Status Report on Transformational and Major Capital Projects
Project name |
Arctic and Offshore Patrol Ships |
||||||||||||||||||||||||||
Description | The objective of the Arctic and Offshore Patrol Ships (AOPS) project is to deliver six ice-capable offshore patrol ships that will be used by the Royal Canadian Navy (RCN) to conduct sovereignty and surveillance operations in Canada’s waters, including the Arctic, as well as to conduct a wide variety of operations abroad. | ||||||||||||||||||||||||||
Project outcomes | This project currently contributes to Program Inventory 5.1 Maritime Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Maritime equipment projects remain in approved scope, schedule and expenditure authority. The AOPS project has the following project outcomes:
Once the vessels are introduced into service they will be contributing to various Program Inventories under Operations and Ready Forces. The project will deliver the following capabilities to the Department of National Defence (DND) and the Canadian Armed Forces (CAF), specifically the RCN:
|
||||||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to this project. Canada will receive IRBs equivalent to 100% of the contracted value for the AOPS implementation. In-Service Support (ISS) of the vessels is managed separately under the Arctic and Offshore Patrol Ships and Joint Support Ship In-Service Support (AJISS) Contract which was awarded in 2017. | ||||||||||||||||||||||||||
Sponsoring department |
|
||||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||||
Participating departments |
|
||||||||||||||||||||||||||
Prime contractor | Acquisition: In-Service Support: Thales Canada Inc. and Thales Australia Inc. – Ottawa, Ontario, Canada. |
||||||||||||||||||||||||||
Major subcontractors |
|
||||||||||||||||||||||||||
Project phase |
|
||||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||||
Progress report and explanation of variances | The AOPS project is achieving project objectives, notably:
Scope: In November 2018, the Government of Canada approved the construction of a sixth ship. The project is on track to deliver its 2018 approved scope. As announced by the Government in May 2019, DND will also provide support to the AOPS variant project for the acquisition of two additional ships for the CCG. Cost: In November 2018, the Government of Canada approved the increased budget to build a sixth AOPS and to extend the production schedule. An assessment is ongoing to confirm cost and schedule impacts resulting from the COVID-19 pandemic. Schedule: In November 2018, the Government of Canada approved the extension of the production schedule by 18 months, thereby mitigating part of the production gap between the AOPS and Canadian Surface Combatant (CSC) construction. An assessment is ongoing to confirm cost and schedule impacts resulting from the COVID-19 pandemic. Year-end Results: In the (FY) 2021-22, the AOPS project achieved the following:
|
Project name |
Armoured Combat Support Vehicle Project |
||||||||||||||||||
Description | The Armoured Combat Support Vehicle (ACSV) Project will deliver an armoured combat support capability to provide Command Support, Combat Support and Combat Service Support to the forward elements of a Brigade Group. These capabilities include, but are not limited to, command vehicles, ambulances, and mobile repair teams. | ||||||||||||||||||
Project outcomes | This project currently contributes to Program Inventory 5.2 Land Equipment Acquisition of the Departmental Results Framework. Its outcome is to deliver the ACSV while remaining within approved scope, schedule and expenditure authority. The ACSV Project will procure 360 ACSV. Once complete, the project will contribute to Program Inventories under Operations and Ready Forces. The ACSV project will deliver the following capabilities and outcomes to the CAF, specifically the Canadian Army:
|
||||||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy was applied to the ACSV Implementation Contract. Total ITB obligation is $1,775M. | ||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED), and its regional development agencies | ||||||||||||||||||
Prime contractor | General Dynamics Land Systems - Canada (GDLS-C) – London, Ontario, Canada | ||||||||||||||||||
Major subcontractors |
|
||||||||||||||||||
Project phase |
|
||||||||||||||||||
Major milestones |
|
||||||||||||||||||
Progress report and explanation of variances | The ACSV is achieving project objectives, notably:
Scope: The project is on track to deliver its 2019 approved scope. Cost: The project is within the 2019 approved budget. Schedule: The project is currently on schedule to complete qualification testing and begin delivery to the Canadian Army of the first two variants in late 2022. Year-end Results: In the fiscal year 2021-22, the ACSV project achieved the following:
|
Project name |
Aurora Incremental Modernization Project |
||||||||||||||||||
Description | The objective of the CP-140 Aurora Incremental Modernization Project (AIMP) is to modernize Canada’s 14 CP-140 Aurora aircraft in order to maintain the fleet’s operational capabilities until the fleet’s current planned retirement date of 2030 (a study is currently underway to assess life extension to 2040). This work will provide the capability to conduct Intelligence, Surveillance and Reconnaissance (ISR) and Anti-Submarine Warfare (ASW) in order to detect threats to Canadian security as early as possible. | ||||||||||||||||||
Project outcomes | This project currently contributes to Program Inventory 5.3 Aerospace Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Aerospace equipment projects remain in approved scope, schedule and expenditure authority. AIMP has the following project outcomes:
Once the modernized fleet has been introduced into service it will contribute to various Program Inventories under Operations and Ready Forces. The CP-140 AIMP will deliver the following capabilities to the Department of National Defence and the Canadian Armed Forces, specifically the Royal Canadian Air Force (RCAF):
|
||||||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy of Canada’s Defence Procurement Strategy (DPS) applies to this project. Canada will receive ITBs equivalent to 100% of the contracted value of the General Dynamics Mission Systems - Canada acquisitions contract. | ||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||||||
Prime contractor (for Block IV) |
|
||||||||||||||||||
Major subcontractors | CAE - Montreal, Quebec, Canada | ||||||||||||||||||
Project phase |
|
||||||||||||||||||
Major milestones |
|
||||||||||||||||||
Progress report and explanation of variances | The AIMP project has achieved several project objectives, notably:
Scope: The Department has prepared a submission to seek an increase in project approval and expenditure authority to allow completion of the full scope of AIMP Block IV. Cost: The Department has prepared a submission to seek an increase in project approval and expenditure authority to allow completion of the full scope of AIMP Block IV. Schedule: As a result of delays in engineering, various technical issues and materialized risks, AIMP Block IV Initial and Full Operational Capability dates have been delayed from the 2015 approved schedule. Year-end Results: In the fiscal year 2021-22, the AIMP project achieved the following:
|
Project name |
Canadian Cryptographic Modernization Program |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Description | The objective of the Canadian Cryptographic Modernization Program (CCMP) is to modernize the Government of Canada’s aging cryptographic equipment and infrastructure in order to safeguard classified information and maintain Canada’s ability to establish secure communications both nationally and internationally. CCMP is an Omnibus Project that includes multiple sub-projects for modernizing cryptographic equipment and a cyclical project for modernizing the key management infrastructure. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project outcomes | This project currently contributes to Program Inventory 5.4 Defence Information Technology Systems Acquisition, Design and Delivery of the Departmental Results Framework. Its outcome is to ensure Information Technology capabilities address a capability gap or deficiency. The CCMP Omnibus Project will deliver affordable information protection to departments and agencies in the Government of Canada by means of the following sub-projects:
Once the project is complete, it will be contributing to various Program Inventories under Operations and Ready Forces. The project will deliver the following capabilities to the Department of National Defence and the Canadian Armed Forces:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Industrial benefits | N/A | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Sponsoring department | Communications Security Establishment (CSE) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Participating departments | Departments and agencies of the Government of Canada using cryptographic equipment to protect classified information | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Prime contractor | N/A | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Major subcontractors | Various allied manufacturers of cryptographic equipment | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project phase |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Major milestones | Project Approval:
CCMP Sub-Project Dates:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Progress report and explanation of variances | The CCMP Omnibus project is achieving project objectives, notably:
Scope: The CCMP Omnibus Project is on track to deliver its 2005 approved scope. Schedule: The schedule is dependent on the United States (U.S.) Cryptographic Modernization Initiative and the Key Management Infrastructure Program. Canada’s collaboration with the United States of America allows Canada to leverage U.S. research and development and maintain interoperability with its Allies. Completion dates for the sub-projects are regularly reviewed for alignment with the U.S. initiative/program. The CCMP Omnibus Project that was originally expected to end in 2016 has been extended to Fiscal Year (FY) 2025-26, due to increased complexity, delays in the CSMI Project that relies on the US Key Management Infrastructure Program, and delays in U.S. development of solutions and implementation into weapon platforms such as ships, submarines and aircraft. Year-end Results: In the FY 2021-22, the CCMP Omnibus Project achieved the following:
|
Project name
|
Canadian Surface Combatant Project |
||||||||||||||||||||||||
Description | The objective of the Canadian Surface Combatant (CSC) project is to acquire a new surface combatant capability that will replace the Iroquois-class destroyers and the Halifax-class frigates. This acquisition will provide the capability to monitor and defend Canadian waters and to make contributions to international naval operations. | ||||||||||||||||||||||||
Project outcomes | This project currently contributes to Program Inventory 5.1 Maritime Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Maritime equipment projects remain in approved scope, schedule and expenditure authority. The CSC project has the following project outcomes:
Once the vessels are introduced into service they will be contributing to various Program Inventories under Operations and Ready Forces. The CSC project will deliver the following capabilities to the Department of National Defence and the Canadian Armed Forces, specifically the Royal Canadian Navy:
|
||||||||||||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy of Canada’s Defence Procurement Strategy (DPS) applied to the evaluation and selection of an existing warship design and design team to design the Canadian Surface Combatant. Canada will receive equivalent to 100% of the contracted value for both the acquisition and the In-Service Support contracts. | ||||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED), and its regional development agencies | ||||||||||||||||||||||||
Prime contractor | Irving Shipbuilding Inc., Halifax, Nova Scotia, Canada | ||||||||||||||||||||||||
Major subcontractors |
|
||||||||||||||||||||||||
Project phase |
|
||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||
Progress report and explanation of variances | The CSC project is achieving project objectives, notably:
Scope: Industry was engaged in early 2016 on a potential refinement to the procurement strategy to competitively select an existing warship to modify rather than to develop a new design. Informed by this engagement, the Government announced the approval of the refined procurement strategy on 13 June 2016. The project remains on track to achieve the scope as approved in May 2016. Cost: The current Definition Phase initially focused on requirements reconciliation and is now in Preliminary Design to evolve the ship design. Completion of the individual design phases will progressively inform the costing of the project. This activity is being jointly undertaken by project staff, Irving Shipbuilding Inc. and its sub-contractors. Project costs have been revalidated through financial reviews conducted to support the project’s March 2021 Revised Project Approval (Definition Phase 2) corporate submission. Schedule: Following Definition Contract award in February 2019 and progress through the initial two years of design, the current Definition Phase is now expected to take five years to support the start of ship construction in 2023-24. While work is still underway with Canada’s prime contractor, Irving Shipbuilding Inc., to optimize a build schedule, first ship delivery is now expected to occur in the early 2030s (2030-33). The revised ship delivery schedule recognizes the complexity of the CSC design and is informed by best practices and lessons learned through allies who are building variants of the same design. Year-end Results: In the fiscal year 2021-22, the CSC project achieved the following:
|
Project name |
Fixed-Wing Search and Rescue Aircraft Replacement Project |
||||||||||||||||||
Description | The objective of the Fixed-Wing Search and Rescue Aircraft Replacement (FWSAR) project is to replace the capability provided by the legacy fixed-wing Search and Rescue (SAR) fleets of CC-115 Buffalo and CC-130H Hercules aircraft. This will be accomplished by acquiring new, sensor-equipped aircraft with long-term In-Service Support (ISS), to ensure the Canadian Armed Forces can continue to provide an acceptable response to SAR incidents anywhere in the Canadian Area of Responsibility (AoR). | ||||||||||||||||||
Project outcomes | This project contributes to Program Inventory 5.3 Aerospace Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Aerospace equipment projects remain in approved scope, schedule and expenditure authority. The FWSAR project has the following objectives:
The FWSAR project will deliver against the following core responsibilities of the Department of National Defence and the Canadian Armed Forces; specifically, for the Royal Canadian Air Force:
The primary beneficiary are those who require SAR Services. |
||||||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy of Canada’s Defence Procurement Strategy (DPS) applies to this project. Canada will receive ITBs equivalent to 100% of the contracted value for both the acquisitions and the In-Service Support. | ||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||||||
Prime contractor | Airbus Defence and Space S.A. – Madrid, Spain | ||||||||||||||||||
Major subcontractors |
|
||||||||||||||||||
Project phase |
|
||||||||||||||||||
Major milestones |
|
||||||||||||||||||
- | |||||||||||||||||||
Progress report and explanation of variances | The FWSAR project is achieving project objectives, notably:
Scope: The project is on track to deliver the 2016 approved scope. Cost: The project is currently within the 2016 approved budget. Schedule: During this reporting period, the project completed a re-baseline of its schedule that accounted for realized risk since the previous schedule re-baseline completed in 2020-21, and unforeseen technical issues. Year-end Results: In the FY 2021-22, the FWSAR project achieved the following:
|
Project name |
Future Fighter Capability Project |
||||||||||||||
Description | The objective of the Future Fighter Capability Project (FFCP) is to successfully acquire and transition into service 88 advanced fighter aircraft and associated equipment, weapons, infrastructure, information technology, and sustainment, including training and software support. This project will leverage Canadian capabilities and support the growth of Canada’s aerospace and defence industries. | ||||||||||||||
Project outcomes | This project currently contributes to Program Inventory 5.3 Aerospace Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Aerospace equipment projects remain in approved scope, schedule and expenditure authority. The FFCP has the following project outcomes:
Once the aircraft have been introduced into service they will be contributing to various Program Inventories under Operations and Ready Forces. The FFCP will deliver the following capabilities to the Department of National Defence and the Canadian Armed Forces, specifically the Royal Canadian Air Force:
|
||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy, including Value Proposition (VP), applies to the Future Fighter Capability Project to ensure that long term, high-quality economic benefits are leveraged for Canadian industry. As part of their bid package, FFCP eligible Suppliers were required to submit a proposal to make investments in Canadian industry that align with Canada’s VP objectives. More specifically, Canada has implemented a VP that seeks to motivate generational investments in Canada’s aerospace and defence industries over the coming decades, and that drives innovation, exports and skills development in Canada’s Key Industrial Capabilities including in such areas as In-Service Support, Aerospace Systems and Components and Space Systems. |
||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||
Prime contractor | To be determined (TBD) | ||||||||||||||
Major subcontractors | TBD | ||||||||||||||
Project phase |
|
||||||||||||||
Major milestones |
|
||||||||||||||
Progress report and explanation of variances | Scope: DND is collaborating with PSPC and ISED to replace the fighter fleet, focusing on options that match Canada’s defence needs. Cost: An acquisition budget of $15B-$19B Canadian was announced as part of Canada’s Defence Policy Strong, Secure, Engaged. The project’s implementation budget will be informed by ongoing project definition work and is contingent on approval as part of the Project Approval process for Implementation. Schedule: Notwithstanding adjustments and delays due to the COVID-19 pandemic and associated work restrictions, FFCP has continued to steadily progress throughout Fiscal Year (FY) 2021-22. This includes competition of the evaluation of submitted proposals, and the selection of the bidder to enter the finalization phase of the procurement process. The project continues to work toward awarding a contract in late 2022. The detailed design of an aircraft agnostic Fighter Squadron Facility in each of Cold Lake and Bagotville continues to progress, along with site preparation at these locations to support eventual construction activities. Year-end Results: In FY 2021-22, the FFCP achieved the following:
|
Project name |
Halifax-Class Point Defence Missile System Upgrade Project |
||||||||||||||||
Description | The objective of the Halifax-class Point Defence Missile System Upgrade (PDMSU) project is to develop and acquire an evolution to the current Evolved Sea Sparrow Missile (ESSM) Point Defence Missile System, fitted in the Halifax-class ships. This work will sustain the Royal Canadian Navy’s Halifax-class ships’ ability to defend against current and future threats originating from surface, sub-surface, air and land-based platforms. | ||||||||||||||||
Project outcomes | This project currently contributes to Program Inventory 5.1 Maritime Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Maritime equipment projects remain in approved scope, schedule and expenditure authority. The PDMSU project has the following project outcomes:
Once introduced into service, the missile and its capabilities will be contributing to various Program Inventories under Operations and Ready Forces. The PDMSU project will deliver the following capabilities to the Department of National Defence and the Canadian Armed Forces, specifically the Royal Canadian Navy:
|
||||||||||||||||
Industrial benefits | The development work, performed under the ESSM Block 2 Engineering and Manufacturing Development Memorandum of Understanding (MOU), consists of Government work and industrial work. While the Government work will be performed primarily by the United States government, the industrial work is shared among the contributing participants in accordance with their cost share percentages. Work share for Implementation Phase is governed by the MOU for the Production of the ESSM Block 2, with work share based on the country’s percentage of total missiles acquired. As a result, the work share is 100% of the value associated with the production of the contracted missiles. Canada’s Industrial and Regional Benefits (IRB) Policy does not apply to this project. |
||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||||
Prime contractor | NATO Sea Sparrow Surface Missile System Project | ||||||||||||||||
Major subcontractors | Raytheon Missile & Defense – Tucson, Arizona, USA | ||||||||||||||||
Project phase |
|
||||||||||||||||
Major milestones |
|
||||||||||||||||
Progress report and explanation of variances | The PDMSU project has achieved project objectives, notably:
Scope: The project is on track to deliver its 2017 approved scope. Cost: The project is currently within its 2017 approved budget. Schedule:
Year-end Results: In the fiscal year 2021-22, the PDMSU project achieved the following:
|
Project name |
Hornet Extension Project |
||||||||||||||||
Description | The Hornet Extension Project (HEP) will ensure that the Royal Canadian Air Forces (RCAF) Hornet fighter fleet is able to meet operational commitments, including to the North American Aerospace Defence Command (NORAD) and the North Atlantic Treaty Organization (NATO), until 2032 when the permanent replacement fleet is expected to be fully operational. | ||||||||||||||||
Project outcomes | This project currently contributes to Program Inventory 5.3 Aerospace Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Aerospace equipment projects remain in approved scope, schedule and expenditure authority. The HEP has the following project outcomes:
Once the aircraft have been upgraded they will be contributing to various Program Inventories under Operations and Ready Forces. The HEP will deliver the following capabilities to the Department of National Defence and the Canadian Armed Forces, specifically the RCAF:
|
||||||||||||||||
Industrial benefits | Industrial Technological Benefits (ITB) Policy will be considered for all acquisitions in excess of $20M to achieve 100% of total contract value in Canadian Content Value as Direct and Indirect ITB Transactions. The policy applies to six contracts: Sniper Pod contract with Lockheed Martin; Radome contract with The Boeing Company, GPS contract with Northrop Grumman, and with Raytheon for the APG-79(v) 4 Radar, AIM-9X missiles, and Joint Standoff Weapons (JSOW). | ||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||
Participating departments |
|
||||||||||||||||
Prime contractor | The Project is contracting through a combination of contract vehicles without a prime contractor. Primarily, equipment is being acquired through agreements with the United States Government under the Foreign Military Sales program, and some equipment is being acquired directly from Original Equipment Manufacturers. Engineering and integration work are being performed through two existing Prime Air Vehicle contracts in Canada. | ||||||||||||||||
Major subcontractors |
|
||||||||||||||||
Project phase |
|
||||||||||||||||
Major milestones |
|
||||||||||||||||
Progress report and explanation of variances | The HEP has achieved several project objectives, notably, on:
Scope: The project is on track to deliver the approved scope. Schedule: The project is currently on schedule to have equipment delivered and integration completed to meet the capabilities required for IOC by December 2023 and FOC by June 2025. Year-end Results: In the fiscal year 2021-22, the HEP achieved the following:
|
Project name |
Interim Fighter Capability Project |
||||||||||||||||||
Description | The objective of the Interim Fighter Capability Project (IFCP) is to acquire 18 surplus Australian F/A-18A/B aircraft, spares and equipment to supplement Canada’s existing CF-18 Hornet fleet to address the fighter capability gap. A secondary objective includes relocation of the Aerospace Engineering Test Establishment (AETE) from Cold Lake to the Ottawa Airport, including hangar renovations in Ottawa and the relocation of current occupants. | ||||||||||||||||||
Project outcomes | This project currently contributes to Program Inventory 5.3 Aerospace Equipment Acquisition of the Departmental Results Framework, its outcome is to ensure Aerospace equipment projects remain in approved scope, schedule and expenditure authority. The IFCP has the following project outcomes:
Once the fleet have been introduced into service, they will be contributing to various Program Inventories under Operations and Ready Forces. The IFCP will deliver the following capabilities to the Department of National Defence and the Canadian Armed Forces, specifically the Royal Canadian Air Force (RCAF):
|
||||||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy of Canada’s Defence Procurement Strategy (DPS) does not apply to the purchase of military equipment from a foreign government where a prime contractor is not involved. ITBs for the Canadian aerospace sector will be realized through opportunities for Canadian industry to provide additional In-Service Support to the surplus F/A-18A/B aircraft. | ||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||||||
Prime contractor | Acquired from the Australian Government through a Government to Government Purchasing Arrangement | ||||||||||||||||||
Major subcontractors |
|
||||||||||||||||||
Project phase |
|
||||||||||||||||||
Major milestones |
|
||||||||||||||||||
Progress report and explanation of variances | The IFCP project is achieving project objectives, notably: In Fiscal Year (FY) 2018-19, IFCP achieved the following:
In FY 2019-20, IFCP achieved the following:
In the FY 2020-21, IFCP achieved the following:
Year-end Results: In FY 2021-22, IFCP achieved the following:
Cost: The IFCP PMO will be requesting additional Project Authority and funding, aiming to complete the project within the approved scope. Schedule: Pending the additional Project Authority and additional funds, the IFCP has identified some major deliverables that will be delayed. Since these deliverables are not on the critical path, there is nil impact on the project’s re-baselined approved schedule. |
Project name |
Joint Support Ship Project |
||||||||||||||||||||||||||
Description | The objective of the Joint Support Ship (JSS) project is to deliver two new support ships to replace the Royal Canadian Navy’s (RCN) Auxiliary Oiler Replenishment vessels that have reached the end of their service. The capabilities required of the JSS are crucial to the RCN. These new Protecteur-class ships will enable a Naval Task Group to remain at sea for extended periods of time. These vessels will provide core replenishment capabilities, plus added capacity for limited sealift and limited support to operations ashore. | ||||||||||||||||||||||||||
Project outcomes | This project currently contributes to Program Inventory 5.1 Maritime Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Maritime equipment projects remain in approved scope, schedule and expenditure authority. The JSS project will deliver two JSS in support of Canada’s Defence Policy Strong, Secure, Engaged (SSE) strategic vision and primary missions (SSE initiative 29). Once the vessels are introduced into service they will be contributing to various Program Inventories under Operations and Ready Forces. The JSS project will deliver the following capabilities to the Department of National Defence and the Canadian Armed Forces, specifically the RCN:
|
||||||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to this project. Canada will receive IRBs equivalent to 100% of the contracted value for the acquisition. In-Service Support of the vessels is managed separately under the Arctic and Offshore Patrol Ships and Joint Support Ship In-Service Support (AJISS) contract which was awarded in 2017. |
||||||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||||||||||||||
Prime contractor | Acquisition: Vancouver Shipyards Co. – North Vancouver, British Columbia, Canada In-Service Support: Thales Canada Inc. and Thales Australia Inc. – Ottawa, Ontario, Canada. A single long-term In-Service Support Contract to support the AOPS and JSS vessels is in place. |
||||||||||||||||||||||||||
Major subcontractors |
|
||||||||||||||||||||||||||
Project phase |
|
||||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||||
Progress report and explanation of variances | The JSS project is achieving project objectives, notably:
Scope: The mandate to deliver two Joint Support Ships remains unchanged. Cost: The Project budget was reviewed and updated as part of the February 2020 project implementation approval. However, in light of the continued impacts of the COVID-19 pandemic, this cost estimate is currently under review. While a cost increase is expected, analysis of the updated build proposal and full impacts on the overall project is proceeding. Schedule: The Project schedule was reviewed and updated as part of the February 2020 project implementation approval. The ship deliveries are expected to be delayed due to COVID impacts on the shipyard and the supply chain. Year-end Results: In the fiscal year 2021-22, the JSS project achieved the following:
|
Project name |
Logistics Vehicle Modernization Project |
||||||||||||||
Description | The Logistics Vehicle Modernization (LVM) project will acquire a new fleet of light trucks of a 4 to 5 tonne cargo capacity; trailers and modules to mount on the trucks; trailers that will provide accommodation space to conduct various tasks (such as office space, command posts and workshops); and armoured protection kits for the cabs. The project will also acquire heavy trucks and trailers with a 16.5 tonne cargo capacity; trailers for engineering construction equipment and to transport a main battle tank; modules for accommodation and specialized cargo (such as fuel); and armoured protection kits for the cabs. The LVM project will pursue sustainment outcomes tailored to meet Canadian Armed Forces (CAF) operational requirements for the planned 20 years of service. The project will also fund new infrastructure and upgrades to existing infrastructure required to support the new fleets. | ||||||||||||||
Project outcomes | This project contributes to Program Inventory 5.2 Land Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Land equipment projects remain in approved scope, schedule and expenditure authority. The LVM project has the following project outcomes:
Once the fleets are brought into service, they will contribute to various Program Inventories under Operations and Ready Forces. The project will deliver the following capabilities to the Department of National Defence and the CAF, specifically to the Canadian Army:
|
||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy including the Value Proposition will apply to the LVM Project. The ITB obligation will be equal to the value of the contract. | ||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||
Prime contractor | To be determined (TBD) | ||||||||||||||
Major subcontractors | TBD | ||||||||||||||
Project phase |
|
||||||||||||||
Major milestones |
|
||||||||||||||
Progress report and explanation of variances | The LVM project is achieving Definition phase project objectives, notably:
Year-end Results: In November 2021, the LVM project hosted an Industry Consultation day with non-Qualified Suppliers. The RFP was released to the Qualified Suppliers on 9 December 2021. |
Project name |
Maritime Helicopter Project |
||||||||||||||||||||||
Description | The objective of the Maritime Helicopter Project (MHP) is to acquire a new maritime helicopter capability to replace the CH-124 Sea King. This acquisition will address the operational deficiencies of the current CH-124, eliminate the supportability difficulties of the older helicopter, and provide a sufficient fleet size of multi-purpose shipborne Maritime Helicopters for operations well into the 21st century. | ||||||||||||||||||||||
Project outcomes | This project contributes to Program Inventory 5.3 Aerospace Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Aerospace equipment projects remain in approved scope, schedule and expenditure authority. The MHP has the following project outcomes:
Once the fleet are introduced into service, they will be contributing to various Program Inventories under Operations and Ready Forces. The project will deliver the following capabilities to the Department of National Defence and the Canadian Armed Forces, specifically being delivered to the Royal Canadian Air Force, and will support the Royal Canadian Navy:
|
||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to this project. Canada will receive IRBs equivalent to 100% of the contracted value for the acquisitions and 80% of the contracted value for the In-Service Support portion from Sikorsky Aircraft. |
||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||||||||||
Prime contractor | Sikorsky International Operations Incorporated – Stratford, Connecticut, USA | ||||||||||||||||||||||
Major subcontractors |
|
||||||||||||||||||||||
Project phase |
|
||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||
Progress report and explanation of variances | Scope: On 18 June 2014, following a revised Project Approval (Implementation), the Government of Canada and Sikorsky International Operations Incorporated signed a contract amendment. This amendment extended the In-Service Support Agreement out to 2038 and re-baselined the project schedule. Cost: The MHP PMO will be requesting additional Project Authority and funding, aiming to complete the project within the approved scope. Schedule: MHP has identified a risk of slippage with its re-baselined approved schedule due to some deliverables pending additional Project Authority and Additional Funds. Year-end Results: In the fiscal year 2021-22, the MHP achieved the following:
|
Project name |
Medium Support Vehicle System Project |
