extension Project

$684,425

$451,720

$232,705

December 15, 2016

Summerland

Waste Water Treatment Plant Grit Removal and Effluent Filter Upgrades

$1,583,340

$1,045,004

$538,336

January 1, 2017

Sunshine Coast RD

Square Bay Wastewater Treatment Plant Upgrade

$420,062

$277,241

$142,822

January 1, 2017

Warfield

Warfield PRV Stations Rehabilitation

$111,000

$73,260

$37,740

January 1, 2017

West Kelowna

East Boundary Lift Station Upgrade

$390,625

$257,812

$132,813

December 15, 2016

West Vancouver

West Vancouver (Marine at the Beach) Lift Station Reconfiguration and Service Area Upgrades

$3,017,250

$1,991,385

$1,025,865

April 3, 2017


Search for related information by keyword

Page details

Date modified: