Financial information summary: The Long Term Vision and Plan for the Parliamentary Precinct—Annual Report 2021 to 2022

Document navigation for "The Long Term Vision and Plan for the Parliamentary Precinct: Annual Report 2021 to 2022"

On this page

Summary of expenditures and delivery timeline

Table 8: Project/program/expenditures and delivery timeline (in millions of dollars)
  Project approval Expenditure authority Planned expenditures 2021 to 2022table 8 note 1 Previous years expenditures Expenditures 2021 to 2022 Cumulative expenditures up to 2021 to 2022 Planned expenditures 2022 to 2023table 8 note 2 Planned expenditures 2023 to 2024 and future yearstable 8 note 2
Total Major Capital Program 9.9B – 10.4B 7,483.4 314.1 3,349.6 290.7 3,640.3 268.8 5,179.5
Total Recapitalization Program 380.7 375.9 40.0 308.7 37.9 346.6 17.2 5.5
Total Building Components and Connectivity Program 286.9 285.6 19.9 220.0 20.3 240.3 21.2 23.2
Total Security Infrastructure Program 157.6 157.6 0.2 156.7 0.3 157.0 0.4 0.0
Total Planning Program 185.5 185.5 15.0 143.8 19.7 163.5 22.0 0.0
Grand Total Long Term Vision and Plan (LTVP) 10.9B – 11.4B 8,488.0 389.2 4,178.8 368.9 4,547.7 329.8 5,208.3

Table 8 Notes

Table 8 Note 1

Period 8 forecasts in alignment with annual performance measurement by the Treasury Board in the management accountability framework.

Return to table 8 note 1 referrer

Table 8 Note 2

Forecast do not exceed project approval values.

Return to table 8 note 2 referrer

Remarks

Number may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments.

Major Capital Program

Table 9: Major Capital Program project spending for the fiscal year 2021 to 2022 (in millions of dollars)
  Project approval Expenditure authority Planned expenditures 2021 to 2022table 9 note 2 Previous years expenditures Expenditures 2021 to 2022 Cumulative expenditures up to 2021 to 2022 Planned expenditures 2022 to 2023table 9 note 3 Planned expenditures 2023 to 2024 and future yearstable 9 note 3 Substantial completion dates
Centre Block Major Rehabilitationtable 9 note 4 4.5B – 5B 3,790.2 129.6 186.4 111.5 297.8 126.4 2,300.7 2030 / 2031
Parliament Welcome Centretable 9 note 4 41.2 52.8 47.8 100.6 61.6 903.1 2030 / 2031
Enablings/Early Workstable 9 note 5 table 9 note 7 569.6 569.6 64.5 385.5 55.5 441.0 42.0 86.6 2024
100 Sparks / 30 Metcalfe Redevelopment 308.0 56.1 20.6 0.0 21.0 21.0 4.0 280.3 2029
Block 2 Redevelopment 1,372.5 52.3 9.2 4.5 5.9 10.5 10.0 1,333.9 TBD
Library of Parliament (LoP) – Virtual Reality Tour 7.5 7.5 0.5 6.6 0.5 7.1 0.2 0.0 2021
Interim Operation Command Center 7.6 7.6 2.8 4.4 2.8 7.1 0.3 0.0 2023
Trompe l'œil Scaffold Coverings 4.5 4.5 0.0 0.0 0.4 0.4 1.8 2.3 2028
40 Elgin Senate Fit-up 112.9 15.5 0.9 0.0 0.5 0.5 5.7 106.7 2027
West Block rehabilitationtable 9 note 6 862.9 862.9 1.0 852.7 1.0 853.7 1.5 0.8 2018
Senate Interim Accommodations (Government Conference Centre)table 9 note 6 219.8 219.8 2.1 213.7 2.1 215.8 0.5 0.0 2018
Wellington Building renovationtable 9 note 6 425.2 425.2 0.0 421.7 0.0 421.7 0.0 0.0 2016
Leased and Lease Fit-uptable 9 note 1 773.8 773.8 34.0 568.1 33.8 602.0 9.6 143.7 n/a
Other Major Capital Program (MCP) (Active) 70.3 70.3 7.7 25.2 8.0 33.2 5.3 21.5 n/a
Completed MCP 628.0 628.0 0.0 628.0 0.0 628.0 0.0 0.0 n/a
Total Major Capital Program 9.9B – 10.4B 7,483.4 314.1 3,349.6 290.7 3,640.3 268.8 5,179.5 n/a

Table 9 Notes

Table 9 Note 1

Project approval for Leases has been adjusted to reflect escalation.

Return to table 9 note 1 referrer

Table 9 Note 2

Period 8 forecasts in alignment with annual performance measurement by the Treasury Board in the management accountability framework.

Return to table 9 note 2 referrer

Table 9 Note 3

Forecast do not exceed project approval values.

Return to table 9 note 3 referrer

Table 9 Note 4

Authorities and expenditures for the Centre Block and Parliament Welcome Centre, and enabling and early works, have been updated from previous years to reflect additional Treasury Board authorities and align with the 2021 public baseline of the Centre Block Rehabilitation Program.

Return to table 9 note 4 referrer

Table 9 Note 5

Includes early works required to establish the program as well as projects carried out that serve broader Long Term Vision and Plan objectives (e.g., Relocation of Books of Remembrance and Monuments; relocation of the National Press Hot Room and Library of Parliament Refit at 125 Sparks St; and the construction of the Parliament Hill Temporary Loading Dock).

Return to table 9 note 5 referrer

Table 9 Note 6

Project completed. Forecasted expenditures associated with project close-out activities.

Return to table 9 note 6 referrer

Table 9 Note 7

Most project elements targeted for completion in 2022 to 2023. Remaining Expenditure Authority to be relocated within the program.

Return to table 9 note 7 referrer

Remarks

Number may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments.

Recapitalization Program

Table 10: Recapitalization Program project spending for the fiscal year 2021 to 2022 (in millions of dollars)
  Project approval Expenditure authority Planned expenditures 2021 to 2022table 10 note 1 Previous years expenditures Expenditures 2021 to 2022 Cumulative expenditures up to 2021 to 2022 Planned expenditures 2022 to 2023table 10 note 2 Planned expenditures 2023 to 2024 and future yearstable 10 note 2 Substantial completion dates
East Block 1867 Wing exterior rehabilitation 97.5 97.5 21.6 66.9 22.0 89.0 5.0 0.0 2022
Lighting Implementation – West Block 9.2 9.2 3.3 0.9 2.2 3.0 5.8 0.0 2023
North Slope Vegetation Management 15.3 15.3 12.5 1.2 11.1 12.4 2.7 0.0 2023
Queen’s Gate Accessibility 6.1 1.2 0.5 0.1 0.5 0.6 1.0 4.5 2024
Postal Station B Heritage Upgrades 3.6 3.6 1.3 0.0 1.3 1.3 1.4 0.0 2023
Other Recapitalization (Active) 18.9 18.9 0.9 9.3 0.8 10.1 1.3 1.0 n/a
Completed Recapitalization 230.2 230.2 0.0 230.2 0.0 230.2 0.0 0.0 n/a
Total Recapitalization Program 380.7 375.9 40.0 308.7 37.9 346.6 17.2 5.5 n/a

Table 10 Notes

Table 10 Note 1

Period 8 forecasts in alignment with annual performance measurement by the Treasury Board in the management accountability framework.

Return to table 10 note 1 referrer

Table 10 Note 2

Forecast do not exceed project approval values.

Return to table 10 note 2 referrer

Remarks

Number may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments.

Building Components and Connectivity Program

Table 11: Building Components and Connectivity Program project spending for the fiscal year 2021 to 2022 (in millions of dollars)
  Project approval Expenditure authority Planned expenditures 2021 to 2022table 11 note 1 Previous years expenditures Expenditures 2021 to 2022 Cumulative expenditures up to 2021 to 2022 Planned expenditures 2022 to 2023table 11 note 2 Planned expenditures 2023 to 2024 and future yearstable 11 note 2 Substantial completion dates
Next generation network infrastructure – telephony 19.9 19.9 0.0 13.4 0.0 13.4 0.0 6.5 2025
Modernization of the Parliament Community access television (CATV) 14.0 14.0 1.5 9.0 1.8 10.9 1.1 2.0 2024
Information technology (IT) infrastructure base building upgrades 15.2 15.2 2.1 7.8 2.4 10.1 2.0 2.2 2022
Datacentre disaster recovery projects 37.0 37.0 4.8 17.3 5.3 22.6 7.4 7.0 2025
Video Surveillance and Security System 7.7 7.7 0.9 0.0 1.4 1.4 3.3 2.8 2025
Simultaneous Interpreting Equipment 2.6 1.3 0.1 1.0 0.2 1.2 0.1 0.5 2024
Other Building Components and Connectivity (Active) 29.1 29.1 10.4 10.2 9.2 19.5 7.3 2.3 n/a
Completed Building Components and Connectivity 161.6 161.6 0.0 161.3 0.0 161.3 0.0 0.0 n/a
Total Building Components and Connectivity Program 286.9 285.6 19.9 220.0 20.3 240.3 21.2 23.2 n/a

Table 11 Notes

Table 11 Note 1

Period 8 forecasts in alignment with annual performance measurement by the Treasury Board in the management accountability framework.

Return to table 11 note 1 referrer

Table 11 Note 2

Forecast do not exceed project approval values.

Return to table 11 note 2 referrer

Remarks

Number may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments.

Security Infrastructure Program

Table 12: Security Infrastructure Program project spending for the fiscal year 2021 to 2022 (in millions of dollars)
  Project approval Expenditure authority Planned expenditures 2021 to 2022table 12 note 1 Previous years expenditures Expenditures 2021 to 2022 Cumulative expenditures up to 2021 to 2022 Planned expenditures 2022 to 2023table 12 note 2 Planned expenditures 2023 to 2024 and future yearstable 12 note 2 Substantial completion dates
Other Security (Active) 0.9 0.9 0.2 0.0 0.3 0.3 0.4 0.0 n/a
Completed Security 156.7 156.7 0.0 156.7 0.0 156.7 0.0 0.0 n/a
Total Security Infrastructure Program 157.6 157.6 0.2 156.7 0.3 157.0 0.4 0.0 n/a

Table 12 Notes

Table 12 Note 1

Period 8 forecasts in alignment with annual performance measurement by the Treasury Board in the management accountability framework.

Return to table 12 note 1 referrer

Table 12 Note 2

Forecast do not exceed project approval values.

Return to table 12 note 2 referrer

Remarks

Number may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments.

Planning Program

Table 13: Planning Program project spending for the fiscal year 2021 to 2022 (in millions of dollars)
  Project approval Expenditure authority Planned expenditures 2021 to 2022table 13 note 1 Previous years expenditures Expenditures 2021 to 2022 Cumulative expenditures up to 2021 to 2022 Planned expenditures 2022 to 2023table 13 note 2 Planned expenditures 2023 to 2024 and future yearstable 13 note 2 Substantial completion dates
Campus planning 9.9 9.9 2.0 6.6 1.1 7.8 2.1 0.0 n/a
Planning program support 73.4 73.4 12.2 37.0 17.6 54.7 18.7 0.0 n/a
Other Planning (Active) 2.2 2.2 0.9 0.0 0.9 0.9 1.2 0.0 n/a
Completed Planning 100.1 100.1 0.0 100.0 0.0 100.1 0.0 0.0 n/a
Total Planning Program 185.5 185.5 15.0 143.8 19.7 163.5 22.0 0.0 n/a

Table 13 Notes

Table 13 Note 1

Period 8 forecasts in alignment with annual performance measurement by the Treasury Board in the management accountability framework.

Return to table 13 note 1 referrer

Table 13 Note 2

Forecast do not exceed project approval values.

Return to table 13 note 2 referrer

Remarks

Number may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments.

Total Long Term Vision and Plan

Table 14: Long Term Vision and Plan cost for 2021 to 2022 (in millions of dollars)
  Project approval Expenditure authority Planned expenditures 2021 to 2022table 14 note 1 Previous years expenditures Expenditures 2021 to 2022 Cumulative expenditures up to 2021 to 2022 Planned expenditures 2022 to 2023table 14 note 2 Planned expenditures 2023 to 2024 and future yearstable 14 note 2 Substantial completion dates
Grand Total LTVP 10.9B – 11.4B 8,488.0 389.2 4,178.8 368.9 4,547.7 329.8 5,208.3 n/a

Table 14 Notes

Table 14 Note 1

Period 8 forecasts in alignment with annual performance measurement by the Treasury Board in the management accountability framework.

Return to table 14 note 1 referrer

Table 14 Note 2

Forecast do not exceed project approval values.

Return to table 14 note 2 referrer

Remarks

Number may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments.

Lease cost

Table 15: Long Term Vision and Plan lease cost breakdown (in millions of dollars)table 15 note 1
LTVP Leases Total lease cost forecasted Previous years expenditures Forecasted expenditures in 2021 to 2022 Actual expenditures in 2021 to 2022 Total expenditures to end of 2021 to 2022
119 Queen Street 3.6 3.6 0.0 0.0 3.6
131 Queen Street 286.7 193.7 12.8 12.8 206.5
181 Queen Street 127.8 110.6 6.3 6.4 116.9
155 Queen Street (10th Floor) 19.4 7.2 1.2 1.2 8.4
155 Queen Street (6th Floor) 0.2 0.2 0.0 0.0 0.2
2074-2086 Walkley Road, Trade Shops 17.6 5.9 0.4 0.4 6.3
768 Belfast Road, House of Commons 1.4 1.4 0.0 0.0 1.4
2455 Don Reid Drive, E-Printing 10.3 8.7 0.5 0.5 9.3
1 Wellington Street - Rideau Committee Rooms 22.8 8.7 0.4 0.4 9.0
C.D. Howe Building 26.2 24.5 1.7 1.7 26.2
Clarica / Sun Life Building 80.6 50.5 3.5 3.5 54.0
Interim Room 200—Government of Canada Conference Centre 8.5 8.5 0.0 0.0 8.5
Parks Canada 0.4 0.5 0.1 0.1 0.6
40 Elgin St. Chambers building 22.0 3.2 0.8 0.8 4.1
150 Slater Street 17.9 5.1 1.4 1.4 6.4
40 Elgin St., Floors 8 & 12 108.7 0.0 2.5 2.5 2.5
40 Elgin St., Floors 9, 10 & 11 25.2 3.0 1.6 1.6 4.6
Grand Total LTVP 779.4 435.2 33.2 33.3 468.6

Table 15 Note

Table 15 Note 1

Total lease cost forecasted includes the rent and escalation amounts for the duration of the lease.

Return to table 15 note 1 referrer

Document navigation for "The Long Term Vision and Plan for the Parliamentary Precinct: Annual Report 2021 to 2022"

Page details

Date modified: