Financial Information Summary: The Long Term Vision and Plan for the Parliamentary Precinct—Annual Report 2018 to 2019

Document navigation for "The Long Term Vision and Plan: Annual Report 2018 to 2019"

On this page

Summary of expenditures and delivery timeline

Table 9: Project/program/expenditures and delivery timeline
(in millions of dollars)
      Budget Expenditures Forecast
Programs Project approval Expenditure authority 2018 to 2019 budget Previous years expenditures 2018 to 2019 expenditures Cumulative expenditures up to 2018 to 2019 Planned expenditures 2019 to 2020table 9 note 1 Planned expenditures 2020 to 2021 and future yearstable 9 note 1
Total Major Capital Programtable 9 note 2 3,511.1 3,498.4 349.0 2,401.6 339.7 2,741.3 324.0 637.6
Total Recapitalization Program 353.6 313.2 15.7 248.7 14.8 263.5 12.5 152.6
Total Building Components and Connectivity Program 229.8 219.9 32.4 154.4 31.2 185.6 15.0 36.9
Total Security Infrastructure Program 184.5 171.7 52.8 103.9 52.8 156.7 0.0 34.5
Total Planning Program 131.9 131.9 14.9 91.8 13.2 105.0 19.5 18.4
Grand Total LTVP 4,410.9 4,335.1 464.8 3,000.4 451.7 3,452.1 370.8 879.9

Table 9 notes

Table 9 note 1

Project approval of Leases Fit-ups are in constant dollars which do not include escalation costs whereas the expenditures are in current dollars.

Return to table 9 note 1 referrer

Table 9 note 2

Forecast to not exceed the overall LTVP funding of $4,702.9M.

Return to table 9 note 2 referrer

Remarks

  • Numbers may not add due to rounding
    • planned forecast may require project approval and/or expenditure authority amendments
  • New project approval process implemented in FY 2016/17 which now excludes pre-planning costs from Project Approval

Major Capital Program

Table 10: Major Capital Program project spending fiscal year 2018 to 2019
(in millions of dollars)
      Budget Expenditures Forecast
Programs Project approval Expenditure authority 2018 to 2019 budget Previous years expenditures 2018 to 2019 expenditures Cumulative expenditures up to 2018 to 2019 Planned expenditures 2019 to 2020table 10 note 1 Planned expenditures 2020 to 2021 and future yearstable 10 note 1 Substantial completion dates
West Block rehabilitation 862.9 862.9 100.3 742.4 100.3 842.7 13.0 7.2 2018
Wellington Building renovation 425.2 425.2 0.4 420.2 0.4 420.6 0.5 4.2 2016
Visitor Welcome Centre (Including UUR) 129.9 129.9 26.2 102.6 26.2 128.9 1.0 0.0 2018
Senate interim accommodations (Senate of Canada Building) 219.8 219.8 46.2 162.3 46.2 208.6 6.0 5.2 2018
Senate interim accommodations (40 Elgin, Floor 6 & 7) 39.2 26.5 8.4 6.3 8.4 14.7 1.1 10.8 2018
Senate interim accommodations (40 Elgin, lobby) 10.5 10.5 8.0 0.0 8.0 8.0 1.2 0.0 2019
Sir John A. Macdonald Building 99.5 99.5 0.0 99.5 0.0 99.5 0.0 0.0 2015
Library of Parliament 134.1 134.1 0.0 134.1 0.0 134.1 0.0 0.0 2016
Centre Block major rehabilitation 655.0 655.0 98.4 50.1 98.4 148.5 215.7 290.9 TBD
Visitor Welcome Centre Complex 106.5 106.5 0.8 0.0 0.8 0.9 20.1 85.6 TBD
Senate interim accommodation—Senate of Canada Building chamber broadcasting 12.3 12.3 2.9 4.0 2.9 6.9 0.0 0.0 2018
Material Management Handling Equipment 7.4 7.4 0.5 6.9 0.5 7.4 0.0 0.0 2018
West Parliament Hill landscape enhancement project 14.0 14.0 11.0 3.0 11.0 14.0 0.0 0.0 2018
Leases, fit-ups and otherstable 10 note 2 794.7 794.7 45.9 670.1 36.6 706.6 65.4 233.7 N/A
Total Major Capital Program 3,511.1 3,498.4 349.0 2,401.6 339.7 2,741.3 324.0 637.6 N/A

Table 10 notes

Table 10 note 1

Forecast to not exceed the overall LTVP funding of $4,702.9M.

Return to table 10 note 1 referrer

Table 10 note 2

Project approval of Leases Fit-ups are in constant dollars which do not include escalation costs whereas the expenditures are in current dollars.

Return to table 10 note 2 referrer

Remarks

  • Numbers may not add due to rounding
    • planned forecast may require project approval and/or expenditure authority amendments
  • New project approval process implemented in FY 2016/17 which now excludes pre-planning costs from Project Approval
  • Expenditures for projects that are already complete is due to building and transition costs

Recapitalization Program

Table 11: Recapitalization Program project spending fiscal year 2018 to 2019
(in millions of dollars)
      Budget Expenditures Forecast
Programs Project approval Expenditure authority 2018 to 2019 budget Previous years expenditures 2018 to 2019 expenditures Cumulative expenditures up to 2018 to 2019 Planned expenditures 2019 to 2020table 11 note 1 Planned expenditures 2020 to 2021 and future yearstable 11 note 1 Substantial completion dates
East Block 1867 Wing exterior rehabilitation 80.6 64.4 10.2 20.3 10.2 30.6 10.0 23.8 TBD
Confederation Building window frame stabilization and sash rehabilitation phase 2 2.1 2.1 0.1 2.0 0.1 2.1 0.0 0.0 2019
Confederation Building mechanical and electrical upgrades 3.9 3.9 0.9 1.8 0.9 2.6 0.0 0.0 2018
Lighting implementation—Visitor Welcome Centre Phase 1 2.0 2.0 2.0 0.0 2.0 2.0 0.0 0.0 2018
Lighting Implementation—West Block 4.9 1.1 0.1 0.0 0.1 0.1 0.7 4.0 2021
North Slope Vegetation Management 7.0 1.1 0.2 0.0 0.2 0.2 0.6 6.2 2023
Other Recapitalization 253.3 238.7 2.2 224.6 1.4 226.0 1.2 118.6 N/A
Total Recapitalization Program 353.6 313.2 15.7 248.7 14.8 263.5 12.5 152.6 N/A

Table 11 note

Table 11 note 1

Forecast to not exceed the overall LTVP funding of $4,702.9M.

Return to table 11 note 1 referrer

Remarks

  • Numbers may not add due to rounding
    • planned forecast may require project approval and/or expenditure authority amendments
  • New project approval process implemented in FY 2016/17 which now excludes pre to planning costs from Project Approval
  • Expenditures for projects that are already complete is due to building and transition costs

Building Components and Connectivity Program

Table 12: Building Components and Connectivity Program project spending fiscal year 2018 to 2019
(in millions of dollars)
      Budget Expenditures Forecast
Programs Project approval Expenditure authority 2018 to 2019 budget Previous years expenditures 2018 to 2019 expenditures Cumulative expenditures up to 2018 to 2019 Planned expenditures 2019 to 2020table 12 note 1 Planned expenditures 2020 to 2021 and future yearstable 12 note 1 Substantial completion dates
Next generation network infrastructure—telephony 19.9 19.9 2.5 10.7 2.5 13.2 1.0 5.7 2020
Modernization of the Parliament CATV 14.0 14.0 1.5 3.3 1.5 4.7 4.0 5.2 2021
South of Wellington connectivity 4.5 3.5 0.9 2.0 0.9 2.9 0.0 0.0 2018
IT infrastructure base building upgrades 15.2 6.3 1.7 0.9 1.7 2.6 2.5 9.2 2020
Datacentre disaster recovery projects 17.6 17.6 5.9 2.1 5.9 8.0 4.5 5.1 2020
Campus Connectivity Upgrades Project 17.6 17.6 17.6 0.0 17.6 17.6 0.0 0.0 2018
Other Building Components and Connectivity 141.1 141.1 2.4 135.5 1.2 136.7 3.0 11.6 N/A
Total Building Components and Connectivity Program 229.8 219.9 32.4 154.4 31.2 185.6 15.0 36.9 N/A

Table 12 note

Table 12 note 1

Forecast to not exceed the overall LTVP funding of $4,702.9M.

Return to table 12 note 1 referrer

Remarks

  • Numbers may not add due to rounding
    • planned forecast may require project approval and/or expenditure authority amendments
  • New project approval process implemented in FY 2016/17 which now excludes pre-planning costs from Project Approval. CATV and South of Wellington include pre-planning costs as both projects were approved before this change

Planning Program

Table 13: Planning Program project spending fiscal year 2018 to 2019
(in millions of dollars)
      Budget Expenditures Forecast
Programs Project approval Expenditure authority 2018 to 2019 budget Previous years expenditures 2018 to 2019 expenditures Cumulative expenditures up to 2018 to 2019 Planned expenditures 2019 to 2020table 13 note 1 Planned expenditures 2020 to 2021 and future yearstable 13 note 1 Substantial completion dates
Block 2 redevelopment, including public use for 100 Wellington 20.0 20.0 3.8 3.2 3.8 7.0 4.4 8.6 TBD
Campus planning 6.3 6.3 2.3 0.0 2.3 2.3 4.1 0.0 N/A
Planning program support 17.0 17.0 7.1 0.0 7.1 7.1 9.8 0.0 N/A
Other Planning 88.6 88.6 1.8 88.6 0.0 88.6 1.2 9.7 N/A
Total Planning Program 131.9 131.9 14.9 91.8 13.2 105.0 19.5 18.4 N/A

Table 13 note

Table 13 note 1

Forecast to not exceed the overall LTVP funding of $4,702.9M.

Return to table 13 note 1 referrer

Remarks

  • Numbers may not add due to rounding
    • planned forecast may require project approval and/or expenditure authority amendments
  • New project approval process implemented in FY 2016/17 which now excludes pre-planning costs from Project Approval

Security Infrastructure Program

Table 14: Security Infrastructure Program spending fiscal year 2018 to 2019
(in millions of dollars)
      Budget Expenditures Forecast
Programs Project approval Expenditure authority 2018 to 2019 budget Previous years expenditures 2018 to 2019 expenditures Cumulative expenditures up to 2018 to 2019 Planned expenditures 2019 to 2020table 14 note 1 Planned expenditures 2020 to 2021 and future yearstable 14 note 1 Substantial completion dates
West Block—Security Enhancement Phase 2 43.0 43.0 43.0 0.0 43.0 43.0 0.0 0.0 2018
Wellington—Security Enhancement 21.9 9.1 2.5 6.6 2.5 9.1 0.0 0.0 2018
Senate of Canada Building—Security Enhancement 18.0 18.0 7.2 10.7 7.2 18.0 0.0 0.0 2018
Other Security 101.6 101.6 0.0 86.6 0.0 86.6 0.0 34.5 N/A
Total Security Infrastructure Program 184.5 171.7 52.8 103.9 52.8 156.7 0.0 34.5 N/A

Table 14 note

Table 14 note 1

Forecast to not exceed the overall LTVP funding of $4,702.9M.

Return to table 14 note 1 referrer

Remarks

  • Numbers may not add due to rounding
    • planned forecast may require project approval and/or expenditure authority amendments
  • New project approval process implemented in FY 2016/17 which now excludes pre-planning costs from Project Approval

Leased

Table 15: Long Term Vision and Plan lease cost breakdown
(in millions of dollars)
LTVP Leases Lease Project Approval (LPA)table 15 note 1 Previous Years Expenditures Forecasted Expenditures in 2018 to 2019 Actual Expenditures in FY 2018 to 2019 Total Expenditures to End of FY 2018 to 2019
119 Queen Street 1.18 3.46 0.18 0.14 0.14
131 Queen Street 166.30 154.39 13.55 13.21 13.21
181 Queen Street 59.90 90.44 6.92 6.38 6.38
155 Queen Street (10th Floor) 13.62 4.61 0.53 0.51 0.51
155 Queen Street (6th Floor) 0.27 0.20 0.00 0.00 0.00
2074 to 2086 Walkley Road, Trade Shops 11.20 4.62 0.83 0.39 0.39
768 Belfast Road, House of Commons 2.01 1.44 0.00 0.00 0.00
2455 Don Reid Drive, E-Printing 11.09 7.10 1.16 0.53 0.53
1 Wellington Street—Rideau Committee Rooms 23.57 7.59 0.37 0.37 0.37
C.D. Howe Building 18.41 19.56 1.72 1.77 1.77
Clarica / Sun Life Building 46.86 40.71 3.83 3.41 3.41
Interim Room 200—Senate of Canada Building 9.11 8.54 0.00 0.00 0.00
Parks Canada 1.02 0.18 0.00 0.16 0.16
40 Elgin St. Chambers building 12.06 12.58 1.05 0.94 0.94
Grand Total LTVP 376.60 355.43 30.13 27.80 27.80

Table 15 note

Table 15 note 1

LPA is always approved at the net present value (NPV) and calculated in constant dollars which does not include escalation costs whereas expenditures are in current dollars.

Return to table 15 note 1 referrer