Description | The objective of the Medium Support Vehicle System (MSVS) project is to acquire a new medium-weight truck capability that will replace the Medium Logistic Vehicle Wheeled (MLVW) fleet. The acquisition will provide the capability to transport troops, cargo, and equipment and to perform Unit level and combat services support functions. The capability provided by the ageing MLVW fleet is no longer supportable nor effective. |
Progress report and explanation of variances | The MG project is in project closeout:
|
Project name |
Mercury Global Project |
Description | The objective of the Mercury Global (MG) project is to acquire assured access to global wideband satellite communications (SATCOM) capabilities (between 70° North to 70° South), which currently provide the Canadian Armed Forces (CAF) with secure, reliable and high availability Beyond Line of Sight communications, enabling SATCOM connectivity for command and control of domestic and international operations. |
Progress report and explanation of variances | The MG project is in project closeout:
|
Project name |
Protected Military Satellite Communications Project |
||||||||||||||
Description | The Protected Military Satellite Communications (PMSC) project utilizes the United States (US) Department of Defense (DoD) Advanced Extremely High Frequency (AEHF) Military Satellite Communications (MILSATCOM) System to deliver worldwide (65ºN - 65ºS), assured, protected, secure, survivable, jam-resistant beyond long of sight communications between the national command authority and deployed forces in support of Canadian Armed Forces (CAF) missions. The PMSC project is providing the CAF with a protected, global MILSATCOM capability as well as interoperability with some of our principal allies; the US, United Kingdom, and the Netherlands. The project includes MILSATCOM terminals for deployed land, sea and air forces. | ||||||||||||||
Project outcomes | This project contributes to Program Inventory 5.4 Defence Information Technology Systems Acquisition, Design and Delivery of the Departmental Results Framework. Its outcome is to ensure Information Technology capabilities address a capability gap or deficiency. The PMSC project has the following project outcomes:
Once this new system is in place, it will contribute to various Program Inventories under Operations and Ready Forces. The project will deliver the following capabilities to the Department of National Defence (DND) and the Canadian Armed Forces (CAF):
|
||||||||||||||
Industrial benefits | The US DoD committed to a work share with Canadian Industry under the completed Phase 1 portion. Canada’s Industrial and Regional Benefits (IRB) Policy was applied to Phase 2 of this project and an IRB agreement was negotiated with Raytheon. Innovation, Science and Economic Development Canada will seek IRBs equivalent to 100% of the contracted value for both the acquisitions and the In-Service Support. | ||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||
Prime contractor | United States Department of Defense via Foreign Military Sales (FMS) | ||||||||||||||
Major subcontractors | Raytheon – Waltham, Massachusetts, USA | ||||||||||||||
Project phase |
|
||||||||||||||
Major milestones |
|
||||||||||||||
Progress report and explanation of variances | The PMSC project has achieved project objectives, notably:
Scope: The project is on track to deliver the 2003 approved scope. Cost: The project is currently within the 2003 approved budget. Risk mitigation strategies have been identified to minimize future costs due to installations that Schedule: The project is scheduled to achieve Effective Project Closeout in June 2022 after having completed the first of class installation and test of the PMSC system on the HMCS Corner Brook Victoria-Class Submarine in October 2021. The completion of the three remaining submarines will be done by DND/CAF. Due to slippages in the US DoD delivery of equipment combined with Canadian Patrol Frigate and Victoria Class Submarine work period scheduling challenges, the PMSC System Full Operational Capability, has moved to March 2029 from the original (2003 approved) expected date of November 2017. The In-Service Support of the Surface Fleet PMSC terminal was formally transitioned to Maritime Equipment Program Management in October 2020. The removal of the Lightweight Portable Terminal requirement was approved by the Defence Capabilities Board in April 2021. The extension of the Advanced Extremely High Frequency Operation & Support Memorandum of Understanding to 2034 was approved by the Office of the Secretary of Defence in October 2021. Year-end Results: In the fiscal year 2021-22, the PMSC project achieved the following:
The extension of the AEHF MOU was approved by Treasury Board and by the Office of the Secretary of Defence in October 2021. |
Project name |
Remotely Piloted Aircraft System Project |
||||||||||
Description | The project will deliver a Remotely Piloted Aircraft System (RPAS) project capability to support three Lines of Tasking, to provide Intelligence, Surveillance, Target Acquisition and Reconnaissance (ISTAR) information, and to deliver precision strike effects. The RPAS capability will be integrated as part of a networked, joint system-of-systems, in support of the Canada’s Defence Policy Strong, Secure, Engaged. | ||||||||||
Project outcomes | This project contributes to Program Inventory 5.3 Aerospace Equipment Acquisition of the Departmental Results Framework, and its outcome to ensure that Aerospace equipment projects remain in approved scope, schedule and expenditure authority. The RPAS project has the following project outcome:
Once this new system is in place, it will contribute to various Program Inventories under Operations and Ready Forces. The project will deliver the following capabilities to the Department of National Defence (DND) and the CAF, specifically to the Royal Canadian Air Force, and will support the Canadian Army, the Royal Canadian Navy, and the Commanders of the Special Operations Forces and Joint Operational Commands.
|
||||||||||
Industrial benefits | Canada’s Industrial and Technological Benefits (ITB) Policy applies to the acquisition and sustainment of the Remotely Piloted Aircraft System. This will require that industry make investments in Canada equal to the value of the acquisition and in-service support contracts/agreements. Canada will seek, through a competitive process, contractual commitments from industry that align with the Value Proposition (VP) strategic objectives. | ||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||
Prime contractor | To be determined (TBD) | ||||||||||
Major subcontractors | TBD | ||||||||||
Project phase |
|
||||||||||
Major milestones |
|
||||||||||
Progress report and explanation of variances | The project RPAS is achieving project objectives, notably:
Scope: The project is on track to deliver the approved scope. Cost: The project is currently within the approved budget. Schedule: The re-baselined project schedule was approved by Defence Procurement Strategy Governance in 2021. Year-end Results: In the fiscal year 2021-22, the RPAS project achieved the following:
|
Project name |
Strategic Tanker Transport Capability Project |
||||||||||
Description | The Strategic Tanker Transport Capability (STTC) project will provide the Royal Canadian Air Force (RCAF) with the ability to refuel aircraft in flight (Air-to-Air Refueling (AAR)) and the ability to provide airlift for personnel and equipment including aeromedical evacuation. The multi-role platform will provide AAR for both domestic and expeditionary coalition operations, while complementing the strategic airlift capabilities of the RCAF fleet. The STTC aircraft will have the adaptability to transfer between strategic AAR and strategic airlift roles with minimal changes to aircraft configuration. The STTC project will acquire sufficient aircraft to replace the existing fleet capability of five CC-150 Polaris aircraft, along with the necessary supporting infrastructure, training capability and associated In-Service Support. | ||||||||||
Project outcomes | This project will contribute to Program Inventory 5.3 Aerospace Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Aerospace equipment projects remain in approved scope, schedule and expenditure authority. The STTC project has the following outcomes:
The STTC project will deliver against the core responsibilities of the Department of National Defence and the Canadian Armed Forces:
|
||||||||||
Industrial benefits | The Defence Procurement Strategy applies to this project and DND is collaborating with Innovation, Science and Economic Development Canada to define its implementation. | ||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies. | ||||||||||
Prime contractor | Airbus Defence and Space S.A. – Madrid, Spain | ||||||||||
Major subcontractors | TBD | ||||||||||
Project phase |
|
||||||||||
Major milestones |
|
||||||||||
Progress report and explanation of variances | Scope: The project is on track to deliver the 2020 approved scope, notably:
Cost: The project is currently within the approved budget. Schedule: The project is on track to seek approval for the Implementation Phase. Year-end Results: In the fiscal year 2021-22, the STTC project achieved the following:
|
Project name |
Underwater Warfare Suite Upgrade Project |
||||||||||||||
Description | The objective of the Underwater Warfare Suite Upgrade (UWSU) project is to modernize the underwater warfare sensor suite currently installed in the Halifax-class frigates. The work will address deficiencies, improve ship underwater sensor performance in the challenging littoral environment and provide a system design to enable continual improvement in a cost-effective manner. The UWSU project will improve the performance of the underwater sensors through the upgrade and/or replacement of the components of the underwater warfare sensor suite. The UWSU In-Service Support Contract (ISSC) will provide long-term, full-spectrum support to the UWSU systems. | ||||||||||||||
Project outcomes | This project contributes to Program Inventory 5.1 Maritime Equipment Acquisition of the Departmental Results Framework. Its outcome is to ensure Maritime equipment projects remain in approved scope, schedule and expenditure authority. The UWSU project has the following project outcomes:
Once vessels are outfitted with the required upgrades, they will contribute to various Program Inventories under Operations and Ready Forces. The project will deliver the following capabilities to the Department of National Defence and the Canadian Armed Forces, specifically to the Royal Canadian Navy:
|
||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy of Canada’s Defence Procurement Strategy (DPS) applies to this project. Canada will receive ITBs equivalent of 100% of the contracted value for both the acquisition and In-Service Support. | ||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||
Prime contractor | General Dynamics Mission Systems-Canada, Ottawa, Ontario and Dartmouth, Nova Scotia, Canada | ||||||||||||||
Major subcontractors |
|
||||||||||||||
Prime contractor (In-Service Support) |
General Dynamics Mission Systems-Canada: Ottawa, Ontario and Dartmouth, Nova Scotia, Canada | ||||||||||||||
Project phase |
|
||||||||||||||
Major milestones |
|
||||||||||||||
Progress report and explanation of variances | The UWSU project has achieved project objectives, notably:
Scope: The project is on track to deliver the implementation phase approved scope of full upgrades for all twelve Halifax-class ships. Cost: The implementation phase expenditures remain within the current authorized budget. Schedule: Key milestones toward an Initial Operating Capability are being actively managed against technical and schedule challenges. Docking work period and trials readiness program schedules have impacted project schedules towards Initial and Final Operational Capability achievement.
|
Project name |
Victoria Class Modernization Project |
||||||||||||||||||||||||
Description | Victoria Class Modernization (VCM) project will provide the modernized and increased capabilities necessary to maintain the Victoria-class submarines’ operational relevance through the mid-late 2030s. | ||||||||||||||||||||||||
Project outcomes | The main objectives of the VCM enterprise are to make Canada and its allies stronger by:
|
||||||||||||||||||||||||
Industrial benefits | Industrial Technological Benefits Policy will be considered for all acquisitions in excess of $20M. | ||||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||
Participating departments |
|
||||||||||||||||||||||||
Prime contractor | The Project is contracting through a combination of contract vehicles without a prime contractor. | ||||||||||||||||||||||||
Major subcontractors | No contracts have been let at this time. | ||||||||||||||||||||||||
Project phase | Individual projects within VCM are currently split between the Options Analysis, Definition, and Implementation Phases. | ||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||
Progress report and explanation of variances | The VCM project is achieving project objectives, notably:
Scope: The project is on track to deliver the approved scope. Cost: The project is within its approved budget. Schedule: The project remains aligned with the schedule approved as part of the November 2020 project definition approval. Initial Operational Capability is scheduled for January 2028 and Full Operational Capability is scheduled for December 2033. Year-end Results: In the fiscal year 2021-22, the VCM project achieved the following:
|
Page details
- Date modified: