Archived: Departmental Plan 2018 to 2019, supplementary tables, Environment and Climate Change Canada, chapter 3

Status Report on Transformational and Major Crown Projects

Randle Reef Sediment Remediation Project

Description

Randle Reef is an area of highly contaminated sediment located on the south shore of Hamilton Harbour in the western end of Lake Ontario, and is considered to be the largest and one of the more complex and highly contaminated sediment sites in the Great Lakes. With the remediation of the Sydney Tar Ponds nearing completion, Randle Reef is now the largest polycyclic aromatic hydrocarbon (PAH) contaminated sediment site in Canada. Sediment remediation is required to reduce the environmental impacts of contaminants, including the PAHs and heavy metals located at this site.

Owing to the long history of contamination (more than 150 years) from multiple sources, it is not possible to apply the polluter pay principle. Instead, a shared responsibility model has been adopted with the Government of Canada, Government of Ontario and the local community, participating equally in the design and implementation of a solution. This legacy site is a priority for remediation in the Hamilton Harbour Remedial Action Plan (RAP) and under the Canada-U.S. Great Lakes Water Quality Agreement (GLWQA).

The Randle Reef Sediment Remediation project involves the construction of a 6.2 ha engineered containment facility (ECF) over the most highly contaminated sediment, dredging and placement of additional contaminated sediment within the facility, and in-situ capping and isolation of remaining targeted sediment for a grand total of 695,000 m3 of sediment being managed.

Project outcomes

The objective of the project is to contribute to the improvement of environmental conditions in Hamilton Harbour and to assist in the delisting of the harbour as an Area of Concern. Performance of the remediation project will be measured with a set of indicator studies designed to assess the effectiveness of the sediment remediation project. Indicator studies have been undertaken for the project to establish baseline biological and chemical conditions in the remediation area, and will be used to assess the effectiveness of the project through a comparison with post-remediation conditions. The studies include:

The Randle Reef Sediment Remediation Project will prevent or reduce the spread of PAH‑contaminated sediment from the project site into the rest of the harbour. The remediation of Randle Reef will improve water quality and reduce contaminant levels in biota, eventually making it safer to consume fish caught in the harbour. It will also remove current restrictions on navigation and generate economic returns through the creation of valuable port lands.

Industrial benefits

Hamilton Harbour is a 2,150 ha embayment located at the western end of Lake Ontario and connected to the lake by a single ship canal across the sandbar that forms the bay. The Harbour accommodates a commercial port and is considered a major shipping centre. The south shore of the harbour supports the highest concentration of heavy-metal industries (primarily iron and steel) in Canada.

The contaminated sediment targeted for remediation is located at Randle Reef along the south shore of Hamilton Harbour in the vicinity of piers 14, 15 and 16. The ECF will be connected to Pier 15, owned by the Hamilton Port Authority (HPA).

Following project completion, the HPA will develop and operate the surface of the ECF  as a marine facility and will be responsible for ongoing monitoring and maintenance. The majority of the site may be developed into a marine terminal that will be suitable for ships of Great Lakes Seaway draught.

In 2007, a research study by York University revealed that the net benefits (environmental, social and economic) of cleaning up Randle Reef were estimated as $126 million over 25 years. The proposed Randle Reef Contaminated Sediment Remediation Project will further advance the economic competitiveness of the region through expanded port facilities, shoreline redevelopment and the creation of approximately 60 jobs a year over the 7-year life of the project.

Sponsoring department

Environment and Climate Change Canada (ECCC)

Contracting authority

Public Services and Procurement Canada  (PSPC)

Participating departments

Not applicable

Prime contractor

Stage 2:  Milestone Environmental Contracting Inc. and Fraser River Pile and Dredge (GP) Inc. 

Major subcontractors

Stage 2:  Veolia Water Technologies Inc.

Project phase

This project is being constructed in three stages and is now in Stage 2 (dredging) of the implementation phase. The Canadian Environmental Assessment Agency Comprehensive Study report was signed by the Minister in May 2013. Project implementation agreements between Environment and Climate Change Canada and each of the project funding organizations were signed in September 2013, following which the Department entered into a specified service agreement with Public Services and Procurement Canada (PSPC) to implement the project as the contracting authority. Following an unsuccessful tender in 2014, the project design and implementation plan were optimized to reduce the cost of the project. PSPC’s contract tendering process was completed in the Spring 2015 towards a construction start in the fall of 2015. The Hamilton Port Authority is the contract authority for re-construction of the adjacent Pier 15 harbour wall which is necessary to allow contaminated sediments to be dredged from this area in Stage 2 of the project. Stage 1, ECF construction began in April 2016 and the facility was substantially complete in December 2017. The contracts for Stage 2 dredging were issued in 2017 in order for work to commence in 2018.

Major milestones

2013–15 – Pre-construction preparations

September 2015 to December 2017 – Stage 1: ECF Construction

January 2018 to December 2019 – Stage 2: Dredging and Containment

2019–20 to December  2022 – Stage 3: Capping and Landscaping

2022–23 to 2036–37 – Post-construction Monitoring/Maintenance

Progress report and explanation of variances

The Treasury Board approved the Randle Reef Sediment Remediation Project on December 13, 2012, with an estimated cost of $138.9 million. The construction phase of the project is scheduled to be completed in 2022, with post‑construction monitoring to continue for an additional 15 years to 2037.

This 7 year project will be implemented in a staged approach, and led by Environment and Climate Change Canada with PSPC as the contract authority and project manager. Legal agreements have been negotiated for cost sharing of the project with Environment and Climate Change Canada, Ontario and the local community each contributing one-third of the project cost.

The initially planned 2014 project start date was delayed as a result of contractor bids on the first stage of the project exceeding cost estimates for this stage. Environment and Climate Change Canada and the project funding partners subsequently evaluated a range of options to advance the project in a manner which will achieve the environmental objectives within available resources. The Minister of the Environment and Climate Change and the project partners agreed on a plan for a modified project design and the project was successfully re-tendered in 2015.

In-water work began in September 2015 with the reconstruction of an adjacent pier which was required to facilitate dredging in the second stage of the project.  Pier re-construction was complete in June 2016.

Stage 1 construction of the ECF began in April 2016 and the ECF was completed on schedule and budget in December 2017.

Contracts for Stage 2 construction (dredging) were awarded in 2017. The contractor began site preparations in November to be ready to commence dredging of the contaminated sediments in the spring of 2018. 

Canadian Weather Radar Replacement Project

Description

The Canadian Weather Radar Replacement Project (CWRRP) is an infrastructure project to replace the obsolete and aging radars with new modernized systems. The primary driver is to replace increasingly unreliable radar systems with new systems that will stabilize operating costs for the network and provide radar data that is more reliably available and consistent in quality.

When the CWRRP is complete, the radar network will be completely upgraded, affordable to operate and will include:

  1. thirty-two (32) new operational radars and one (1) training radar, including all infrastructure and any necessary real estate requirements;
  2. radars that will increase Doppler coverage and have the capability to provide dual polarized data;
  3. a modest extension of the network in the lower Athabasca region of Northeastern Alberta;
  4. an affordable, mature and fully documented life-cycle management system, including the training radar;
  5. all formal technical documentation and training required to operate the network;
  6. upgraded data processing systems incorporating applied science work that ensures data integrity and utility.  

This project supports the following Core Responsibility and Program Inventory that relates to weather services and indicates that:

Core Responsibility: Predicting Weather and Environmental Conditions

Program Inventory: Weather and Environmental Observations, Forecasts and Warnings

Project outcomes

The Business Outcomes are articulated in the Department’s Departmental Plan (DP) structure. The Business Outcomes are supported by the goals of this Radar Project. In fact, this Radar Project is one of several projects and initiatives, funded through Budget 2011 and Budget 2013, within a portfolio intended to modernize Canada’s Weather Services. These commitments stem from the Government’s recognition that significant investments are required to ensure the modernization and sustainability of Canada’s weather services into the future, from monitoring to forecasting.

Reliable, timely, and accessible radar observations are critical to the production of weather forecasts and warnings of severe weather for informed decision making by Canadians. Radar data and products form a critical part of the foundation for achieving the high level Public Good mandate of Environment and Climate Change Canada (ECCC) programs related to the safety and security of Canadians.

The goals of the project is to:

Industrial benefits

In Canada, weather-related events account for 80% of disasters with significant consequences for the health and safety of citizens and to Canada’s economic performance. Industries that are directly affected by weather conditions, such as transportation, agriculture, tourism and forestry, account for over 30% of the annual Gross Domestic Product (GDP).

New radars will increase radar data availability to the public and clients (including first responders), which allows for Canadians to better predict, prepare for, and respond to weather related emergencies and natural disasters  and will provide more timely warnings of severe weather. 

Sponsoring department

Environment and Climate Change Canada (ECCC)

Contracting authority

Public Services and Procurement Canada  (PSPC)

Participating departments

Shared Services Canada (SSC)

Prime contractor

Selex ES GmbH, located in Neuss, Germany

Major subcontractors

WesTower Communications Canada

Project outcomes

This project is in the implementation phase. The Treasury Board Submission for the project was approved on May 19th, 2016 without conditions for $206.9M. On June 21, 2016, PSPC awarded the CWRRS contract to the successful bidder, Selex ES GmbH, located in Neuss, Germany. The contract is for 20 new radar systems, with 13 additional options, including infrastructure, training and documentation.

Major milestones

TBS approval of Radar Renewal funding

19/May/2016

PSPC award of contract to Selex

21/Jun/2016

Approval of Final Implementation Plan

27/Feb/2017

Site preparation activities

30/Sep/2022

Adaptation, testing, implementation of URP completed

1/Jul/2022

New Radar Scan Strategy

1/Jul/2017

SSC - Telecom and data center upgrades

31/Mar/2022

First Radar installation

15/Dec/2017

Second Radar installation

31/Jul/2018

Firm radar installs 2-20

1/May/2020

Optional radar installs 21-33

30/Sep/2022

Decommissioning of old radars

31/Mar/2023

Project Close-Out - transfer of ownership

31/Mar/2023

Project outcomes

The Canadian Weather Radar Replacement Project (CWRRP) is a seven-year project to replace Canada's weather radar network. The project will replace 31 existing radars with modern radars systems and associated infrastructure, add one new radar site in Alberta (Lower Athabaska region) and add a new training site. A contract was awarded in June 2016 for the installation of 20 systems with options for up to 13 additional ones to replace the balance of the existing network and add the new site plus the training site.

We just completed the first year of the implementation phase and the project remains on schedule and on budget to deliver the first site installation in Radisson, SK during Fiscal Year (FY) 2017–18 followed by four additional installations in FY 2018–19.

Page details

Date modified: