Financial information summary: The Long Term Vision and Plan for the Parliamentary Precinct—Annual Report 2020 to 2021
On this page
Summary of expenditures and delivery timeline
| Programs | Project approval |
Expenditure authority |
Budget | Expenditures | Forecast | |||
|---|---|---|---|---|---|---|---|---|
| Planned expenditures for 2020 to 2021table 1 note 2 | Previous years’ expenditures |
2020 to 2021 expenditures |
Cumulative expenditures up to 2020 to 2021 | Planned expenditures for 2021 to 2022table 1 note 3 |
Planned expenditures for 2022 to 2023 and future yearstable 1 note 3 |
|||
| Total Major Capital Programtable 1 note 1 | 4979.2 | 3646.4 | 301.2 | 3,054.4 | 290.0 | 3,344.4 | 188.3 | 1392.1 |
| Total Recapitalization Program | 371.3 | 367.9 | 29.6 | 277.7 | 31.0 | 308.7 | 35.8 | 8.9 |
| Total Building Components and Connectivity Program | 276.9 | 274.6 | 17.2 | 203.4 | 16.6 | 220.0 | 21.4 | 34.6 |
| Total Security Infrastructure Program | 156.7 | 156.7 | 0.0 | 156.7 | 0.0 | 156.7 | 0.0 | 0.0 |
| Total Planning Program | 157 | 157 | 14.2 | 126.5 | 17.3 | 143.8 | 13.2 | 0.0 |
| Grand total Long Term Vision and Plan (LTVP) | 5941.2 | 4602.6 | 362.2 | 3,818.6 | 354.9 | 4,173.5 | 258.7 | 1435.6 |
Table 1 Notes
RemarksNumbers may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments. |
||||||||
Major Capital Program
| Programs | Project approval |
Expenditure authority |
Budget | Expenditures | Forecast | Substantial completion dates |
|||
|---|---|---|---|---|---|---|---|---|---|
| Planned expenditures for 2020 to 2021table 2 note 2 | Previous years’ expenditures |
2020 to 2021 expenditures |
Cumulative expenditures up to 2020 to 2021 | Planned expenditures for 2021 to 2022 table 2 note 3 |
Planned expenditures for 2022 to 2023 and future years table 2 note 3 |
||||
| West Block rehabilitation | 862.9 | 862.9 | 0.5 | 851.8 | 0.9 | 852.7 | 0.5 | 0.0 | 2018 |
| Wellington Building renovation | 425.2 | 425.2 | 0.6 | 421.0 | 0.6 | 421.7 | 0.0 | 0.0 | 2016 |
| Visitor Welcome Centre (incl. UUR) | 129.9 | 129.9 | 0.0 | 129.9 | 0.0 | 129.9 | 0.0 | 0.0 | 2018 |
| Senate interim accommodations (Government Conference Centre) | 219.8 | 219.8 | 2.5 | 211.2 | 2.5 | 213.7 | 2.1 | 0.4 | 2018 |
| Senate interim accommodations (40 Elgin, floor 6 and 7) | 39.2 | 26.5 | 0.8 | 15.7 | 0.8 | 16.5 | 0.8 | 9.1 | 2018 |
| Senate interim accommodations (40 Elgin, lobby) | 10.5 | 10.5 | 0 | 8.9 | 0.1 | 8.9 | 0.0 | 0.0 | 2019 |
| Sir John A. Macdonald Building | 99.5 | 99.5 | 0.0 | 99.5 | 0.0 | 99.5 | 0.0 | 0.0 | 2015 |
| Library of Parliament | 134.1 | 134.1 | 0.0 | 134.1 | 0.0 | 134.1 | 0.0 | 0.0 | 2006 |
| Centre Block major rehabilitationtable 2 note 4 | 655.0 | 655.0 | 194.7 | 386.0 | 185.9 | 571.9 | 83.1 | 0.0 | TBD |
| Parliament Welcome Centretable 2 note 4 | 106.5 | 106.5 | 50.0 | 5.7 | 47.1 | 52.8 | 53.8 | 0.0 | TBD |
| 100 Wellington short-term use | 6.0 | 6.0 | 0.3 | 5.3 | 0.3 | 5.6 | 0.0 | 0.0 | 2020 |
| Block 2 redevelopment | 1,372.5 | 52.3 | 5.0 | 0.0 | 4.5 | 4.5 | 8.6 | 1337.8 | TBD |
| Library of Parliament (LoP)—virtual reality tour | 7.5 | 7.5 | 3.9 | 2.7 | 3.9 | 6.6 | 0.6 | 0.0 | 2021 |
| Victoria lookout reinstatement | 0.8 | 0.8 | 0.8 | 0.0 | 0.8 | 0.8 | 0.0 | 0.0 | 2020 |
| Interim operation command center | 7.6 | 7.6 | 3.4 | 0.0 | 4.4 | 4.4 | 2.2 | 0 | 2022 |
| Leases, fit-ups and otherstable 2 note 1 | 902.1 | 902.1 | 38.5 | 782.6 | 38.1 | 820.8 | 36.6 | 44.8 | N/A |
| Total Major Capital Program | 4979.2 | 3646.4 | 301.2 | 3,054.4 | 290.0 | 3,344.4 | 188.3 | 1392.1 | N/A |
Table 2 Notes
RemarksNumbers may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments. |
|||||||||
Recapitalization Program
| Programs | Project approval |
Expenditure authority |
Budget | Expenditures | Forecast | Substantial completion dates |
|||
|---|---|---|---|---|---|---|---|---|---|
| Planned expenditures for 2020 to 2021table 3 note 1 | Previous years’ expenditures |
2020 to 2021 expenditures |
Cumulative expenditures up to 2020 to 2021 | Planned expenditures for 2021 to 2022 table 3 note 2 |
Planned expenditures for 2022 to 2023 and future years table 3 note 2 |
||||
| East Block rehabilitation | 97.5 | 97.5 | 24.5 | 40.8 | 26.2 | 66.9 | 21.6 | 4.5 | 2022 |
| Lighting implementation—West Block | 7.2 | 7.2 | 0.4 | 0.5 | 0.4 | 0.9 | 5.8 | 0.6 | 2022 |
| North slope vegetation management | 9.1 | 9.1 | 0.9 | 0.5 | 0.8 | 1.2 | 7.9 | 0 | 2023 |
| Queen's Gate accessibility | 4.4 | 0.9 | 0.4 | 0.0 | 0.1 | 0.1 | 0.5 | 3.8 | 2023 |
| Other recapitalization | 253.1 | 253.1 | 3.5 | 235.9 | 3.6 | 239.5 | 0.1 | 0.0 | N/A |
| Total Recapitalization Program | 371.3 | 367.9 | 29.6 | 277.7 | 31.0 | 308.7 | 35.8 | 8.9 | N/A |
Table 3 Notes
RemarksNumbers may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments. |
|||||||||
Building Components and Connectivity Program
| Programs | Project approval |
Expenditure authority |
Budget | Expenditures | Forecast | Substantial completion dates |
|||
|---|---|---|---|---|---|---|---|---|---|
| Planned expenditures for 2020 to 2021table 4 note 1 | Previous years’ expenditures |
2020 to 2021 expenditures |
Cumulative expenditures up to 2020 to 2021 | Planned expenditures for 2021 to 2022 table 4 note 2 |
Planned expenditures for 2022 to 2023 and future years table 4 note 2 |
||||
| Next generation network infrastructure—telephony | 19.9 | 19.9 | 0.0 | 13.3 | 0.0 | 13.4 | 0.0 | 6.5 | 2024 |
| Modernization of the Parliament Community access television (CATV) | 14.0 | 14.0 | 2.1 | 7.0 | 2.0 | 9.0 | 1.5 | 3.4 | 2023 |
| IT infrastructure base building upgrades | 15.2 | 15.2 | 3.1 | 5.2 | 2.6 | 7.8 | 2.6 | 4.0 | 2022 |
| Datacentre disaster recovery projects | 37.0 | 37.0 | 4.3 | 13.4 | 4.0 | 17.3 | 5.8 | 13.9 | 2024 |
| Other building components and connectivity | 190.8 | 188.5 | 7.7 | 164.5 | 7.9 | 172.5 | 11.5 | 6.9 | N/A |
| Total Building Components and Connectivity Program | 276.9 | 274.6 | 17.2 | 203.4 | 16.6 | 220.0 | 21.4 | 34.6 | N/A |
Table 4 Notes
RemarksNumbers may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments. |
|||||||||
Planning Program
| Programs | Project approval |
Expenditure authority |
Budget | Expenditures | Forecast | Substantial completion dates |
|||
|---|---|---|---|---|---|---|---|---|---|
| Planned expenditures for 2020 to 2021table 5 note 1 | Previous years’ expenditures |
2020 to 2021 expenditures |
Cumulative expenditures up to 2020 to 2021 | Planned expenditure for 2021 to 2022 table 5 note 2 |
Planned expenditure for 2022 to 2023 and future years table 5 note 2 |
||||
| Campus planning | 8.6 | 8.6 | 3.3 | 5.1 | 1.5 | 6.6 | 2.0 | 0.0 | N/A |
| Planning program support | 48.3 | 48.3 | 10.9 | 21.2 | 15.8 | 37.0 | 11.3 | 0.0 | N/A |
| Other planning | 100.1 | 100.1 | 0.0 | 100.1 | 0.0 | 100.1 | 0.0 | 0.0 | N/A |
| Total Planning Program | 157.0 | 157.0 | 14.2 | 126.5 | 17.3 | 143.8 | 13.2 | 0.0 | N/A |
Table 5 Note
RemarksNumbers may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments. |
|||||||||
Security Infrastructure Program
| Programs | Project approval |
Expenditure authority |
Budget | Expenditures | Forecast | Substantial completion dates |
|||
|---|---|---|---|---|---|---|---|---|---|
| 2020 to 2021 budget |
Previous years’ expenditures |
2020 to 2021 expenditures |
Cumulative expenditures up to 2020 to 2021 | Planned expenditure for 2021 to 2022 table 6 note 1 |
Planned expenditures for 2022 to 2023 and future years table 6 note 1 |
||||
| Other security | 156.7 | 156.7 | 0.0 | 156.7 | 0.0 | 156.7 | 0.0 | 0.0 | N/A |
| Total Security Infrastructure Program | 156.7 | 156.7 | 0.0 | 156.7 | 0.0 | 156.7 | 0.0 | 0.0 | N/A |
Table 6 Note
RemarksNumbers may not add due to rounding. Planned expenditures may require project approval and/or expenditure authority amendments. |
|||||||||
Lease cost
| LTVP leases | Total lease cost forecasted table 7 note 1 |
Previous years' expenditures | Planned expenditures for 2020 to 2021 | Expenditures for 2020 to 2021 | Cumulative expenditures up to 2020 to 2021 |
|---|---|---|---|---|---|
| 119 Queen Street | 3.6 | 3.6 | 0.0 | 0.0 | 3.6 |
| 131 Queen Street | 286.7 | 180.7 | 13.1 | 13.0 | 193.7 |
| 181 Queen Street | 127.8 | 103.7 | 7.0 | 6.9 | 110.6 |
| 155 Queen Street (10th floor) | 19.4 | 6.0 | 1.2 | 1.2 | 7.2 |
| 155 Queen Street (6th floor) | 0.2 | 0.2 | 0.0 | 0.0 | 0.2 |
| 2074-2086 Walkley Road, trade shops | 17.6 | 5.4 | 0.5 | 0.5 | 5.9 |
| 768 Belfast Road, House of Commons | 1.4 | 1.4 | 0.0 | 0.0 | 1.4 |
| 2455 Don Reid Drive, e-printing | 10.3 | 8.2 | 0.7 | 0.6 | 8.7 |
| 1 Wellington Street—Rideau committee rooms | 22.8 | 8.2 | 0.4 | 0.4 | 8.7 |
| C.D. Howe Building | 22.8 | 22.8 | 1.7 | 1.7 | 24.5 |
| Clarica / Sun Life Building | 80.6 | 47.3 | 3.5 | 3.1 | 50.5 |
| Interim room 200—Government of Canada Conference Centre | 8.5 | 8.5 | 0.0 | 0.0 | 8.5 |
| Parks Canada | 0.4 | 0.4 | 0.1 | 0.1 | 0.5 |
| 40 Elgin St. Chambers building | 22.0 | 2.4 | 0.8 | 0.8 | 3.2 |
| 150 Slater Street | 2.3 | 3.7 | 1.4 | 1.4 | 5.1 |
| Grand Total LTVP | 626.4 | 402.7 | 30.4 | 29.6 | 432.3 |
Table 7 Note
|
|||||