French River Dam complex
Portage Channel Bridge replacement project

Find key information about the Portage Channel Bridge replacement in the French River area of northeastern Ontario. Learn what the project includes, when construction will take place, how it may affect access, and how it will improve safety and reliability.

On this page

Project overview

Location
Dokis, Ontario
Locate the Portage Dam from the French River Dams Site on a map
Type of project
Replacement
Lead department
Public Services and Procurement Canada
Project status
Design
Next steps
Public Services and Procurement Canada (PSPC) plans to launch the tender for construction contract services in late 2026 or early 2027. Construction is expected to start in spring 2027.

Project description

The current Portage Channel bridge was built in 1986. It has reached the end of its service life.

PSPC must replace the bridge to maintain safe and reliable access for vehicles, including emergency and service vehicles.

PSPC will build a new bridge north of the existing one. The current bridge will stay open during construction.

Specialists will carry out environmental protection and archaeological work during the project.

After reviewing several options, PSPC selected a modern concrete bridge because it:

Photo gallery

Select the image to view a larger version.

Steel bridge crossing a partially frozen river in a snowy landscape

The existing Portage Channel Bridge in winter conditions. A steel-truss bridge crosses a partly frozen river, surrounded by snow covered rocks and tall evergreen trees.
(Select the image to enlarge)

Metal bridge crossing a river beside rocky terrain and dense evergreen forest

The Portage Channel Bridge crosses a calm river beside rocky terrain and dense evergreen forest under a bright sky.
(Select the image to enlarge)

A water-monitoring station beside the Portage Channel Bridge. The metal bridge crosses a river beside rocky terrain and dense green forest

A water-monitoring station beside the Portage Channel Bridge. The metal bridge crosses a river beside rocky terrain and dense green forest.
(Select the image to enlarge)

A steel-truss bridge beside rocky shore and dense green forest

A view of the west abutment of the existing Portage Channel Bridge. The bridge is beside rocky banks and dense green forest.
(Select the image to enlarge)

Key milestones

Benefits to Canadians

The project will:

Project background

The Portage Channel was created in 1949 during construction of the Portage Dam. The channel separated part of the Dokis First Nation’s reserve land. As a result, the bridge is the only road access to the eastern area of the territory.

The current bridge does not meet modern standards for:

Sharp turns at both ends also make it difficult for larger vehicles to cross.

The bridge is the only road connection to a large portion of the Dokis First Nation lands. Its condition affects: