Status report on transformational and major Crown projects – Government of Canada Secret Infrastructure Expansion

General information
Project name Government of Canada Secret Infrastructure (GCSI) Expansion
Description The GCSI project’s duration is six years with the first 18 months devoted to planning activities. The estimated expanded sites and additional capabilities include adding 2000 users, 900 endpoints, 60 sites across the Government of Canada (GC) and 60 secure meeting rooms with voice and video conferencing up to SECRET. In addition to expanding new sites, new capabilities include high availability, low-to-high notifications and 24/7 support.
Project outcomes

The project aims to achieve the following business outcomes:

  • GC will have easy access to communicate securely using enterprise secure communications services, minimizing the need to use unmanaged legacy networks and unsecure means
  • GC workers will have access to real-time classified (SECRET) communication tools to support operational needs including during times of crisis
  • GC will be able to host classified (SECRET) mission-critical services that must be always available
  • Deliver an infrastructure system that can resist a data center level disaster
Industrial benefits
  • Adding 2000 users, 900 endpoints, 60 sites across the GC
  • 60 secure meeting rooms with voice and video conferencing up to SECRET
  • High availability and disaster recovery
  • Low-to-high data transfers and High to Low notifications
  • 24/7 enterprise support and Security monitoring
Sponsoring department Treasury Board of Canada Secretariat
Contracting authority Shared Services Canada
Participating departments Communications Security Establishment
Shared Services Canada
Treasury Board of Canada Secretariat
Prime contractor N/A
Major subcontractors N/A
Project phase Phase 3 - planning
Major milestones
  • Phase 1 – Idea Generation – March 2018
  • Phase 2 – Initiation – December 2018
  • Phase 3 – Planning – September 2020
  • Phase 4 – Operational Readiness – March 2023
  • Phase 5 – Deployment – December 2023
  • Phase 6 – Closeout – March 2024
Progress report and explanation of variances
  • The GCSI Expansion is achieving defined performance objectives
  • The GCSI Expansion is running on budget
  • The GCSI Expansion Gate 3 is to be completed by June 2020 as planned