Joint funding through the Investing in Canada infrastructure program will support eight public and road infrastructure projects in Corner Brook and neighboring municipalities.
The Government of Canada is investing more than $1.2 million toward these projects through COVID-19 Resilience Infrastructure Stream and the Rural and Northern Infrastructure Stream of theInvesting in Canada Infrastructure Program. The Government of Newfoundland and Labrador is contributing $734,774 towards the projects while the municipalities are providing a total of $624,556.
Project Information:
Project Name |
Location |
Fund |
Project Details |
Federal Funding |
Provincial Funding |
Municipal Funding |
---|---|---|---|---|---|---|
Corner Brook Royal Newfoundland Constabulary Building Controls Upgrade |
Corner Brook |
CVRIS |
Upgrade building controls at the Corner Brook Royal Newfoundland Constabulary building. |
$80,000 |
$20,000 |
$0 |
College of the North Atlantic (Corner Brook Campus) Garage Door Replacement |
Corner Brook |
CVRIS |
Replace a garage door at the College of the North Atlantic's Corner Brook Campus. |
$40,000 |
$10,000 |
$0 |
Sir Richard Squires Building Elevator Modernization |
Corner Brook |
CVRIS |
Elevator modernization at the Sir Richard Squires Building. |
$400,000 |
$100,000 |
$0 |
Corner Brook Arts and Culture Center Heating and Lighting Upgrade |
Corner Brook |
CVRIS |
Upgrade heating and lighting at the Corner Brook Arts and Culture Center. |
$112,000 |
$28,000 |
$0 |
Park Drive, Retaining Wall/Culvert Replacement |
Cox's Cove |
RNIS |
Replace a timber crib retaining wall and the associated culverts and roadway along 1 kilometre of Park Drive. The project aims to upgrade and protect existing municipal infrastructure in the area of Park Drive as well as improve the road conditions. |
$110,873 |
$110,840 |
$110,840 |
Street Improvements - Hughes Brook |
Hughes Brook |
RNIS |
Reconstruct and repave Lidstone’s Road to improve driving conditions. |
$90,702 |
$90,674 |
$90,702 |
Cox Avenue Road Construction |
Channel-Port aux Basques |
RNIS |
The reconstruction of Cox Avenue from Legrow Street to Carson Crescent will include the removal and replacement of existing asphalt, curbs, gutters and sidewalks, along with rehabilitation of associated works, such as catch basins, valves and affected nearby properties. |
$220,405 |
$220,339 |
$220,339 |
Grand Bay Road Storm Sewer Installation |
Channel-Port aux Basques |
RNIS |
The replacement of the storm water collection system along Grand Bay Road, from Allen’s Road to Grandview Crescent will include installing 150 m of storm water piping, manholes, and catch basins, as well as upgrades to 270 m of Grand Bay road. |
$154,968 |
$154,921 |
$202,675 |