Construction: Committee of the Whole—August 12, 2020

Document navigation for "Committee of the Whole: August 12, 2020"

National Capital Region bridges

Context

Budget 2019 provided funding to replace the Alexandra Bridge, support for rehabilitation and ongoing maintenance of the MacDonald-Cartier Bridge and the Chaudière Crossing, as well as the directive to refresh studies on a potential sixth interprovincial crossing in the National Capital Region (NCR), and develop a Long-term Integrated Interprovincial Crossings Plan.

Suggested response

If pressed on a sixth crossing:

If pressed on replacing the Alexandra Bridge:

If pressed on the program of work:

If pressed on the Long-term Integrated Interprovincial Crossings Plan:

Background

There are 5 crossings in the NCR. PSPC manages and operates the Alexandra Bridge (built in 1900), Chaudière Crossing (portions built in 1828, and Union Bridge built in 1919) and the Macdonald-Cartier Bridge (built in 1965). The NCC manages and operates the Champlain Bridge (built in 1928) and the Portage Bridge (built in 1973).

The 5 crossings are currently at full capacity at peak travel periods (average daily traffic on all crossings: 187,000 vehicles daily; 9,000 using active transportation). Transportation studies conducted over the last 10 years have consistently shown that the existing Ottawa River crossings and connecting roadways are at full capacity during morning and evening peak travel times.

Alexandra Bridge condition

A 2017 third-party life-cycle cost assessment concluded that replacing the 120-year-old Alexandra Bridge is the most cost-effective alternative, as it will have reached the end of its life span within the next 10 years. A recent structural evaluation of the bridge (completed in March 2020) revealed that due to the deterioration of several bridge members, load restrictions were required. Its replacement has become more critical after inspectors found an unexpected structural flaw, which forced the bridge’s closure from May 1 to 23 for emergency repairs. Other repair projects are planned and will be completed to ensure the bridge remains safe and accessible until its replacement.

Sixth crossing

Budget 2019 directed the NCC to “Address the demonstrated need for an additional NCR crossing by refreshing existing studies and developing a long-term integrated interprovincial crossing plan with both provincial governments and the cities of Gatineau and Ottawa.” Additional crossings could help to reduce congestion, improve fluidity and increase transportation options throughout the region.

Long Term Integrated Interprovincial Crossings Plan

Budget 2019 also announced that the NCC would lead the development of a Long-term Integrated Interprovincial Crossings Plan. The result of this plan will be a long-term strategy with a vision and approaches for all parties to build on past successes and move forward to meet new and emerging challenges. The plan will set long-term targets as well as provide options on how we may achieve the vision, and address the following issues:

Timing

The study refresh on a potential sixth crossing has been completed while the Long-Term Integrated Interprovincial Crossing Plan is expected to be completed in late 2021.

We are at the preliminary phase of the Alexandra Bridge replacement project which includes environmental studies and assessments, as required by the Impact Assessment Act.

Other bridge projects

In addition to the studies and projects listed above, the government supported the rehabilitation and ongoing maintenance of the NCR crossings, including the Alexandra Bridge, Chaudière Crossing and Macdonald-Cartier Bridge in Budget 2019 over 10 years.

Through the approval of Supplementary Estimates (A), the NCC received additional appropriations from Parliament to address the condition of its assets. Included in this funding was an investment to address the maintenance and rehabilitation requirements of the Champlain and the Portage bridges. Those projects are set to commence in 2020.

Rehabilitation of the Supreme Court of Canada and the West Memorial buildings

Context

From 2019 to 2023, the West Memorial Building (WMB) will undergo rehabilitation in order to meet the standards of the National Building Code of Canada.

Once rehabilitation is complete, the WMB will temporarily accommodate occupants of the Supreme Court of Canada Building (SCCB) from 2023 to 2028, as the SCCB undergoes its own rehabilitation.

Suggested response

If pressed on current building conditions:

Background

The WMB has been vacant since 2008 and requires major rehabilitation in order to meet the standards of the National Building Code of Canada. Work began in fall 2019 and will include upgrades to meet current building standards for sustainability, health and safety, and accessibility, while at the same time conserving its heritage character.

The selection of the WMB for rehabilitation makes sense as it will allow a vacant classified federal heritage building, within the downtown Ottawa area to return to the active federal real estate portfolio.

From 2019 to 2023, the WMB will undergo its rehabilitation. It will serve as an interim space for occupants of the SCCB from 2023 to 2028 The SCCB rehabilitation will take place from 2023 to 2028 once the occupants have moved into the WMB.

The contract award to EllisDon Corporation for construction management services was announced on October 26, 2018, and the contract to Moriyama & Teshima Architects and Kasian Architecture Interior Design and Planning Ltd. for design and architectural services was announced on February 23, 2018, for the WMB rehabilitation project.

Demolition started in October around the site. A City of Ottawa permit was received and construction started in April 2020. COVID-19 pandemic situation has had minimal impact on the project schedule.

Rehabilitation of the National Capital Commission assets including 24 Sussex and Harrington Lake

Context

The Official Residences of Canada: Asset Portfolio Condition Report, identified a requirement for a one-time injection of $83 million over 10 years to address the deferred maintenance deficit for all 6 official residences and ensure that the official residences meet universal accessibility and sustainability requirements.

Note

The numbers in the asset condition report represent recommended and projected investments based on 2017 asset values, not actual expenditures/commitments/planned spending by the National Capital Commission (NCC).

Suggested response

If pressed on Harrington Lake rehabilitation costs:

If pressed on the NCC’s Asset Portfolio Condition Report:

Background

Official Residences of Canada Asset Portfolio Condition Report

In 2017, the NCC commissioned in-depth building condition reports for the largest and most complex buildings in the official residences portfolio. These reports found that 58% of the assets in the official residences portfolio were considered to be in ‘poor’ to ‘critical’ condition, including half of the main official residences (24 Sussex and Harrington Lake main cottage are in critical condition while the farm is in poor condition). The complete report, Official Residences of Canada Asset Portfolio Condition Report, was endorsed by the NCC Board of Directors in April 2018 and publicly released in October 2018.

The report reflects an in-depth analysis of the official residences asset portfolio and highlights the shortfall in funding required to restore and maintain these heritage buildings.

24 Sussex

On October 16, 2018, the NCC released the Official Residences of Canada: Asset Portfolio Condition Report, which found that 24 Sussex Drive was in “critical” condition. The report identified a requirement for a one-time injection of $83 million over 10 years to address the deferred maintenance deficit for all 6 official residences, and a further $24.6 million annually for ongoing maintenance, repairs and renovations. The implementation of this 10-year recapitalization plan would also need to consider the investment required to ensure that the official residences meet universal accessibility and sustainability requirements, as well as escalation.

Over the last decade, the NCC has completed significant work at 24 Sussex including the rehabilitation of chimneys and fireplaces, fire compartmentalization, stabilization of the escarpment at the back and west sides of the property and the removal of hazardous materials from the main building. However, it has not been able to proceed with the extensive rehabilitation of the residence and has been limited to completing work on the repairs relating to health and safety that were urgently required.

As 24 Sussex Drive has not seen significant investment in over 60 years, the additional work required would include the rehabilitation of the building envelope, mechanical and electrical systems, all buildings on the site would require extensive recapitalization and NCC would need prolonged access to the residence.

Construction activities on the main residence would allow for the abatement of hazardous materials, retention of certain heritage components, improvement in the building envelope, replacement of mechanical and electrical systems, construction of universally accessible entrances and washrooms, creation of dining facilities and support spaces to accommodate state functions.

Harrington Lake

While the main cottage at Harrington Lake is 95 years old, most of the buildings were built between 1850 and 1925. Harrington Lake, the official country residence of the Prime Minister, is used for both official and private functions, with buildings that can accommodate official business as well as state visits.

Harrington Lake last saw major capital investment during the 1950s (over 60 years ago); the property has not seen any investment since 2005, when the NCC made critical repairs to the roofing, eavestroughs, piping, electrical, mechanical and structural systems of the property. The Harrington Lake property was deemed to be in critical condition in the NCC’s 2018 Official Residences of Canada: Asset Portfolio Condition Report (see pages 38 to 43).

Federal construction work

Context

On May 11, commercial construction re-opened in the province of Quebec, and on Thursday, May 14, the Government of Ontario communicated that all construction work could resume effective May 19.

Suggested response

If pressed on the Parliamentary Precinct:

If pressed on the Canadian Construction Association (CCA) request to support industry:

Background

PSPC continues to monitor the situation to ensure that any decision regarding construction sites respects the advice of public health officials and aligns with the CCA’s standardized COVID-19 protocols for all Canadian construction sites and respective provincial and territorial government direction.

The CCA has voiced their support for keeping federal construction sites open and its workforce employed on project sites that can meet a high standard of health and safety measures and that involve defence, security, infrastructure and the administration of justice and government. Federal unions (for example, Unionized Building and Construction Trades Council) wrote to the Minister directly expressing their gratitude for maintaining jobs by keeping the Parliament Hill site open specifically, noting that it is among the safest in the country.

Projects not aligned with the revised Province of Ontario directives have paused construction work. The 85 demobilized projects are in 3 primary categories:

Status of the Long Term Vision and Plan for the Parliamentary Precinct

Context

Public Services and Procurement Canada (PSPC) is implementing the Long Term Vision and Plan (LTVP)—a multi-decade strategy to restore and modernize the Parliamentary Precinct.

Suggested response

If pressed on governance and costs for the Centre Block:

If pressed on redevelopment of block 2:

Background

The LTVP was first approved in 2001 for the restoration and modernization of Canada’s Parliamentary Precinct. All major projects continue to track on time and budget.

PSPC has invested approximately $3.5 billion in the Parliamentary Precinct to-date, which has created over 25,000 jobs in local and national economies in, for example, engineering, architecture, construction, manufacturing and skilled trades sectors.

The restored West Block and Senate of Canada Building and the new Visitor Welcome Centre (Phase 1), were transferred to Parliament in fall 2018. These projects followed the completion of the 21 key projects since the Library of Parliament in 2006, including the 180 Wellington Building (2016) and the Sir John A Macdonald Building (2015).

Efforts are now focused on restoring and modernizing the Centre Block and leveraging the remaining 23 assets in the precinct to create an integrated parliamentary campus that addresses Parliament’s long term requirements, including material handling, the movement of people and goods, accessibility, sustainability, and security.

Restoring the Centre Block is a core objective of the LTVP. It will be the largest project of its kind in Canadian history. The program is on track and several key milestones have been accomplished:

PSPC is working with the parliamentary partners (Senate, House of Commons, the Library of Parliament, and the Office of the Prime Minister and Privy Council) to finalize their functional and design requirements (for example, number, size and types of functional spaces such as offices and committee rooms). The outcomes of these assessments and outreach will directly support the design efforts of the building rehabilitation. The completion of the schematic design is planned for spring 2020. This will inform the baseline scope, schedule and budget for the Centre Block rehabilitation.

Parliament Hill draws millions of visitors annually and is a key driver of tourism that contributes significantly to the Ottawa economy. PSPC is committed to ensuring that a positive visitor experience continues during the rehabilitation program.

PSPC has leveraged the LTVP to create opportunities for Canadians, including youth and Indigenous Peoples. We have committed to include provisions in all of our major projects’ contracts that would subcontract at least 5% of work to Indigenous firms.

The LTVP is reducing the government’s carbon footprint. PSPC has already reduced greenhouse gas levels in the precinct by 56% from 2005 levels and is on track to reach 80% by 2030 while also diverting more than 90% of demolition materials from landfills.

The precinct is a model for accessibility. It will achieve, and in some cases exceed, accessibility standards. The West Block and Senate of Canada Building include barrier-free access and improved accessibility features in the Chambers, public galleries, offices, meeting places, washrooms and corridors.

Big Bar landslide remediation

Context

The contract for the Big Bar landslide in British Columbia has increased to over $53.5 million since it was awarded on December 31, 2019, at an original value of $17.6 million to Peter Kiewit Sons ULC.

Suggested response

If pressed on contract amendments:

Background

PSPC is working with the DFO to improve fish passage in the Fraser River in response to a landslide near Big Bar, north of Lillooet, British Columbia, that was discovered in June 2019.

On November 27, 2019, PSPC, on behalf of DFO, published a request for information on www.BuyandSell.gc.ca for the purpose of seeking industry feedback on possible options and capacity to address the Big Bar landslide.

In accordance with trade agreement provisions and based on the information gathered through the RFI, 5 suppliers were invited to submit a proposal by December 27, 2019. A limited tender process was completed.

The remediation project is occurring on the traditional territories of the Secwepemc Nation, specifically High Bar First Nation and Stswecem’c Xget’tem First Nation. The contract includes an Indigenous Benefits Plan to provide socio-economic benefits to these 2 First Nations consisting of opportunities related to subcontracting, employment, skills and development and training, protocols, community engagement and other measures.

When the landslide occurred, a large volume of rock fell into the river (approximately 75,000 cubic metres). Therefore, removal and restoration of the river will take multiple construction seasons and a long-term response and commitment. 

Without immediate environmental remediation, many salmon stocks native to the upper Fraser River may become extinct. These impacts could result in economic losses throughout British Columbia and pose risks to the food security and culture of many First Nations communities.

Cold spring weather and the consequent late arrival of the spring freshet allowed more time for completing additional urgent works that were made possible through contract amendments.

As of May 29, 2020 there have been 18 change-orders processed, resulting in a total contract value of $53.5 million. These change orders encompass work such as additional scaling, slope stabilization and protection systems, civil work to support the installation of a pneumatic fish transport system, installation of ancillary equipment to supply water and power to the fish transport system, increased road maintenance costs, costs associated with increased quantities and costs related to additional shifts resulting from weather shut downs, as well as site direct and indirect costs related to the contract extensions.

In addition, it is important to note that the slide site is in an isolated, remote canyon with harsh weather conditions and constant rock fall danger. The costs associated to perform this work reflect the dynamic nature of the response required at Big Bar to improve fish passage.