7. Appendix B: ECCC project management lifecycle

Long description

ECCC Project Management Framework (PMF)

Gate 0: Intake

Phase Purpose

  • Identifies the business problem to be solved or the opportunity
  • Defines project high level outcomes
  • Engages stakeholders

Process and Deliverables

  • Project Intake Document (All Tiers)
  • Benefits Realization Plan (T2-T3)

Project Cost

  • Cost for this stage: Not tracked
  • Project estimate plus or minus 100%

Governance

  • Tier 1: Director Level Committees
  • Tier 2: DG Level Committees
  • Tier 3: DG Level Committees to Executive Management Committee to TBS

Gate 1: Initiation

Phase Purpose

  • To officially initiate the project, define roles and responsibilities and allocate resources (via the Project Charter)

Process and Deliverables

  • Project Brief (T1)
  • Business Case (T2 and T3)
  • PCRA (T2 and T3)
  • TBS Project Brief (T3)
  • TBS Sub Approval (T3)
  • Business requirements (All)
  • Project Charter (All)
  • Benefits Realization Plan (updating) (T2 and T3)

Project Cost

  • Cost for this stage: Not tracked
  • Project estimate plus or minus 50%

Governance

  • Tier 1
    • Project Sponsor = Director
    • Project Steering Committee to Director Level Committees
  • Tier 2
    • Project Sponsor = DG
    • Project Steering Committee to DG Level Committees (for example, IMSC, RP DG)
  • Tier 3
    • Project Sponsor = DG or ADM for PCRA 3 and EX04 or EX05 for PCRA 4
    • Project Steering Committee to DG Level Committees (for example, IMSC, RP DG) to Executive Management Committee to TBS

Gate 2: Planning

Phase Purpose

  • To plan the project scope, time and cost (via the Project Management Plan) and to obtain buy-in from the targeted user community

Process and Deliverables

  • Project Management Plan – Lite version (T1)
  • Project Management Plan (T2 and T3)
    • Scope Management
    • Work Breakdown Structure
    • Cost Management
    • Quality Management and Change Order Management
    • Human Resource Plan
    • Procurement Management
    • Risk Management
    • Communication Management
  • Schedule (All)
  • Dashboard and Project Executive Summary (T2 and T3)
  • Benefits Realization Plan (monitoring) (T2 and T3)
  • Meeting Minutes or Records of Decision (All)

Project Cost

  • Cost for this stage: Actuals
  • Project estimate plus or minus 10%

Governance

  • Tier 1
    • Project Sponsor = Director
    • Project Steering Committee to Director Level Committees
  • Tier 2
    • Project Sponsor = DG
    • Project Steering Committee to DG Level Committees (for example, IMSC, RP DG)
  • Tier 3
    • Project Sponsor = DG or ADM for PCRA 3 and EX04 or EX05 for PCRA 4
    • Project Steering Committee to DG Level Committees (for example, IMSC, RP DG) to Executive Management Committee to TBS

Gate 3: Execution

Phase Purpose

  • To execute the project management plan while monitoring and controlling scope, time and cost

Process and Deliverables

  • PCRA (updating) (T2 and T3)
  • Change Requests (All)
  • Change Order Log (All)
  • Issue Log (All)
  • Risk Log (All)
  • Schedule (All)
  • Dashboard and Project Executive Summary (T2 and T3)
  • Benefits Realization Plan (monitoring) (T2 and T3)
  • Meeting Minutes or Records of Decision (All)
  • Handover Document (all)
  • TBS Project Performance Data (T2 and T3)

Project Cost

  • Cost for this stage: Actuals

Governance

  • Tier 1
    • Project Sponsor = Director
    • Project Steering Committee to Director Level Committees
  • Tier 2
    • Project Sponsor = DG
    • Project Steering Committee to DG Level Committees (for example, IMSC, RP DG)
  • Tier 3
    • Project Sponsor = DG or ADM for PCRA 3 and EX04 or EX05 for PCRA 4
    • Project Steering Committee to DG Level Committees (for example, IMSC, RP DG) to Executive Management Committee to TBS

Gate 4: Close-Out

Phase Purpose

  • Provide an assessment of the project performance against its objectives and requirements and capture Lessons Learned

Process and Deliverables

  • Close-Out Report  - Lite version (T1)
  • Close-Out Report (T2 and T3)
    • Completion of all contract administration activities
    • Final evaluation of project teams including consultants and contractors
    • Outstanding issues
    • Lessons learned
    • Stored project documents
  • Dashboard and Project Executive Summary (T2 and T3)
  • Benefits Realization Plan (assessment) T2 and T3)
  • TBS Project Performance Data (T2 and T3)

Project Cost

  • Cost for this stage: Actuals

Governance

  • Tier 1
    • Project Sponsor = Director
    • Project Steering Committee to Director Level Committees
  • Tier 2
    • Project Sponsor = DG
    • Project Steering Committee to DG Level Committees (for example, IMSC, RP DG)
  • Tier 3
    • Project Sponsor = DG or ADM for PCRA 3 and EX04 or EX05 for PCRA 4
    • Project Steering Committee to DG Level Committees (for example, IMSC, RP DG) to Executive Management Committee to TBS

Gate 5: Post Implementation

Phase Purpose

  • Measures the project success
  • Runs the operations

Process and Deliverables

  • Benefits Realization Results Report (BRRR) and Presentation (T2 and T3)

Project Cost

  • Operating Budget

Governance

  • Tier 1: Director Level Committees
  • Tier 2: DG Level Committees
  • Tier 3: DG Level Committees to Executive Management Committee to TBS

Notes

  • For enquiries, please contact the DPMO team at EC.BureauGestionDeProjets-ProjectManagementOffice.EC@canada.ca
  • Tier 1 = project under $1 million; Tier 2 = project over $1 million, PCRA = 1 or 2; Tier 3 = project over $1 million, PCRA = 3 or 4
  • The PMF aligns with ECCC’s OPMCA scoring of 2 and TBS Policy on the Management of Projects
  • A PMF compliance monitoring will be completed annually
  • Governance is for sharing project information with Senior Management and Stakeholders for the input, feedback and decisions prior to crossing a Gate

Source: ECCC Project Management Framework 1.0, approved by the ECCC Executive Management Committee in May 2017

Long description

ECCC Project Management Framework (PMF) 2.0

(Pre-Project) – Gate 0: Intake

Phase Purpose

  • To identify the opportunity
  • To define project high level outcomes

Process and Deliverables

  • Tier 0: less than $1 million – Lite templates apply
    • Opportunity Proposal Document
    • Business Case
  • Tier 1: $1 million to $5 million – Lite templates apply
    • Same as Tier 0 plus, for IT projects only, Concept case
  • Tier 2: more than $5 million, PCRA = 1 or 2
    • Same as Tier 1
  • Tier 3: more than $5 million, PCRA = 3 or 4
    • Same as Tier 1

Project Cost

  • Cost for this stage: Not tracked
  • Project estimate plus or minus 100%

Governance

  • Tier 1: Director Level Committees
  • Tier 2: DG Level Committees
  • Tier 3: DG Level Committees to Executive Management Committee to TBS

Gate 1: Initiation

Phase Purpose

  • To define roles and responsibilities and allocate resources (via the Project Charter)

Process and Deliverables

  • Tier 0
    • Project Performance Record
    • Official Project Launch email (from Sponsor)
  • Tier 1: Same as Tier 0 plus
    • Benefits Realization Plan
    • Project Charter

When applicable:

  • Business Analysis and Requirements Document (BARD)
    • IT Security Documentation
    • Enterprise Architecture (EA) Assessment
    • Preliminary Privacy Impact Assessment (PIA)
  • Tier 2: Same as Tier 1 plus
    • PCRA
  • Tier 3: Same as Tier 2 plus
    • TB Project Brief

Project Cost

  • Cost for this stage: Not tracked
  • Project estimate plus or minus 50% at Gate 1

Governance

  • Tier 1
    • Project Sponsor = Director
    • Project Steering Committee to Director Level Committees
  • Tier 2
    • Project Sponsor = DG
    • Project Steering Committee to DG Level Committees (for example, IMSC)
  • Tier 3
    • Project Sponsor = DG or ADM for PCRA 3 and EX04 or EX05 for PCRA 4
    • Project Steering Committee to DG Level Committees (for example, IMSC) to Executive Management Committee to TBS

Gate 2: Planning

Phase Purpose

  • To plan and officially baseline the project scope, time and cost (via the Project Management Plan) and to obtain buy-in from the targeted user community

Process and Deliverables

  • Tier 0
    • Project Performance Record -- update
  • Tier 1: Same as Tier 0 plus
    • Benefits Realization Plan – update
    • Project Management Plan
    • Schedule
    • Meeting Minutes or RoD
    • Lessons Learned from Initiation

When applicable:

  • BARD – update
    • IT Security Documentation
  • Tier 2: Same as Tier 1 plus
    • Dashboard and Project Executive Summary
  • Tier 3: Same as Tier 2 plus
    • TB Sub Approval
    • Project Sponsor Letter

Project Cost

  • Cost for this stage: Actuals
  • Project estimate plus or minus 20% at Gate 2

Governance

  • Tier 1
    • Project Sponsor = Director
    • Project Steering Committee to Director Level Committees
  • Tier 2
    • Project Sponsor = DG
    • Project Steering Committee to DG Level Committees (for example, IMSC)
  • Tier 3
    • Project Sponsor = DG or ADM for PCRA 3 and EX04 or EX05 for PCRA 4
    • Project Steering Committee to DG Level Committees (for example, IMSC) to Executive Management Committee to TBS

Gate 3: Execution

Phase Purpose

  • To execute the project management plan while monitoring and controlling scope, time and cost against baselines

Process and Deliverables

  • Tier 0
    • Project Performance Record – update
  • Tier 1: Same as Tier 0 plus
    • Benefits Realization Plan (monitoring)
    • Transition Plan
    • Schedule
    • Meeting Minutes or RoD
    • Lessons Learned from Planning
    • Change Requests Log
    • Issue Log
    • Risk Log

When applicable:

  • BARD – update
    • IT Security Documentation
  • Tier 2: Same as Tier 1 plus
    • Dashboard and project Executive Summary
    • PCRA – update
  • Tier 3: Same as Tier 2 plus

Project Cost

  • Cost for this stage: Actuals

Governance

  • Tier 1
    • Project Sponsor = Director
    • Project Steering Committee to Director Level Committees
  • Tier 2
    • Project Sponsor = DG
    • Project Steering Committee to DG Level Committees (for example, IMSC)
  • Tier 3
    • Project Sponsor = DG or ADM for PCRA 3 and EX04 or EX05 for PCRA 4
    • Project Steering Committee to DG Level Committees (for example, IMSC) to Executive Management Committee to TBS

Gate 4: Close-Out

Phase Purpose

  • To provide an assessment of the project performance against its objectives, requirements and its baselines, and capture Lessons Learned

Process and Deliverables

  • Tier 0
    • Project Performance Record – update
    • Official Project Close-Out email (from Sponsor)
  • Tier 1: Same as Tier 0 plus
    • Benefits Realization Plan (assessment)
    • Close-Out Report and Lessons Learned
  • Tier 2: Same as Tier 1 plus
    • Dashboard and Project Executive Summary
  • Tier 3: Same as Tier 2

Project Cost

  • Cost for this stage: Actuals

Governance

  • Tier 1
    • Project Sponsor = Director
    • Project Steering Committee to Director Level Committees
  • Tier 2
    • Project Sponsor = DG
    • Project Steering Committee to DG Level Committees (for example, IMSC)
  • Tier 3
    • Project Sponsor = DG or ADM for PCRA 3 and EX04 or EX05 for PCRA 4
    • Project Steering Committee to DG Level Committees (for example, IMSC) to Executive Management Committee to TBS

(Post-Project) – Gate 5: Post Implementation

Phase Purpose

  • To measure the project success
  • To run the operations

Process and Deliverables

  • Tier 0
    • Project Performance Record – update
  • Tier 1: Same as Tier 0 plus
    • Benefits Realization Results Report (BRRR) and Presentation
  • Tier 2: Same as Tier 1 plus

For IT projects only

  • S-ATO Maintenance Log (SML)
  • Tier 3: Same as Tier 2

Project Cost

  • Operating Budget

Governance

  • Tier 1
    • Director Level Committees
  • Tier 2
    • DG Level Committees
  • Tier 3
    • DG Level Committees to ADM Corporate Operations Committee to Executive Management Committee to TBS

Notes

  • The PMF aligns with ECCC’s OPMCA scoring of 2 and TBS Policy on the Planning and Management of Investments and the Direction on the Management of Projects and Programmes
  • Project Performance Record is created and updated as required during the Lifecycle.
  • Governance is for sharing project information with Senior Management and Stakeholders for the input, feedback and decisions prior to crossing a Gate.
  • Projects in Tier 1 to 3 present to the Project management Advisory Committee (PMAV) at each gate for endorsement to proceed.
  • For enquiries, please contact the DPMO team at EC.BureauGestionDeProjets-ProjectManagementOffice.EC@canada.ca
  • For IT Security documents, contact It Security.
  • For PIA, contact Access to Information and Privacy (ATIP) Group.
  • For BARD documents, contact the Business Analysts Group.
  • For EA documents, contact Enterprise Architecture Group.
  • For Project Intake, contact the Portfolio Management Group.

Source: ECCC Project Management Framework 2.0, approved by the ECCC Executive Management Committee in October 2019