Backgrounder: Canada and Manitoba invest in ventilation, heating and cooling upgrades in schools and healthcare facilities across the province

Backgrounder

Backgrounder: Canada and Manitoba invest in ventilation, heating and cooling upgrades in schools and healthcare facilities across the province

The Government of Canada is investing $10,469,172 and the Government of Manitoba is investing up to $2,697,399 through the COVID-19 Resilience Stream of the Investing in Canada Infrastructure Program to support 32 ventilation projects in schools, health facilities, treatment facilities, and emergency services buildings.

Project Information:

Location

Project Name

Project Details

Federal Funding

Provincial Funding

Town of Arborg

Arborg and the District Health Centre - Heating, Ventilation and Air Conditioning (HVAC) System Upgrade

This project consists of upgrading the HVAC systems cooling capacity to provide suitable environmental conditions.

$336,000

$84,000

City of Brandon

Dinsdale Personal Care Home - HVAC Upgrade and Replace Air Handling Unit

This project consists of upgrading the HVAC system and replacing the air handling unit to improve ventilation.

$91,034

$22,758

City of Brandon

Addictions Foundation of Manitoba Brandon - Resident Suite HVAC Upgrade

This project consists of upgrading the HVAC system to increase air filtration and meet current healthcare codes.

$176,000

$44,000

Town of Churchill

Churchill Health Centre - HVAC Improvements

This project consists of upgrading the HVAC system to increase air filtration and meet current healthcare code requirements.

$262,400

$65,600

Rural Municipality of La Broquerie

Arborgate School - Boiler Replacement and Ventilation Upgrades

This project consists of a boiler replacement and the installation of a heat recovery ventilator (HRV) with the goal of increasing outdoor air intake.

$560,000

$140,000

Municipality of Louise

Thomas Greenway Middle Years School - Steam Boiler System Replacement and Ventilation System Upgrade

This project consists of replacing cabinet unit heaters, the installation of a roof top unit (RTU), the installation of an air-handling unit (AHU) and a heating system upgrade.

$343,440

$85,860

Municipality of Minitonas-Bowsman

Bowsman School - Unit Ventilator Replacement

This project includes the replacement of classroom unit ventilators and the installation of a central dual core, reversing the flow of the HRV.

$560,000

$140,000

Municipality of North Cypress-Langford

Ecole la Source - Boiler Replacement and Ventilation Upgrades

This project includes the replacement of the school boiler heating system, the main AHU and the gym AHU.

$280,000

$70,000

Municipality of Rockwood

Stonewall Collegiate - Steam Boiler System Replacement and Ventilation System Upgrades

This project consists of the replacement of fan coil units and variable air volume boxes in classrooms, the installation of a central dual core energy recovery ventilator (ERV), the installation of a make-up air unit (MUA), the installation of a roof top unit (RTU) and the corresponding upgrade of the heating system.

$695,760

$173,940

City of Selkirk

Betel Personal Care Home - Air Handling Unit Replacements

This project consists of upgrading the HVAC system to improve ventilation by increasing filtration and air changes.

$236,000

$59,000

City of Thompson

Thompson General Hospital (TGH) - OR Department Humidity Control Phase II

This project consists of an upgrade to the HVAC system to provide adequate operating room humidity control, in order to reduce downtime.

$800,000

$200,000

City of Thompson

Thompson General Hospital (TGH) - Building Management System Controls Upgrade

This project consists of the upgrade of an obsolete HVAC control system, in order to better provide optimal environmental conditions.

$88,234

$102,165

City of Winnipeg

Lions Manor Personal Care Home - Air Handling Unit Replacement #3

This project consists of upgrading the HVAC system to improve ventilation by increasing filtration and air changes.

$16,240

$4,060

City of Winnipeg

Lions Manor Personal Care Home - Air Handling Unit Replacement #4

This project consists of upgrading the HVAC system to improve ventilation by increasing filtration and air changes.

$21,200

$5,300

City of Winnipeg

Lions Manor Personal Care Home - Air Handling Unit Replacement #5

This project consists of upgrading the HVAC system to improve ventilation by increasing filtration and air changes.

$30,400

$7,600

City of Winnipeg

Golden Links Lodge Personal Care Home - Geothermal Well Upgrade

This project consists of upgrading the Geothermal Well Pump to increase the systems cooling capacity to provide suitable environmental conditions.

$48,800

$12,200

City of Winnipeg

Lions Manor Personal Care Home - Air Handling Unit Replacement #2

This project consists of upgrading the HVAC system to improve ventilation by increasing filtration and air changes.

$60,320

$15,080

City of Winnipeg

Saul & Claribel Simkin Centre - Replace Kitchen Condensing Unit

This project consists of replacing the kitchen’s Condensing Unit to increase the systems cooling capacity to provide suitable environmental conditions.

$72,000

$18,000

City of Winnipeg

Lions Manor Personal Care Home - Air Handling Unit Replacement #1

This project consists of upgrading the HVAC system to improve ventilation by increasing filtration and air changes.

$78,320

$19,580

City of Winnipeg

Cadham Provincial Laboratory - Cooling Upgrade

This project consists of a cooling system upgrade to increase the overall cooling capacity, providing suitable environmental conditions.

$80,000

$20,000

City of Winnipeg

Actionmarguerite - Replace and Upsize Rooftop Air Handling System

This project consists of upgrading the HVAC system to improve ventilation by increasing filtration and air changes.

$104,000

$26,000

City of Winnipeg

Bethania Personal Care Home - Main Air Handling Unit Mechanical Upgrade

This project consists of upgrading the HVAC system to improve ventilation by increasing filtration and air changes.

$109,024

$27,256

City of Winnipeg

Grace General Hospital - Critical Building Management Control System Upgrade Phase 2

This project consists of upgrading the HVAC system to improve ventilation by increasing filtration and air changes.

$112,000

$28,000

City of Winnipeg

Fred Douglas Lodge Personal Care Home - East Side Heat and Air Conditioning Unit Replacement

This project consists of upgrading to the buildings heating and cooling capacity to provide suitable environmental conditions.

$200,000

$50,000

City of Winnipeg

Ecole Precieux Sang - Boiler Replacement and Ventilation Upgrades

This project includes replacing the school’s boiler heating system capacity and the classroom unit ventilators.

$240,000

$60,000

City of Winnipeg

Health Sciences Centre (HSC) - Cooling/ Condensing Unit Replacement Phase 1

This project consists of upgrading the cooling system to increase the overall capacity to provide suitable environmental conditions.

$260,000

$65,000

City of Winnipeg

St. Boniface Hospital - Install Redundant Operating Room Exhaust Fan

This project includes supplying and installing supply and installation of redundant exhaust fans for site operating rooms to meet current healthcare code requirements.

$328,000

$82,000

City of Winnipeg

Health Sciences Centre (HSC) - HVAC Controls Upgrade Phase 1

This project consists of upgrading the HVAC control system to better provide optimal environmental conditions.

$560,000

$140,000

City of Winnipeg

Victoria General Hospital - HVAC Upgrade Phase 2 Operating Rooms

This project includes installing an additional AHU for site operating rooms to meet current healthcare code requirements.

$640,000

$160,000

City of Winnipeg

Misericordia Hospital - Building Management System Controls Upgrade Phase 1

This project consists of upgrading the HVAC control system to better provide optimal environmental conditions.

$680,000

$170,000

City of Winnipeg

Health Sciences Centre (HSC) - HVAC Controls Upgrade Phase 2

This project consists of upgrading the HVAC control system to better provide optimal environmental conditions.

$1,200,000

$300,000

City of Winnipeg

Health Sciences Centre (HSC) - General Hospital HVAC Upgrade Phase 10

This project consists of upgrading the HVAC system to improve ventilation by increasing filtration and air changes.

$1,200,000

$300,000

Page details

Date modified: