Summary of expenditures and delivery timeline
Table 9: Project/program/expenditures and delivery timeline
(in millions of dollars)
|
|
|
Budget |
Expenditures |
Forecast |
Programs |
Project approval |
Expenditure authority |
2018 to 2019 budget |
Previous years expenditures |
2018 to 2019 expenditures |
Cumulative expenditures up to
2018 to 2019 |
Planned expenditures 2019 to 2020table 9 note 1 |
Planned expenditures 2020 to 2021 and future yearstable 9 note 1 |
Total Major Capital Programtable 9 note 2 |
3,511.1 |
3,498.4 |
349.0 |
2,401.6 |
339.7 |
2,741.3 |
324.0 |
637.6 |
Total Recapitalization Program |
353.6 |
313.2 |
15.7 |
248.7 |
14.8 |
263.5 |
12.5 |
152.6 |
Total Building Components and Connectivity Program |
229.8 |
219.9 |
32.4 |
154.4 |
31.2 |
185.6 |
15.0 |
36.9 |
Total Security Infrastructure Program |
184.5 |
171.7 |
52.8 |
103.9 |
52.8 |
156.7 |
0.0 |
34.5 |
Total Planning Program |
131.9 |
131.9 |
14.9 |
91.8 |
13.2 |
105.0 |
19.5 |
18.4 |
Grand Total LTVP |
4,410.9 |
4,335.1 |
464.8 |
3,000.4 |
451.7 |
3,452.1 |
370.8 |
879.9 |
|
Remarks
- Numbers may not add due to rounding
- planned forecast may require project approval and/or expenditure authority amendments
- New project approval process implemented in FY 2016/17 which now excludes pre-planning costs from Project Approval
Major Capital Program
Table 10: Major Capital Program project spending fiscal year 2018 to 2019
(in millions of dollars)
|
|
|
Budget |
Expenditures |
Forecast |
Programs |
Project approval |
Expenditure authority |
2018 to 2019 budget |
Previous years expenditures |
2018 to 2019 expenditures |
Cumulative expenditures up to
2018 to 2019 |
Planned expenditures 2019 to 2020table 10 note 1 |
Planned expenditures 2020 to 2021 and future yearstable 10 note 1 |
Substantial completion dates |
West Block rehabilitation |
862.9 |
862.9 |
100.3 |
742.4 |
100.3 |
842.7 |
13.0 |
7.2 |
2018 |
Wellington Building renovation |
425.2 |
425.2 |
0.4 |
420.2 |
0.4 |
420.6 |
0.5 |
4.2 |
2016 |
Visitor Welcome Centre (Including UUR) |
129.9 |
129.9 |
26.2 |
102.6 |
26.2 |
128.9 |
1.0 |
0.0 |
2018 |
Senate interim accommodations (Senate of Canada Building) |
219.8 |
219.8 |
46.2 |
162.3 |
46.2 |
208.6 |
6.0 |
5.2 |
2018 |
Senate interim accommodations (40 Elgin, Floor 6 & 7) |
39.2 |
26.5 |
8.4 |
6.3 |
8.4 |
14.7 |
1.1 |
10.8 |
2018 |
Senate interim accommodations (40 Elgin, lobby) |
10.5 |
10.5 |
8.0 |
0.0 |
8.0 |
8.0 |
1.2 |
0.0 |
2019 |
Sir John A. Macdonald Building |
99.5 |
99.5 |
0.0 |
99.5 |
0.0 |
99.5 |
0.0 |
0.0 |
2015 |
Library of Parliament |
134.1 |
134.1 |
0.0 |
134.1 |
0.0 |
134.1 |
0.0 |
0.0 |
2016 |
Centre Block major rehabilitation |
655.0 |
655.0 |
98.4 |
50.1 |
98.4 |
148.5 |
215.7 |
290.9 |
TBD |
Visitor Welcome Centre Complex |
106.5 |
106.5 |
0.8 |
0.0 |
0.8 |
0.9 |
20.1 |
85.6 |
TBD |
Senate interim accommodation—Senate of Canada Building chamber broadcasting |
12.3 |
12.3 |
2.9 |
4.0 |
2.9 |
6.9 |
0.0 |
0.0 |
2018 |
Material Management Handling Equipment |
7.4 |
7.4 |
0.5 |
6.9 |
0.5 |
7.4 |
0.0 |
0.0 |
2018 |
West Parliament Hill landscape enhancement project |
14.0 |
14.0 |
11.0 |
3.0 |
11.0 |
14.0 |
0.0 |
0.0 |
2018 |
Leases, fit-ups and otherstable 10 note 2 |
794.7 |
794.7 |
45.9 |
670.1 |
36.6 |
706.6 |
65.4 |
233.7 |
N/A |
Total Major Capital Program |
3,511.1 |
3,498.4 |
349.0 |
2,401.6 |
339.7 |
2,741.3 |
324.0 |
637.6 |
N/A |
|
Remarks
- Numbers may not add due to rounding
- planned forecast may require project approval and/or expenditure authority amendments
- New project approval process implemented in FY 2016/17 which now excludes pre-planning costs from Project Approval
- Expenditures for projects that are already complete is due to building and transition costs
Recapitalization Program
Table 11: Recapitalization Program project spending fiscal year 2018 to 2019
(in millions of dollars)
|
|
|
Budget |
Expenditures |
Forecast |
Programs |
Project approval |
Expenditure authority |
2018 to 2019 budget |
Previous years expenditures |
2018 to 2019 expenditures |
Cumulative expenditures up to 2018 to 2019 |
Planned expenditures 2019 to 2020table 11 note 1 |
Planned expenditures 2020 to 2021 and future yearstable 11 note 1 |
Substantial completion dates |
East Block 1867 Wing exterior rehabilitation |
80.6 |
64.4 |
10.2 |
20.3 |
10.2 |
30.6 |
10.0 |
23.8 |
TBD |
Confederation Building window frame stabilization and sash rehabilitation phase 2 |
2.1 |
2.1 |
0.1 |
2.0 |
0.1 |
2.1 |
0.0 |
0.0 |
2019 |
Confederation Building mechanical and electrical upgrades |
3.9 |
3.9 |
0.9 |
1.8 |
0.9 |
2.6 |
0.0 |
0.0 |
2018 |
Lighting implementation—Visitor Welcome Centre Phase 1 |
2.0 |
2.0 |
2.0 |
0.0 |
2.0 |
2.0 |
0.0 |
0.0 |
2018 |
Lighting Implementation—West Block |
4.9 |
1.1 |
0.1 |
0.0 |
0.1 |
0.1 |
0.7 |
4.0 |
2021 |
North Slope Vegetation Management |
7.0 |
1.1 |
0.2 |
0.0 |
0.2 |
0.2 |
0.6 |
6.2 |
2023 |
Other Recapitalization |
253.3 |
238.7 |
2.2 |
224.6 |
1.4 |
226.0 |
1.2 |
118.6 |
N/A |
Total Recapitalization Program |
353.6 |
313.2 |
15.7 |
248.7 |
14.8 |
263.5 |
12.5 |
152.6 |
N/A |
|
Remarks
- Numbers may not add due to rounding
- planned forecast may require project approval and/or expenditure authority amendments
- New project approval process implemented in FY 2016/17 which now excludes pre to planning costs from Project Approval
- Expenditures for projects that are already complete is due to building and transition costs
Building Components and Connectivity Program
Table 12: Building Components and Connectivity Program project spending fiscal year 2018 to 2019
(in millions of dollars)
|
|
|
Budget |
Expenditures |
Forecast |
Programs |
Project approval |
Expenditure authority |
2018 to 2019 budget |
Previous years expenditures |
2018 to 2019 expenditures |
Cumulative expenditures up to 2018 to 2019 |
Planned expenditures 2019 to 2020table 12 note 1 |
Planned expenditures 2020 to 2021 and future yearstable 12 note 1 |
Substantial completion dates |
Next generation network infrastructure—telephony |
19.9 |
19.9 |
2.5 |
10.7 |
2.5 |
13.2 |
1.0 |
5.7 |
2020 |
Modernization of the Parliament CATV |
14.0 |
14.0 |
1.5 |
3.3 |
1.5 |
4.7 |
4.0 |
5.2 |
2021 |
South of Wellington connectivity |
4.5 |
3.5 |
0.9 |
2.0 |
0.9 |
2.9 |
0.0 |
0.0 |
2018 |
IT infrastructure base building upgrades |
15.2 |
6.3 |
1.7 |
0.9 |
1.7 |
2.6 |
2.5 |
9.2 |
2020 |
Datacentre disaster recovery projects |
17.6 |
17.6 |
5.9 |
2.1 |
5.9 |
8.0 |
4.5 |
5.1 |
2020 |
Campus Connectivity Upgrades Project |
17.6 |
17.6 |
17.6 |
0.0 |
17.6 |
17.6 |
0.0 |
0.0 |
2018 |
Other Building Components and Connectivity |
141.1 |
141.1 |
2.4 |
135.5 |
1.2 |
136.7 |
3.0 |
11.6 |
N/A |
Total Building Components and Connectivity Program |
229.8 |
219.9 |
32.4 |
154.4 |
31.2 |
185.6 |
15.0 |
36.9 |
N/A |
|
Remarks
- Numbers may not add due to rounding
- planned forecast may require project approval and/or expenditure authority amendments
- New project approval process implemented in FY 2016/17 which now excludes pre-planning costs from Project Approval. CATV and South of Wellington include pre-planning costs as both projects were approved before this change
Planning Program
Table 13: Planning Program project spending fiscal year 2018 to 2019
(in millions of dollars)
|
|
|
Budget |
Expenditures |
Forecast |
Programs |
Project approval |
Expenditure authority |
2018 to 2019 budget |
Previous years expenditures |
2018 to 2019 expenditures |
Cumulative expenditures up to 2018 to 2019 |
Planned expenditures 2019 to 2020table 13 note 1 |
Planned expenditures 2020 to 2021 and future yearstable 13 note 1 |
Substantial completion dates |
Block 2 redevelopment, including public use for 100 Wellington |
20.0 |
20.0 |
3.8 |
3.2 |
3.8 |
7.0 |
4.4 |
8.6 |
TBD |
Campus planning |
6.3 |
6.3 |
2.3 |
0.0 |
2.3 |
2.3 |
4.1 |
0.0 |
N/A |
Planning program support |
17.0 |
17.0 |
7.1 |
0.0 |
7.1 |
7.1 |
9.8 |
0.0 |
N/A |
Other Planning |
88.6 |
88.6 |
1.8 |
88.6 |
0.0 |
88.6 |
1.2 |
9.7 |
N/A |
Total Planning Program |
131.9 |
131.9 |
14.9 |
91.8 |
13.2 |
105.0 |
19.5 |
18.4 |
N/A |
|
Remarks
- Numbers may not add due to rounding
- planned forecast may require project approval and/or expenditure authority amendments
- New project approval process implemented in FY 2016/17 which now excludes pre-planning costs from Project Approval
Security Infrastructure Program
Table 14: Security Infrastructure Program spending fiscal year 2018 to 2019
(in millions of dollars)
|
|
|
Budget |
Expenditures |
Forecast |
Programs |
Project approval |
Expenditure authority |
2018 to 2019 budget |
Previous years expenditures |
2018 to 2019 expenditures |
Cumulative expenditures up to 2018 to 2019 |
Planned expenditures 2019 to 2020table 14 note 1 |
Planned expenditures 2020 to 2021 and future yearstable 14 note 1 |
Substantial completion dates |
West Block—Security Enhancement Phase 2 |
43.0 |
43.0 |
43.0 |
0.0 |
43.0 |
43.0 |
0.0 |
0.0 |
2018 |
Wellington—Security Enhancement |
21.9 |
9.1 |
2.5 |
6.6 |
2.5 |
9.1 |
0.0 |
0.0 |
2018 |
Senate of Canada Building—Security Enhancement |
18.0 |
18.0 |
7.2 |
10.7 |
7.2 |
18.0 |
0.0 |
0.0 |
2018 |
Other Security |
101.6 |
101.6 |
0.0 |
86.6 |
0.0 |
86.6 |
0.0 |
34.5 |
N/A |
Total Security Infrastructure Program |
184.5 |
171.7 |
52.8 |
103.9 |
52.8 |
156.7 |
0.0 |
34.5 |
N/A |
|
Remarks
- Numbers may not add due to rounding
- planned forecast may require project approval and/or expenditure authority amendments
- New project approval process implemented in FY 2016/17 which now excludes pre-planning costs from Project Approval
Leased
Table 15: Long Term Vision and Plan lease cost breakdown
(in millions of dollars)
LTVP Leases |
Lease Project Approval (LPA)table 15 note 1 |
Previous Years Expenditures |
Forecasted Expenditures in 2018 to 2019 |
Actual Expenditures in FY 2018 to 2019 |
Total Expenditures to End of FY 2018 to 2019 |
119 Queen Street |
1.18 |
3.46 |
0.18 |
0.14 |
0.14 |
131 Queen Street |
166.30 |
154.39 |
13.55 |
13.21 |
13.21 |
181 Queen Street |
59.90 |
90.44 |
6.92 |
6.38 |
6.38 |
155 Queen Street (10th Floor) |
13.62 |
4.61 |
0.53 |
0.51 |
0.51 |
155 Queen Street (6th Floor) |
0.27 |
0.20 |
0.00 |
0.00 |
0.00 |
2074 to 2086 Walkley Road, Trade Shops |
11.20 |
4.62 |
0.83 |
0.39 |
0.39 |
768 Belfast Road, House of Commons |
2.01 |
1.44 |
0.00 |
0.00 |
0.00 |
2455 Don Reid Drive, E-Printing |
11.09 |
7.10 |
1.16 |
0.53 |
0.53 |
1 Wellington Street—Rideau Committee Rooms |
23.57 |
7.59 |
0.37 |
0.37 |
0.37 |
C.D. Howe Building |
18.41 |
19.56 |
1.72 |
1.77 |
1.77 |
Clarica / Sun Life Building |
46.86 |
40.71 |
3.83 |
3.41 |
3.41 |
Interim Room 200—Senate of Canada Building |
9.11 |
8.54 |
0.00 |
0.00 |
0.00 |
Parks Canada |
1.02 |
0.18 |
0.00 |
0.16 |
0.16 |
40 Elgin St. Chambers building |
12.06 |
12.58 |
1.05 |
0.94 |
0.94 |
Grand Total LTVP |
376.60 |
355.43 |
30.13 |
27.80 |
27.80 |
Table 15 note
- Table 15 note 1
-
LPA is always approved at the net present value (NPV) and calculated in constant dollars which does not include escalation costs whereas expenditures are in current dollars.
Return to table 15 note 1 referrer
|
Document navigation for "The Long Term Vision and Plan: Annual Report 2018 to 2019"