Backgrounder: Canada and Ontario announce funding for 312 public transit projects across Ontario
Backgrounder
A new list of transit projects has been approved under the Canada-Ontario Public Transit Infrastructure Fund (PTIF) agreement, which is designed to address key infrastructure priorities with a focus on repairing and upgrading existing facilities and assets.
The Government of Canada is providing Ontario with over $1.48 billion under PTIF, and will fund up to 50 per cent of the eligible project costs.
As part of the bilateral agreement with Ontario, the following projects in 28 municipalities have now been approved for federal funding amounting to more than $202 million.
Location |
Project Name |
Federal Funding |
Anticipated Start Date |
Burlington |
New two way radio command console |
$57,500 |
March 1, 2017 |
Burlington |
Purchase Handivan expansion fleet (2 new buses) |
$200,700 |
January 1, 2017 |
Burlington |
Purchase conventional expansion fleet (3 new buses) |
$769,800 |
January 1, 2017 |
Burlington |
New Transit Workforce Management System Module |
$112,500 |
February 1, 2017 |
Burlington |
Consulting for Transit Master Plan / Mobility Plan / Cycling Plan |
$175,000 |
January 2, 2017 |
Burlington |
Building automation system upgrade |
$35,000 |
January 2, 2017 |
Burlington |
Conversion of bus bay lighting to light-emitting diode (LED) |
$62,500 |
January 2, 2017 |
Burlington |
Project to remove asbestos insulation at Transit Headquarters |
$167,500 |
January 2, 2017 |
Burlington |
Elgin Promenade - multi use pathway - Phase 2 (Elizabeth St. to John St) |
$225,000 |
May 1, 2017 |
Burlington |
Construction of a concrete sidewalk on John Lucas Drive |
$240,000 |
May 1, 2017 |
Burlington |
Construction of a concrete sidewalk on the South Service Road |
$425,000 |
May 1, 2017 |
Burlington |
Integrated bus arrival display signs at Aldershot, Burlington and Appleby GO stations |
$50,000 |
February 1, 2017 |
Burlington |
Downtown terminal shelter upgrade |
$112,500 |
May 1, 2017 |
Burlington |
Bus Rapid Transit (BRT) Study - Plains / Fairview Corridor |
$75,000 |
January 2, 2017 |
Burlington |
Construction of multi-use paths - Hydro Corridor |
$267,500 |
November 15, 2016 |
Burlington |
Elgin Promenade multi use pathway - Phase 3 (John St. to Brant St.) |
$438,460 |
May 1, 2017 |
Chatham-Kent |
Opticom Emergency Response installation at eight locations for public transit pre-emption |
$72,650 |
June 2, 2017 |
Chatham-Kent |
Installation of required concrete works at five transit shelter locations to address accessibility constraints |
$70,000 |
May 5, 2017 |
Chatham-Kent |
Smart-Card implementation, by Transitfare & Systems, for accessible transit services to provide improved service reliability |
$18,000 |
July 7, 2017 |
Chatham-Kent |
NextBus integration, by NextBus, for inter-urban transit service lines to provide real-time transit information and improved service reliability |
$50,000 |
July 7, 2017 |
Chatham-Kent |
Installation of new concrete sidewalk to provide access and customer safety/security to multiple transit stop locations |
$90,000 |
May 5, 2017 |
Chatham-Kent |
Installation of new concrete sidewalk to provide access to new transit shelter location and address accessibility constraints |
$3,000 |
May 5, 2017 |
Chatham-Kent |
Installation of transit shelter trash receptacles at twenty locations to provide enhanced customer service, health and safety |
$10,000 |
May 5, 2017 |
Chatham-Kent |
Smart-Card web service implementation, by Transitfare & Systems, for Chatham-Kent Conventional Transit Services to introduce new technologies and enhance customer service |
$10,000 |
July 7, 2017 |
Chatham-Kent |
Installation of required concrete works at fifty transit stop locations to improve customer service and security |
$50,000 |
May 5, 2017 |
Chatham-Kent |
McFarlane Ave. and St. Clair Street installation of a designated right turn lane along transit route to improve schedule adherence |
$44,000 |
April 7, 2017 |
Chatham-Kent |
Heritage Drive and Keil Drive installation of a designated right turn lane along transit route to improve schedule adherence |
$2,500 |
April 7, 2017 |
Chatham-Kent |
Transit service/route extensions including 46 stop removals and various new stop installations to address ridership demands and route schedule adherence |
$5,200 |
September 1, 2016 |
Chatham-Kent |
Installation of three new dome-style transit pedestrian shelters, by Mountain Shelter Solutions |
$27,000 |
September 1, 2016 |
Chatham-Kent |
Installation of 27 new Solar Packages, by Mountain Shelter Solutions at existing transit passenger shelter locations |
$80,000 |
May 5, 2017 |
Chatham-Kent |
