Program financial performance: The Long Term Vision and Plan—Annual Report 2018 to 2019
On this page
Fiscal year financial highlights
In 2018 to 2019, significant progress was made on advancing the Long Term Vision and Plan (LTVP) and planning for future projects. The LTVP’s total expenditures were $451.7 million, as seen in in table 1.
Planned expenditures | 464.8 |
---|---|
Actual expenditures | 451.7 |
Percentage spent | 97.2 |
Expenditures for each of the 5 program components are shown in table 2. This breakdown of program expenditures is slightly different from fiscal year 2017 to 2018, due to evolving priorities. The program continues to be within 3% of planning and forecasting expectations.
Program | Expenditures – fiscal year 2018 to 2019 |
Budget – fiscal year 2018 to 2019 |
---|---|---|
Major Capital Program | 339.7 | 349.0 |
Recapitalization Program | 14.8 | 15.7 |
Building Components and Connectivity Program | 31.2 | 32.4 |
Security Infrastructure Program | 52.8 | 52.8 |
Planning Program | 13.2 | 14.9 |
Total | 451.7 | 464.8 |
In fiscal year 2018 to 2019, the Major Capital Program (MCP) represented (75%) of all LTVP expenditures, followed by the Security Infrastructure Program (12%), the Building Components and Connectivity Program (BCC) (7%), the Recapitalization Program (RECAP) (3%), and the Planning Program (3%).
Program | Expenditures | Percentage |
---|---|---|
Major Capital Program | 349.0 | 75.1 |
Recapitalization Program | 15.7 | 3.4 |
Building Components and Connectivity Program | 32.4 | 7.0 |
Security Infrastructure Program | 52.8 | 11.4 |
Planning Program | 14.9 | 3.2 |
Total | 464.8 | 100.0 |
Note
All forecasts are for currently approved projects and are subject to change.
Major Capital Program
The Major Capital Program (MCP) focuses on the rehabilitation of major buildings in the Parliamentary Precinct, including the Centre Block, the East Block, the West Block, and the Senate of Canada Building. In addition, this program also manages new construction projects, such as the Visitor Welcome Centre Complex.
Financial performance
In fiscal year 2018 to 2019:
- MCP expenditures were $339.7 million, a slight increase over expenditures in the previous fiscal year
- this increase is a result of construction work completed this past fiscal year, and the commencement of the Centre Block Rehabilitation Project, including the Enabling Projects (Table 4)
- All MCP projects were on time, on scope, and on budget
- Looking ahead, total annual expenditures within the MCP are expected to decrease over the next fiscal year as major projects are completed ahead of the implementation of the next rolling program of work
- Following the next fiscal year, total annual expenditures within MCP are expected to increase as the construction activity on the Centre Block rehabilitation increases
Year | Annual budget | Annual expenditures | Annual expenditure forecast |
---|---|---|---|
Prior years | 46.0 | 44.1 | N/A |
2002 to 2003 | 29.1 | 26.5 | N/A |
2003 to 2004 | 23.4 | 38.8 | N/A |
2004 to 2005 | 40.6 | 44.4 | N/A |
2005 to 2006 | 64.5 | 44.2 | N/A |
2006 to 2007 | 65.4 | 67.5 | N/A |
2007 to 2008 | 58.9 | 58.2 | N/A |
2008 to 2009 | 62.1 | 66.3 | N/A |
2009 to 2010 | 121.3 | 120.7 | N/A |
2010 to 2011 | 109.6 | 112.9 | N/A |
2011 to 2012 | 126.2 | 125.5 | N/A |
2012 to 2013 | 202.8 | 180.4 | N/A |
2013 to 2014 | 246.6 | 246.8 | N/A |
2014 to 2015 | 301.4 | 306.9 | N/A |
2015 to 2016 | 346.6 | 328.0 | N/A |
2016 to 2017 | 289.7 | 293.1 | N/A |
2017 to 2018 | 342.8 | 329.9 | N/A |
2018 to 2019 | 349.0 | 339.7 | N/A |
2019 to 2020 | N/A | N/A | 324.0 |
2020 to 2021 | N/A | N/A | 260.7 |
Note
All forecasts are for currently approved projects and are subject to change.
Recapitalization Program
The Recapitalization Program (RECAP) addresses projects in buildings that are occupied and operational but have not yet been fully rehabilitated. The projects are designed to preserve buildings, stop or reduce ongoing deterioration, respond to urgent building repair requirements, address health and safety issues, and reduce cost and complexity of future work. RECAP is also responsible for the restoration and rehabilitation of the heritage Parliament Hill grounds.
In most cases, recapitalization projects are identified ahead of time and integrated into the LTVP’s sequencing of work, to serve as permanent necessary interventions that will ensure the ongoing viability of the buildings, and will advance the implementation of longer term projects.
Financial performance
In fiscal year 2018 to 2019:
- RECAP expenditures were $14.8 million, a large decrease over expenditures from the previous fiscal year, due to various RECAP projects that had been completed in the previous fiscal year, as shown in Table 5
- All RECAP projects were on time, on scope, and on budget
- Looking ahead, $12.5 million is projected to be spent in the next fiscal year, on projects such as the East Block 1867 Wing project
Year | Annual budget | Annual expenditures | Annual expenditure forecast |
---|---|---|---|
Prior years | 11.0 | 11.0 | N/A |
2002 to 2003 | 14.4 | 14.4 | N/A |
2003 to 2004 | 25.6 | 25.6 | N/A |
2004 to 2005 | 6.8 | 6.8 | N/A |
2005 to 2006 | 3.7 | 3.7 | N/A |
2006 to 2007 | 3.2 | 3.2 | N/A |
2007 to 2008 | 5.4 | 5.4 | N/A |
2008 to 2009 | 3.5 | 3.5 | N/A |
2009 to 2010 | 2.4 | 2.4 | N/A |
2010 to 2011 | 7.5 | 7.3 | N/A |
2011 to 2012 | 14.5 | 13.5 | N/A |
2012 to 2013 | 15.4 | 15.9 | N/A |
2013 to 2014 | 15.2 | 15.9 | N/A |
2014 to 2015 | 22.9 | 18.8 | N/A |
2015 to 2016 | 23.8 | 23.6 | N/A |
2016 to 2017 | 31.1 | 21.5 | N/A |
2017 to 2018 | 24.7 | 23.4 | N/A |
2018 to 2019 | 15.7 | 14.8 | N/A |
2019 to 2020 | N/A | N/A | 12.5 |
2020 to 2021 | N/A | N/A | 37.3 |
2018 to 2019 progress
In fiscal year 2018 to 2019, RECAP completed the following projects:
- West Sector Rehabilitation Grounds: Completed a feasibility study to assess the current condition of the West Sector landscape elements and infrastructure to inform future safety requirements
- South Drive Accessibility Improvement: Completed a feasibility study to explore options for improving accessibility to the Parliamentary Precinct from Wellington Street to South Drive
RECAP also advanced work on the following projects:
- Confederation Building—Mechanical and Electrical Upgrade: Completed the final stages of the mechanical and electrical required upgrades, including the introduction of a chilled water heat exchanger and the replacement of the steam valve components and of deficient electrical receptacles
- Victoria Building Recapitalization: Continued a feasibility study to identify options for an optimum phasing of recapitalization projects to improve the overall condition of the building
- North Slope Vegetation Management: Restored the northern slope escarpment to its natural state by re-establishing links with the Ottawa River; reinforcing the contrast between the cultured landscape on the plateau and wild landscape on the slope; and reinforcing the continuity of the parliamentary and judicial promontories
- West Block Exterior Lighting: Enhanced the High Victorian Gothic style of the West Block for darkness hours as per the concepts laid out in the 2015 Parliamentary Precinct Exterior Lighting Master Plan
Up next
In 2019 to 2020, RECAP will work to complete the Confederation Building Mechanical and Electrical Upgrade project, as well as advance the following projects:
- Grounds—Wellington Wall and Wrought Iron Gates (to be completed in 2022)
- Grounds—West Sector Rehabilitation (completion date to be determined)
- Victoria Building Recapitalization (completion date to be determined)
- South Drive Accessibility Improvement (completion date to be determined)
- North Slope Vegetation Management (to be completed in 2023)
Building Components and Connectivity Program
The Building Components and Connectivity Program (BCC) entails the modernization of the precinct’s campus-wide communication and information technology (IT) infrastructure for more than 30 buildings within the precinct, to meet the Parliamentarian’s modern business needs. BCC IT projects are coordinated and integrated with LTVP projects as they roll out to ensure efficient and cost-effective delivery of building connectivity elements.
Financial performance
In fiscal year 2018 to 2019:
- BCC expenditures were $31.2 million, a large increase over expenditures from the previous fiscal year, due to the Campus Connectivity Upgrades Project, IT Infrastructure and Base Building Upgrade, and Datacentre Risk Mitigation projects, as shown in Table 6
- All BCC projects were on time, on scope, and on budget
- Looking ahead $15 million is projected to be spent in the next fiscal year, which will include ongoing projects such as the IT infrastructure base building upgrades and the modernization of the Parliament Community Access Television (CATV)
Year | Annual budget | Annual expenditures | Annual expenditure forecast |
---|---|---|---|
Prior years | 6.3 | 6.3 | N/A |
2002 to 2003 | 5.2 | 5.2 | N/A |
2003 to 2004 | 7.5 | 7.5 | N/A |
2004 to 2005 | 7.0 | 7.0 | N/A |
2005 to 2006 | 7.9 | 7.9 | N/A |
2006 to 2007 | 12.0 | 12.0 | N/A |
2007 to 2008 | 3.5 | 3.5 | N/A |
2008 to 2009 | 2.2 | 2.2 | N/A |
2009 to 2010 | 1.0 | 1.0 | N/A |
2010 to 2011 | 5.7 | 5.5 | N/A |
2011 to 2012 | 3.4 | 3.4 | N/A |
2012 to 2013 | 5.2 | 5.0 | N/A |
2013 to 2014 | 15.3 | 14.9 | N/A |
2014 to 2015 | 21.2 | 19.4 | N/A |
2015 to 2016 | 19.5 | 23.1 | N/A |
2016 to 2017 | 17.6 | 15.7 | N/A |
2017 to 2018 | 17.6 | 14.7 | N/A |
2018 to 2019 | 32.4 | 31.2 | N/A |
2019 to 2020 | N/A | N/A | 15.0 |
2020 to 2021 | N/A | N/A | 25.1 |
2018 to 2019 progress
In 2018 to 2019, the BCC program completed the following projects:
- Integrated Security System Upgrade: Upgraded and expanded the main integrated security systems to support increasing security requirements for the Parliamentary Precinct, including card swipes, video cameras, and intruder detection alarms
- Master Control Distribution Upgrade: Modernized asset audio and video broadcast distribution network
- master control facilities were also upgraded for buildings such as the West Block, the Senate of Canada Building, and the Wellington Building to support digital and high definition formats
- Phase 1 of the South of Wellington Connectivity: Established cabling pathway connections to the newly rehabilitated Senate of Canada Building
The BCC program is also advancing work on the following projects:
- Community Access Television: Equip buildings with modern IT infrastructure and cabling (replacing co-axial cables) to accept the broadcast industry’s technological change from analog to digital content
- Next phases of the South of Wellington Connectivity: Initiate planning for future phases in order to provide pathway connections to buildings, to support connectivity requirements for the precinct in the long term, and to ensure business continuity
- Next Generation Network Infrastructure—Telephony: Modify the delivery model for Parliamentary telephony in order to eliminate the cost of operating traditional phone lines through external service providers
- Information Technology Infrastructure Base Buildings Upgrades: Align and modernize IT equipment rooms, and associated in-building pathway infrastructure to meet the current and future requirements of the LTVP program
- Datacentre Risk Mitigation: Investigate, identify, and analyze risks to the continuity of Parliamentary services within the Centre Block Underground Services (CBUS) facilities, and to devise risk mitigation strategies and option
- Committee Rooms Senate Conversion—1 Wellington: Update Senate committee rooms to convert to full broadcast capabilities and integrate into the Senate systems
Up next
In 2019 to 2020, BCC will work to complete the first and second phases of the South of Wellington Connectivity project (full project to be completed by 2020 to 2021), as well as to advance the following:
- Community Access Television (to be completed in 2021 to 2022)
- Next phases of the South of Wellington Connectivity (to be completed 2021 to 2022)
- Next Generation Network Infrastructure—Telephony (to be completed in 2020 to 2021)
- Information Technology Infrastructure Base Buildings Upgrades (to be completed in 2022 to 2023)
- Datacentre Risk Mitigation (to be completed in 2020 to 2021)
- Committee Rooms Senate Conversion—1 Wellington (to be completed in 2019 to 2020)
Planning Program
The Planning Program focuses on the development of master plans and cost estimates to guide project planning and preparatory work for future projects. It provides overall coordination between active projects to ensure they dovetail and contribute to the broader objectives of the LTVP vision and guiding principles.
Through studies, design guidelines, and strategic advice, the planning team supports the planning of new projects and coordinates active projects to ensure they support and contribute to the broader objectives of the LTVP. Once projects have been identified and the preplanning work is complete, projects are transferred to the MCP and RECAP programs for delivery.
Financial performance
In fiscal year 2018 to 2019:
- Planning Program expenditures were $13.2 million, a slight increase over expenditures from the previous fiscal year, largely due to Program Support costs (such as labour and consultants fees), as shown in Table 7
- Looking ahead $19.5 million is projected to be spent in the next fiscal year
- this increase is reflected in Program Support costs, Campus planning, and Block 2 pre-planning
Year | Annual budget | Annual expenditures | Annual expenditure forecast |
---|---|---|---|
Prior years | 5.8 | 5.8 | N/A |
2002 to 2003 | 1.6 | 1.6 | N/A |
2003 to 2004 | 2.4 | 2.4 | N/A |
2004 to 2005 | 2.0 | 2.0 | N/A |
2005 to 2006 | 2.6 | 2.6 | N/A |
2006 to 2007 | 1.1 | 1.1 | N/A |
2007 to 2008 | 0.4 | 0.4 | N/A |
2008 to 2009 | 1.5 | 1.5 | N/A |
2009 to 2010 | 1.8 | 1.8 | N/A |
2010 to 2011 | 3.7 | 3.7 | N/A |
2011 to 2012 | 4.0 | 3.9 | N/A |
2012 to 2013 | 4.4 | 3.9 | N/A |
2013 to 2014 | 5.5 | 6.1 | N/A |
2014 to 2015 | 12.4 | 10.7 | N/A |
2015 to 2016 | 18.1 | 13.1 | N/A |
2016 to 2017 | 21.1 | 21.4 | N/A |
2017 to 2018 | 9.8 | 9.8 | N/A |
2018 to 2019 | 14.9 | 13.2 | N/A |
2019 to 2020 | N/A | N/A | 19.5 |
2020 to 2021 | N/A | N/A | 6.0 |
2018 to 2019 progress
In 2018 to 2019, the Planning Program launched and completed a number of key initiatives, including:
- Sustainability actions, such as a Climate Change Vulnerability Assessment and an Environmental Sustainability Strategy and Action Plan for the Parliamentary Precinct
- A Universal Accessibility Review and Action Plan (UARAP) for the Parliamentary Precinct
- A seismic study in collaboration with the Built in Canada Innovation Program (BCIP) to assess the Parliamentary Precinct portfolio’s response to an extreme seismic event, including recovery time
- Collaboration with Natural Resources Canada and the National Research Commission to develop Sustainable Design Principles for new construction projects in the Parliamentary Precinct
- Precinct-wide guidelines for temporary construction enclosures
- Partnering with the City of Ottawa and the National Capital Commission on the Sparks Street Public Realm Study, including providing a temporary pop-up space for the public consultation at 79 Sparks Street
- A number of reports to inform decision-making on future projects and support improved conservation of heritage features
Up next
In 2019 to 2020, the Planning Program will work to advance the following:
- Advance Universal Accessibility Review and Action Plan
- Implement ESAP
- Advance planning of the redevelopment of Blocks 1, 2 and 3
Security Infrastructure Program
The Security Infrastructure Program (security, material handling, etc.) focuses on the implementation of improved and modernized security measures in the precinct.
Financial performance
In fiscal year 2018 to 2019:
- Security Infrastructure Program expenditures were $52.8 million, a large decrease over expenditures from the previous fiscal year, as shown in Table 8
- This is due to the decrease in security projects in comparison with fiscal year 2017 to 2018
- All Security Infrastructure Program projects were on time, on scope, and on budget
- Looking ahead there are no expenditures projected to be spent in the next fiscal year
Year | Total budget | Total expenditures | Total forecast | Annual budget | Annual expenditures | Annual expenditure forecast |
---|---|---|---|---|---|---|
2015 to 2016 | 0.0 | 0.0 | N/A | 0.0 | 0.0 | N/A |
2016 to 2017 | 22.5 | 12.6 | N/A | 22.5 | 12.6 | N/A |
2017 to 2018 | 113.9 | 104.0 | N/A | 91.4 | 91.4 | N/A |
2018 to 2019 | 166.7 | 156.7 | N/A | 52.8 | 52.8 | N/A |
2019 to 2020 | N/A | N/A | 156.7 | N/A | N/A | 0.0 |
2020 to 2021 | N/A | N/A | 156.7 | N/A | N/A | 0.0 |
2018 to 2019 progress
In 2018 to 2019, the Security Infrastructure Program completed the following projects:
- West Block—Security Enhancement Phase 2
- Wellington Building—Security Enhancement
- Senate of Canada Building—Security Enhancement
Page details
- Date modified: