Status report on transformational and major Crown projects – Government of Canada Network Wide Area Network Project

General information
Project name Government of Canada Network Wide Area Network (GCNet WAN) Project
Description Government of Canada Network Services
Project outcomes

Stream 1: National Internet Protocol (IP)

  • Consolidation of approximately 50 different WANs on 12 separate contracts into a single infrastructure on 2 contracts to provide national WAN services to SSC’s partners
  • IP-based service providing any-to-any network connectivity
  • Fully-managed service to 3,500+ sites across Canada

Stream 2: National Transport (Legacy)

  • Legacy point-to-point analog and digital services (700+ sites)

Stream 3: International

  • Both IP and Transport services
  • Service to approximately 220 locations internationally
Industrial benefits Private sector vendors will provide goods and services for the new service(s).
Sponsoring department Shared Services Canada
Contracting authority Shared Services Canada
Participating departments Shared Services Canada
Prime contractor

Stream 1 (Contractor 1) – TELUS
257 Slater Street, 7th floor, Ottawa, Ontario, Canada, K1P0A6

Stream 1 (Contractor 2) – Zayo Canada
150 Laurier Avenue West, 3rd floor, Ottawa, Ontario, Canada, K1P5J4

Stream 2 – TELUS
257 Slater Street, 7th floor, Ottawa, Ontario, Canada, K1P0A6

Stream 3 – Bell Canada
160 Elgin Street, 5th floor, Ottawa, Ontario, Canada, K2P2C4

Major subcontractors N/A
Project phase Phase 5 – Deployment
Major milestones
  • Phase 1 – Idea Generation – August 2013
  • Phase 2 – Initiation – October 2013
  • Phase 3 – Planning – August 2017
  • Phase 4 – Operational Readiness – August 2017
  • Phase 5 – Deployment – January 2020
  • Phase 6 – Closeout – March 2020
Progress report and explanation of variances

The overall project health is “red” due to the cumulative effect of various issues and risks that have led to the slippage of the Stream 1 migration schedule.

Stream 2 – forecast completion date is 30 Sept 2019

Stream 3 – forecast completion date is 31 Mar 2020

  • The GCNet WAN Project is achieving defined performance objectives (see note above re Stream 1 schedule slippage).
  • The GCNet WAN Project is currently running “on” budget (see note above re additional funding required to support Stream 1 schedule slippage).
  • The GCNet WAN Project is currently scheduled to be completed by March 2020 but will be seeking approval for March 2023 (to accommodate the Stream 1 migration schedule).