Restoration, rehabilitation and upgrades to 12 existing transit passenger shelters, by Mountain Shelter Solutions |
$70,000 |
May 5, 2017 |
Cornwall |
Replace Three Conventional Buses |
$771,000 |
January 1, 2017 |
Cornwall |
Replace Four Specialized Buses |
$240,000 |
October 31, 2016 |
Cornwall |
Replace One Diesel Fuel Tank and One Waste Oil Tank |
$228,000 |
April 31, 2017 |
Cornwall |
Install surveillance cameras on 25 buses for the safety of operators and passengers |
$88,000 |
October 31, 2016 |
Cornwall |
Implementation of Specialized Transit Scheduling Software |
$38,000 |
October 31, 2016 |
Cramahe |
Replacement of 1 Specialized Transit Vehicle |
$32,500 |
April 1, 2017 |
Cramahe |
Implement New Scheduling Software/Hardware |
$6,250 |
January 1, 2017 |
Durham Region |
Construction of PULSE Curbside Bus-Only Lanes on Highway 2 between Westney Road and Harwood Avenue |
$4,475,000 |
January 1, 2017 |
Durham Region |
Detail Design and Critical Utility Relocations for Highway 2 PULSE (Route 900) Curbside BRT Expansion between Glenanna Road and Brock Road in the City of Pickering |
$500,000 |
January 1, 2017 |
Durham Region |
Construction of a cycling lane to support Highway 2 PULSE (Route 900) Bus Rapid Transit (BRT) Expansion between Galea Drive and Lake Ridge Road in Ajax |
$165,000 |
January 1, 2017 |
Durham Region |
On Board Bus Security Cameras |
$1,000,000 |
January 1, 2017 |
Durham Region |
Improvements to the North Simcoe Commuter Lot through the installation of a paved surface and lighting |
$55,000 |
January 1, 2017 |
Durham Region |
Preparation for Raleigh Garage Facility Expansion |
$3,725,000 |
January 1, 2017 |
Durham Region |
Durham Region Transit Fleet Refurbishment - 5 conventional buses |
$505,114 |
January 1, 2017 |
Durham Region |
Durham Region Transit Mini- Bus Fleet Expansion - 2 mini-buses |
$200,000 |
January 1, 2017 |
Durham Region |
Durham Region Transit Fleet Replacements - 24 conventional buses |
$6,105,000 |
January 1, 2017 |
Durham Region |
Durham Region Transit Specialized Services Fleet Replacements - 8 specialized buses |
$800,000 |
January 1, 2017 |
Fort Erie |
Install on-board fare collection and audiovisual stop announcement and display technologies on fleet |
$20,000 |
January 1, 2017 |
Fort Erie |
Install a new bus stop network |
$129,056 |
March 1, 2017 |
Guelph |
Replacement of 100 transit fare boxes |
$1,300,000 |
November 1, 2016 |
Guelph |
Transit Master Plan design |
$147,500 |
February 1, 2017 |
Guelph |
Transit bus stop upgrades for 132 stops |
$363,221 |
April 1, 2017 |
Guelph |
Transit/ traffic signal system upgrade |
$500,000 |
October 1, 2016 |
Guelph |
Transit Bus Replacement: 24 conventional buses, 9 specialized vehicles |
$7,370,770 |
April 1, 2016 |
Hamilton |
Design and planning of New Maintenance & Storage Facility in lower Hamilton |
$14,325,000 |
January 1, 2017 |
Hamilton |
Fleet expansion as per Ten Year Local Transit Strategy |
$5,190,000 |
January 1, 2017 |
Hamilton |
Transit shelter and bus stop rehabilitation including shelter refurbishment, replacement and bus stop pylon upgrades |
$3,521,704 |
January 1, 2017 |
Hamilton |
226 Automated passenger counters |
$2,150,000 |
January 1, 2017 |
Hamilton |
Transit priority measures on A-Line and/or T-Line express routes including queue jump lanes and transit signal priority |
$1,925,000 |
January 1, 2017 |
Hamilton |
End of line/hard surface on-street infrastructure |
$1,650,000 |
January 1, 2017 |
Hamilton |
Vehicle hoist replacements at Mountain Transit Centre |
$1,512,500 |
January 1, 2017 |
Hamilton |
Sustainable transportation/transit connections - sidewalks |
$1,512,500 |
January 1, 2017 |
Hamilton |
Radio system replacement (switch from analog to digital) |
$1,500,000 |
January 1, 2017 |
Hamilton |
Heating, ventilation and air conditioning (HVAC) upgrades at Mountain Transit Centre |
$1,100,000 |
January 1, 2017 |
Hamilton |
Passenger information technology & software upgrades |
$802,500 |
January 1, 2017 |
Hamilton |
Garage door replacement at Mountain Transit Centre |
$660,000 |
January 1, 2017 |
Hamilton |
New transit vehicle wash racks at Mountain Transit Centre |
$440,000 |
January 1, 2017 |
Leamington |
Preparation of Master Transit Plan |
$34,014 |
March 1, 2017 |
Leamington |
Oak Street West sidewalk extension |
$65,000 |
July 1, 2017 |
London |
Shift Rapid Transit Environmental Assessment (EA) / Transit Project Assessment Process (TPAP) |
$1,500,000 |
April 1, 2016 |
London |
Shift Rapid Transit Engineering |
$5,942,909 |
April 1, 2016 |
London |
Rehabilitation of Dundas Place |
$8,000,000 |
April 1, 2016 |
London |
Dundas Place transit improvements |
$1,000,000 |
April 1, 2017 |
London |
New accessible transit pads and sidewalks |
$1,000,000 |
October 15, 2016 |
London |
Installation of 25 new pedestrian crossovers |
$345,000 |
October 15, 2016 |
London |
Kiwanis Park pathway connection |
$1,050,000 |
October 15, 2016 |
London |
Construct new downtown cycle tracks |
$1,075,000 |
May 1, 2016 |
London |
Byron Baseline and Wonderland Road sidewalk and bicycle facilities |
$875,000 |
October 1, 2016 |
London |
Separated bicycle lane renewal |
$645,000 |
October 1, 2016 |
London |
Construct Bradley Avenue extension transit and active transportation features |
$250,000 |
May 1, 2016 |
London |
Sidewalk and bicycle lane improvements on the Field Marshall Wolseley Bridge |
$95,000 |
May 1, 2016 |
London |
Rehabilitate and upgrade Blackfriars Bridge active transportation components |
$750,000 |
May 1, 2016 |
London |
Old East Village Shift Rapid Transit route parking lot improvements |
$650,000 |
May 1, 2016 |
London |
Feasibility Study for a Downtown Transportation Alliance |
$75,000 |
January 14, 2017 |
London |
Neighbourhood bike parking infrastructure preliminary concepts study |
$25,000 |
March 28, 2017 |
London |
Install bike parking facility (near downtown Bus Rapid Transit Station) |
$60,000 |
January 14, 2017 |
London |
Upgrade Automatic Vehicle Location/Communication System utilized at London Transit |
$121,000 |
January 1, 2017 |
London |
Replacement of existing 8-line wayside transit information signs |
$195,500 |
January 1, 2017 |
London |
Upgrade of on-board bus audio/video recording system |
$175,000 |
May 1, 2017 |
London |
Replacement of current telephone system in use at London Transit |
$150,000 |
October 1, 2016 |
London |
Retrofit current bus fleet (110 buses) with perimeter seating to increase accessibility |
$562,500 |
February 1, 2017 |
London |
Asphalt repairs at both transit facilities |
$200,000 |
May 1, 2017 |
London |
Upgrade lighting to Light-emitting diodes (LED) at both transit facilities |
$162,500 |
February 1, 2017 |
London |
Replacement of 2 hoists at Highbury Transit Facility |
$200,000 |
January 1, 2017 |
London |
Upgrade of fuel cardlock system at Highbury Transit Facility |
$57,500 |
January 1, 2017 |
London |
Replacement of 10 engines in buses that have surpassed the planned six year replacement cycle |
$450,000 |
January 1, 2017 |
London |
Replacement of all 380 bus shelters currently in place in the City of London |
$1,319,500 |
October 1, 2016 |
London |
Upgrades to file server and network switching infrastructure in use at the Highbury Transit Facility |
$101,500 |
May 1, 2017 |
London |
Replacement of bus wash infrastructure at Highbury Transit Facility |
$368,000 |
May 1, 2017 |
London |
Replacement batteries for eight Hybrid buses currently in fleet |
$372,500 |
January 1, 2017 |
London |
Replacement dual power invertor modules for 8 hybrid buses |
$200,000 |
January 1, 2017 |
London |
Replacement of transmissions for eight Hybrid buses |
$414,000 |
January 1, 2017 |
London |
Replacement of the autotechnik joints for nine articulated buses in the fleet |
$276,000 |
January 1, 2017 |
London |
Replacement of the salt storage tent at Highbury Transit Facility |
$37,500 |
May 1, 2017 |
London |
Complete construction to enclose existing structure at Wonderland Transit Facility to provide for additional storage |
$30,000 |
January 1, 2017 |
London |
Replace/repair existing perimeter fencing at Highbury Transit Facility |
$40,000 |
January 1, 2017 |
London |
Replace security gate infrastructure at Highbury Transit Facility |
$75,000 |
January 1, 2017 |
London |
Replacement of all 25 man doors at Highbury Transit Facility |
$15,000 |
May 1, 2017 |
London |
Completion of concrete repair at Wonderland Transit Facility |
$75,000 |
January 1, 2017 |
London |
Replacement of sewage pump infrastructure at the Wonderland Transit Facility |
$34,500 |
January 1, 2017 |
London |
Renovation of reception area at Highbury Transit Facility to provide greater security |
$11,500 |
January 1, 2017 |
London |
Supply and installation of 35 wayside transit information signs at identified locations across the City |
$162,500 |
January 1, 2017 |
London |
Completion of a facility needs assessment and detailed plan for Highbury Transit Facility |
$150,000 |
January 1, 2017 |
London |
Purchase and installation of 72 automatic passenger counters for remainder of bus fleet |
$287,500 |
January 1, 2017 |
London |
Purchase and installation of closed-circuit monitors for all 213 buses |
$1,992,500 |
January 1, 2017 |
London |
Increased bus replacement program in 2017 to include seven buses planned for 2018 replacement |
$2,000,000 |
January 1, 2017 |
London |
Increased bus replacement program in 2018 to include seven buses planned for 2019 replacement |
$2,000,000 |
January 1, 2018 |
London |
Rehabilitation of Thames Valley Parkway (TVP), South Branch |
$500,000 |
November 1, 2016 |
London |
Rehabilitation of Thames Valley Parkway (TVP), Main Branch |
$375,000 |
November 1, 2016 |
London |
Rehabilitation of three pedestrian bridges |
$300,000 |
November 1, 2016 |
London |
12 audible pedestrian signal upgrades |
$195,000 |
January 1, 2017 |
London |
Installation of 60 pedestrian countdown signal heads |
$155,000 |
January 1, 2017 |
London |
Bicycle detection improvements at four intersections |
$50,000 |
January 1, 2017 |
Mississauga |
Building expansion to accommodate future growth and life cycle renewal (Malton Satellite Terminal) |
$419,854 |
January 1, 2017 |
Mississauga |
Lifecycle renewal/replacement of building systems to improve efficiency and to extend system useful life (City Centre Transit Terminal). |
$88,892 |
January 1, 2017 |
Mississauga |
Lifecycle renewal/replacement of building systems to improve efficiency and to extend system useful life (Edward J. Dowling Transit Facility) |
$1,686,197 |
January 1, 2017 |
Mississauga |
Lifecycle renewal/replacement of exterior door to extend the useful life (Edward J. Dowling Transit Facility) |
$19,084 |
January 1, 2017 |
Mississauga |
Lifecycle renewal/replacement of mechanical and electrical upgrades to improve efficiency and to extend system useful life (City Centre Transit Terminal) |
$1,245,752 |
January 1, 2017 |
Mississauga |
Information Technology Project for Network Fiber Design and Construction for Transit and Traffic Site Connectivity to Build 100 New Nodes in Support of Advanced Transportation Management System (ATMS), Includes Replacement of any Degraded Fiber Infrastructure |
$571,524 |
May 4, 2017 |
Mississauga |
Information Technology Project for Switches and Routers for Transit and Traffic Voice and Data Communications to Support the New Network Fiber Design Required for the Advanced Transportation Management System (ATMS) |
$225,998 |
May 4, 2017 |
Mississauga |
Information Technology Project for The Vehicle Communication (VCOM) Radio Infrastructure for Transit iBus Communications |
$581,568 |
May 4, 2017 |
Mississauga |
Information Technology Project for Wireless Infrastructure for Transit and Transit Rider Broadband Connectivity |
$150,665 |
May 4, 2017 |
Mississauga |
Bus Communication Gateway Replacement on all MiWay Fleet |
$1,506,654 |
April 1, 2017 |
Mississauga |
Construction of New Transit Operator Facility (Mount Charles Park) |
$502,218 |
January 1, 2017 |
Mississauga |
Enhancement of Pavement Entranceways and Exterior bays at 9 Terminals |
$100,443 |
March 1, 2017 |
Mississauga |
Purchase of Transit Performance Metrics Module (HASTUS Analytics)-Runtimes, Ridership and Data Warehouse |
$200,887 |
January 1, 2017 |
Mississauga |
Installation of additional 250 Accessible MiWay Bus Pads |
$136,603 |
March 1, 2017 |
Mississauga |
Installation of 100 additional MiWay Transit Shelters |
$1,255,545 |
March 1, 2017 |
Mississauga |
Refurbishment of 250 existing bus stops pads to increase accessibility |
$140,621 |
March 1, 2017 |
Mississauga |
Refurbishment of 2 existing Transit Mini Terminals for optimization of Transit Infrastructure |
$100,443 |
January 1, 2017 |
Mississauga |
Replacement of Asphalt with concrete Transit Bus Landing Pads at 75 high traffic bus stops |
$502,218 |
March 1, 2017 |
Mississauga |
Replacement of 500 existing Transit MiWay Stop Signs |
$50,221 |
January 1, 2017 |
Mississauga |
Study for Anchor Terminals at Strategic locations across the City |
$251,109 |
January 10, 2017 |
Mississauga |
Transit Bus Seat Modification on 84 buses |
$753,327 |
April 15, 2017 |
Mississauga |
Transit Capital Bus Engine Maintenance on up to 280 buses |
$1,888,008 |
April 1, 2016 |
Mississauga |
Transit Capital Bus Maintenance - Major Component Rehabilitation/Replacement on up to 280 buses |
$3,610,948 |
January 1, 2017 |
Mississauga |
Transit Facility Repairs (Minor) |
$70,310 |
May 1, 2017 |
Mississauga |
Purchase of additional Transit Operations Modules - Garage Management & Bus Allocation |
$286,264 |
January 1, 2017 |
Mississauga |
Transit Maintenance Management System Replacement |
$753,327 |
March 1, 2017 |
Mississauga |
Etobicoke Creek Trail reconstruction - trail resurfacing, signage, trail markers and trail user-count technology |
$1,135,013 |
January 1, 2017 |
Mississauga |
Trail Reconstruction - Garnetwood Park |
$152,473 |
January 1, 2017 |
Mississauga |
Trail Reconstruction - Huron Heights |
$116,564 |
January 1, 2017 |
Mississauga |
Trail Reconstruction - Pheasant Run Park |
$96,677 |
January 1, 2017 |
Mississauga |
Trail Reconstruction - Quenippenon Meadows Park |
$62,425 |
January 1, 2017 |
Mississauga |
Trail Reconstruction - Stonewood Park |
$55,796 |
January 1, 2017 |
Mississauga |
Trail Reconstruction - Max Ward Park |
$95,572 |
January 1, 2017 |
Mississauga |
Trail Reconstruction - South Common Park |
$128,501 |
January 1, 2017 |
Mississauga |
Trail Reconstruction -Crawford Green Park |
$41,985 |
January 1, 2017 |
Mississauga |
Waterfront Trail Improvements and trail reconstruction - Signage, trail markers, trail user-count technology and minor trail reconstructions |
$246,415 |
January 1, 2017 |
Mississauga |
Acquisition of new Intelligent Transportation System (ITS) equipment (i.e. Closed-Circuit Television, detection devices) |
$39,823 |
April 1, 2017 |
Mississauga |
Acquisition of new traffic signal equipment enhancements (i.e. Accessible Pedestrian Signals and Pedestrian Countdown Signals) |
$79,652 |
April 1, 2017 |
Mississauga |
Installation of tactile plates at pedestrian crossings to meet Accessibility for Ontarians with Disabilities Act requirements. |
$2,124,128 |
April 1, 2017 |
Mississauga |
Conduct Detailed Safety Assessments for all at-grade railway crossings |
$53,103 |
April 1, 2017 |
Mississauga |
Construction of Multi-Use Trails along the Hanlan Water Project |
$329,239 |
April 1, 2017 |
Mississauga |
Lakeshore Road Transportation Master Plan |
$132,755 |
April 1, 2017 |
Mississauga |
Replacement of traffic controllers/cabinets |
$100,893 |
April 1, 2017 |
Mississauga |
Mississauga Cycling Master Plan Update |
$53,103 |
January 1, 2017 |
Mississauga |
New sidewalks to transit stations |
$318,619 |
April 1, 2017 |
Mississauga |
Pedestrian & Cyclist Access to Mississauga's Transitway & GO Transit Stations |
$3,757,047 |
May 1, 2017 |
Mississauga |
Transportation Master Plan Study |
$132,755 |
March 1, 2017 |
Mississauga |
Acquisition of up to 3 new transit buses to increase service and ridership |
$131,144 |
October 1, 2017 |
Mississauga |
Acquisition of up to 10 new transit buses to increase Service Hours |
$2,923,222 |
October 1, 2017 |
Mississauga |
Acquisition of up to 51 - 40 foot buses to replace aging buses |
$14,776,036 |
October 1, 2017 |
Mississauga |
Acquisition of up to 29 - 60 foot buses to replace aging buses |
$13,855,135 |
October 1, 2017 |
Niagara Falls |
Addition of 6 new growth vehicles to meet ridership demand |
$2,035,200 |
January 16, 2017 |
Niagara Falls |
Addition of 2 replacement vehicles to replace older assets |
$122,112 |
January 17, 2016 |
Niagara Falls |
Purchase of new software and hardware to better manage daily bus schedules and payroll |
$35,616 |
January 16, 2017 |
Niagara Falls |
Purchase of new scheduling software for Para-Transit service |
$27,984 |
May 13, 2017 |
Niagara Falls |
Installation of Intelligent Transportation Management Systems to enhance tracking and customer service interface and communications to passengers for the Niagara Falls Transit Fleet |
$382,617 |
January 16, 2017 |
Niagara Falls |
Electronic Farebox Upgrade for seven Chair-A-Van to meet Accessibility for Ontarians with Disabilities Act (AODA) requirements |
$71,232 |
February 20, 2017 |
Niagara Falls |
Radio Upgrade and Replacement for seven vans for Chair-A-Van |
$6,868 |
January 16, 2017 |
Niagara Falls |
Farebox Replacement for Niagara Falls Transit (Conventional Fleet) for five vans. |
$50,880 |
February 20, 2017 |
Niagara Falls |
Upgrade Radio System and Control Station Requirements at WEGO building |
$6,614 |
January 16, 2017 |
Niagara Falls |
Bus Way & Shelter Rehabilitation and Platform upgrades at Lundy's Lane and Morrison/Dorchester Transit Hubs |
$228,960 |
January 11, 2017 |
Niagara Falls |
Replacement of 6 Cummins ISL diesel engines that have surpassed life expectancy (500,000 km) |
$122,112 |
January 23, 2017 |
Niagara Falls |
Installation of Emco-Wheaton posi-lock fuelling system on 46 (forty-six) buses. |
$14,246 |
February 20, 2017 |
Niagara Falls |
Purchase of Fleet Management Software to support the asset management capacity of the Niagara Falls Transit system. |
$30,528 |
January 3, 2017 |
Niagara Falls |
Replace refrigerant recover, recycle and recharge machine in maintenance facility |
$3,561 |
January 9, 2017 |
Niagara Falls |
Purchase of ZF Transmission Diagnostic Software for buses |
$3,052 |
January 9, 2017 |
Niagara Falls |
Upgrade of fluid tracking system for all Niagara Falls Transit buses |
$14,246 |
February 22, 2017 |
Niagara Falls |
Vinyl decal replacement for 6 Orion VII buses |
$18,316 |
January 9, 2017 |
Niagara Falls |
Orion VII Powertrain and body refurbishments to extend life expectancy of two buses |
$228,960 |
February 13, 2017 |
Niagara Region |
Purchase of one new 40' bus to be utilized by Welland Transit to deliver Niagara Region's inter-municipal transit service. |
$254,171 |
January 30, 2017 |
Niagara Region |
The purchase of computer aided dispatch / automated vehicle location equipment for the 3 existing inter-municipal transit buses operated by the City of Niagara Falls on behalf of Niagara Region. |
$53,983 |
January 30, 2017 |
Niagara Region |
The purchase of computer aided dispatch / automated vehicle location equipment for the 2 existing inter-municipal transit buses operated by the City of Welland on behalf of Niagara Region. |
$35,989 |
January 30, 2017 |
Niagara-on-the-Lake |
Install Integrated On-Board Annunciator, GPS, and Electronic Fare Card System to increase efficiency and meet accessibility requirements |
$25,000 |
January 1, 2017 |
Niagara-on-the-Lake |
Improvements to 26 bus stops and installation of up to 8 new stops on expanded transit route to meet accessibility requirements |
$47,610 |
January 1, 2017 |
Norfolk County |
Improvements to approximately 26 bus stops |
$58,000 |
April 1, 2017 |
Oakville |
Addition of two accessible growth vehicles to meet specialized transit ridership demand |
$260,000 |
January 1, 2017 |
Oakville |
Addition of 8 new 30 foot growth buses to meet conventional ridership demand |
$2,126,431 |
January 1, 2017 |
Oakville |
Installation of 25 new transit pedestrian shelters to support Transit service |
$75,000 |
April 1, 2017 |
Oakville |
Replacement of 17 transit pedestrian shelters at end of useful life |
$96,000 |
April 1, 2017 |
Oakville |
Refurbishment of 15 2009 buses to achieve optimal life expectancy |
$1,200,000 |
January 1, 2017 |
Oakville |
Addition of 5 security cameras at high traffic or vulnerable locations |
$12,500 |
January 1, 2017 |
Oakville |
Installation of 80 new garbage receptacles at transit pedestrian shelters to meet needs of customers |
$40,000 |
January 1, 2017 |
Oakville |
Installation of digital signage at bus shelters at the hospital |
$45,000 |
January 1, 2017 |
Oakville |
Installation of accessibility improvements at bus service stops |
$100,000 |
January 1, 2017 |
Oakville |
Purchase and installation of a new specialized transit scheduling software |
$170,000 |
January 1, 2017 |
Oakville |
Strategic Review of specialized transit service to meet accessibility needs |
$75,000 |
January 1, 2017 |
Oakville |
Completing the installation of the new Transit Information and Communication System |
$140,000 |
January 1, 2017 |
Oakville |
Purchase and installation of a an automatic vehicle monitoring system |
$225,000 |
January 1, 2017 |
Oakville |
Construction of a multi-use trail on North Service Road |
$400,000 |
January 1, 2017 |
Oakville |
Installation of bike lockers and bike racks at the Uptown Core terminal and bus shelters |
$17,500 |
January 1, 2017 |
Peterborough |
Transit Intelligent Transportation System Enhancements to provide real time passenger information |
$100,000 |
January 31, 2017 |
Peterborough |
Transit Storage Garage Replacement Study |
$450,000 |
January 15, 2017 |
Peterborough |
Construction of a new Transit Maintenance Garage & Public Works Yard |
$1,000,000 |
January 15, 2017 |
Peterborough |
Transit Stop Shelter Upgrades of up to 110-120 new accessible transit stops and amenities |
$813,893 |
January 31, 2017 |
Peterborough |
Accessible Transit Stop Upgrades of up to 10-12 new accessible transit stops |
$50,000 |
January 31, 2017 |
Peterborough |
Replace 9 conventional transit buses with new accessible and efficient buses, as part of the Transit Bus Replacement Program |
$2,650,000 |
January 31, 2017 |
Peterborough |
Replace 5 and purchase 1 new accessible specialized transit buses, as part of the Specialized Transit Bus Replacement Program |
$337,500 |
January 31, 2017 |
Peterborough |
Replace one accessible Caremobile Van |
$50,398 |
November 1, 2016 |
Port Colborne |
Restoration of sidewalk to bus stop at Vale Centre |
$10,000 |
March 1, 2017 |
Port Colborne |
Restoration of the internal trail system at Thomas A. Lanna Sports Complex (Vale Centre) |
$15,000 |
March 1, 2017 |
Port Colborne |
Restoration of trail from Omer Ave to Weir Road |
$7,500 |
March 1, 2017 |
Port Colborne |
Restoration of trail from Robin Hood Mill north to Dain City |
$10,000 |
March 1, 2017 |
Port Colborne |
Promenade improvements on West St south of Clarence St |
$24,000 |
March 1, 2017 |
Port Colborne |
Trail entrance point improvements at various locations |
$15,000 |
March 1, 2017 |
Port Colborne |
Trail signage replacements/improvements/new signage at various locations |
$15,000 |
March 1, 2017 |
Quinte West |
Design and Planning of a new office and vehicle storage space for Quinte Access Transportation |
$56,166 |
January 1, 2017 |
Quinte West |
Purchase of 2 new specialized buses to improve service reliability and accessibility needs, and meet ridership demand |
$113,775 |
January 1, 2017 |
Sarnia |
Purchase of two low floor Nova Buses |
$498,000 |
January 31, 2017 |
Sarnia |
Purchase of two accessible buses (Care A Vans) |
$115,000 |
January 1, 2017 |
Sarnia |
Purchase of eight low floor ARBOC specialty cutaway buses |
$666,000 |
January 1, 2017 |
Sarnia |
Installation of 240 concrete pads for accessible transit stops |
$200,000 |
May 1, 2017 |
Sarnia |
Installation of a new fuel storage tank to refuel buses |
$50,000 |
May 1, 2017 |
Sarnia |
Bus facility upgrades |
$67,160 |
May 1, 2017 |
Sarnia |
Installation of cameras in all buses, 6 cameras per bus to be installed in 29 buses for a total of 174 cameras. |
$88,500 |
January 31, 2017 |
Sarnia |
Installation of an accessible transit scheduling software |
$51,948 |
January 31, 2017 |
St. Catharines |
Replacement of automatic gates at maintenance facility |
$50,000 |
May 1, 2017 |
St. Catharines |
Conventional service fleet expansion (4 new forty foot buses) to accommodate future growth and improve spare ratio of fleet |
$1,240,000 |
April 1, 2017 |
St. Catharines |
Purchase one Paratransit bus to accommodate increased demand |
$120,000 |
January 1, 2017 |
St. Catharines |
Purchase three Paratransit buses to replace existing vehicles for Paratransit service |
$270,000 |
January 1, 2017 |
St. Catharines |
Purchase three 60' buses and nine 40' buses to replace existing vehicles for conventional service |
$3,850,000 |
April 1, 2017 |
St. Catharines |
Purchase a service truck to replace maintenance service truck |
$90,000 |
April 1, 2017 |
St. Catharines |
Retrofit four buses to address wheelchair restraints on conventional buses |
$42,500 |
January 1, 2017 |
St. Catharines |
Purchase one Paravan to replace existing Paravan vehicle |
$50,000 |
January 1, 2017 |
St. Catharines |
Install computer aided dispatch (CAD) modems on all existing Paratransit vehicles |
$31,000 |
January 1, 2017 |
St. Catharines |
Expand maintenance facility to install an additional hoist to do bus maintenance work |
$1,300,000 |
January 1, 2017 |
St. Catharines |
Install automatic vehicle monitoring on all conventional vehicles |
$200,000 |
January 1, 2017 |
St. Catharines |
Install automatic passenger counting on all 70 of our conventional vehicles |
$360,000 |
January 1, 2017 |
St. Catharines |
Purchase automated driver management and timekeeping system |
$125,000 |
July 1, 2017 |
St. Catharines |
Remove four underground tanks for transmission fluid, waste oil, paint and engine oil, and replace with three aboveground tanks |
$75,000 |
January 1, 2017 |
St. Catharines |
Upgrade video camera system at maintenance facility and downtown terminal for buses |
$50,000 |
January 1, 2017 |
St. Catharines |
Restoration of multiple bus shelters |
$300,000 |
January 1, 2017 |
St. Catharines |
Replace a bus wash system with a new system |
$100,000 |
January 1, 2017 |
St. Catharines |
Purchase and install CleverWorks system to enhance accuracy of real-time bus information |
$155,000 |
January 1, 2017 |
St. Catharines |
Purchase and install new emergency generator for maintenance facility and garage |
$175,000 |
January 1, 2017 |
St. Catharines |
Replace top coat of asphalt at bus terminal bay |
$35,000 |
May 1, 2017 |
St. Catharines |
Upgrade access control system for bus terminal and maintenance facility |
$110,000 |
January 1, 2017 |
St. Marys |
Accessibility improvements to sidewalks |
$67,500 |
June 1, 2017 |
St. Thomas |
Installation of transit shelters |
$50,000 |
June 1, 2017 |
St. Thomas |
Installation of safety lighting at various transit shelters |
$20,000 |
June 1, 2017 |
St. Thomas |
Improving visibility of transit signage |
$25,000 |
June 1, 2017 |
St. Thomas |
Accessible transit fleet replacement |
$300,000 |
June 1, 2017 |
Tecumseh |
Purchase a low floor accessible community transit bus to replace an existing transit bus |
$94,584 |
November 10, 2016 |
Thorold |
Repair of six existing bus/pedestrian shelters |
$28,000 |
January 1, 2017 |
Thorold |
Installation of six new bus shelters at various bus stops |
$31,401 |
January 1, 2017 |
Thorold |
Installation of new bus laybys and bus shelters at seven bus stops |
$157,500 |
July 1, 2017 |
Thorold |
Installation of a new bus layby, 2 bus shelters and new sidewalk with a stopping complex on Towpath |
$214,008 |
June 15, 2017 |
Thorold |
Installation of 10 new concrete pads with accessible markings at multiple bus locations for improved accessibility at bus stops. Includes two locations on Schmon Parkway and eight locations on St. David's Road |
$46,000 |
June 1, 2017 |
Thorold |
Sidewalk extension for transit at six locations |
$75,000 |
July 1, 2017 |
Thorold |
Remediation of transit parking lot at transit terminal to improve accessibility. |
$75,000 |
May 1, 2017 |
Welland |
Purchase two 12-metre accessible transit buses to replace existing vehicles |
$520,000 |
September 9, 2016 |
Welland |
Purchase two 9-metre accessible transit buses to replace existing vehicles |
$465,000 |
October 11, 2016 |
Welland |
Purchase two 8-metre accessible transit buses to replace existing vehicles |
$150,000 |
October 11, 2016 |
Welland |
Purchase two specialized transit buses to replace existing vehicles |
$115,000 |
October 18, 2016 |
Welland |
Purchase a new van to replace existing transit supervisor's van |
$20,000 |
October 18, 2016 |
Welland |
Install a new hoist to replace existing bus hoist |
$50,000 |
January 1, 2017 |
Welland |
Refurbish existing bus wash system |
$40,000 |
January 15, 2017 |
Welland |
Maintenance/vault office renovations |
$77,322 |
January 15, 2017 |
Welland |
Replace of manual fare boxes with electronic fare boxes on specialized transit vehicles (phase II) |
$50,000 |
January 15, 2017 |
Welland |
Purchase a tow motor to lift heavy transit-related equipment |
$7,500 |
January 15, 2017 |
Welland |
Purchase new transmission jack for buses to replace old transmission jack |
$3,750 |
January 15, 2017 |
West Perth |
Replace 1 Accessible Van |
$28,304 |
February 15, 2017 |
West Perth |
Improve Accessible Trail Approaches to the Specialized Transit Depot |
$13,799 |
April 1, 2017 |
Windsor |
Improved functionality of farebox through use of technology enhancements |
$410,672 |
February 1, 2017 |
Windsor |
Quantification of ridership through the use of automatic passenger counters |
$100,000 |
June 1, 2017 |
Windsor |
Two additional intelligent transportation system laptops for on road supervisory support vehicles |
$4,500 |
February 1, 2017 |
Windsor |
Installation of eight LED outdoor message signs at bus stops and two flat panel indoor displays |
$100,000 |
July 1, 2017 |
Windsor |
Conduct a service delivery review focusing on current and potential growth opportunities |
$275,000 |
September 1, 2017 |
Windsor |
Conduct a fare structure review focusing on current fare structures with a view to Incorporating the latest industry standards |
$195,000 |
June 1, 2017 |
Windsor |
Restoration of multiple Transit Windsor pedestrian shelters |
$500,000 |
February 1, 2017 |
Windsor |
Acquisition of twenty-four 40 foot clean diesel buses |
$6,247,392 |
January 1, 2017 |
Windsor |
Implementation of a hybrid bus refurbishing program |
$600,000 |
September 1, 2017 |
Windsor |
Implementation of a bulk fluid asset control system |
$50,000 |
January 1, 2017 |
Windsor |
Rehabilitation of concrete surfaces and drains in fuelling and cleaning area of maintenance garage |
$35,000 |
June 1, 2017 |
Windsor |
Rehabilitation of concrete surfaces throughout the maintenance garage |
$50,000 |
June 1, 2017 |
Windsor |
Replacement of three high speed doors in the maintenance garage |
$45,000 |
March 1, 2017 |
Windsor |
Expansion of customer service parking to support increased demand |
$10,000 |
March 1, 2017 |
Windsor |
Renovations and enhancements to customer service area at the main transit terminal |
$20,000 |
May 1, 2017 |
Windsor |
Installation of a makeup/exhaust unit for improved ventilation at main transit terminal |
$375,000 |
July 1, 2017 |
Windsor |
Renovations and enhancements at the West end transit terminal |
$100,000 |
March 1, 2017 |
Windsor |
Acquisition of a commercial grade floor sweeper for maintenance garage floor |
$42,500 |
February 1, 2017 |
Windsor |
Acquisition of a commercial grade parts washer for maintenance garage |
$37,500 |
February 1, 2017 |
Windsor |
Update existing safety and security features at main transit facility and Windsor International Transit Terminal |
$90,000 |
January 1, 2017 |
Windsor |
Renovations and enhancements to the Transportation Services Area, including central dispatch, at the main transit terminal |
$100,000 |
July 1, 2017 |
Windsor |
Acquisition of fleet inspection equipment to support the Bus Rehabilitation Program |
$387,500 |
January 1, 2017 |
Windsor |
Cycling-transit connection on South Cameron Blvd. - Totten to Northwood |
$167,500 |
March 1, 2017 |
Windsor |
Cycling-transit connection on Little River Blvd - Radcliffe to East City Limits |
$35,000 |
March 1, 2017 |
Windsor |
Cycling-transit connection on Malden Road - Armanda to South City Limits |
$250,000 |
March 1, 2017 |
Windsor |
Cycling-transit connection on Kamloops Street - Calderwood to the West Limit |
$34,515 |
March 1, 2017 |
Report a problem or mistake on this page