French River Dam complex
Completed projects

Infrastructure projects help to ensure safe and reliable dam operations.

Project to replace the boathouse and wharf and rehabilitate the workshop

The French River Dam complex includes a wharf, boathouse and workshop. Structural inspection had identified that the boathouse and wharf had reached the end of their service life. The boathouse and wharf were replaced with similar structures with a smaller footprint. The workshop foundation was rehabilitated to meet building code requirements.

In support of Indigenous reconciliation, the procurement process for construction was only open to Indigenous companies in accordance with the Set-aside Program for Indigenous Business. The project team had contacted and consulted with the local Dokis First Nation, as well as authorities having jurisdiction.

Benefits

Construction began in fall 2023 and was completed in spring 2024. There were no impacts to dam operations during construction.

The boathouse is a single-storey building for boat entry and sheltered mooring.

Boathouse

The wharf consists of a timber crib structure and also serves as a retaining wall.

Wharf

The workshop is a single-storey building with 1 room housing a shop area and storing a variety of equipment and building materials.

Workshop

New foundation of existing workshop

Southeast view of the new boathouse

Page details