Audit of the Governance Framework over Information Management
Appendix D: Audit Time Line
Activity | Time |
---|---|
Audit planning | July - September 2010 |
On-site examination | October - November 2010 |
Clearance draft to management | April 6, 2011 |
Management action plan finalized | July 19, 2011 |
Recommended for approval by Audit Committee | August 4, 2011 |
Report approved by the Deputy Minister | August 4, 2011 |