Follow-up on Internal Audit of the Joint Support Ship Project
Caveat
The result of this work does not constitute an audit of the Joint Support Ship (JSS) project. Rather, this report was prepared to provide reasonable assurance that the Management Action Plans (MAPs) that resulted from the 2011 audit were implemented as stated and as such have addressed the associated recommendations.
Alternate Formats
Assistant Deputy Minister (Review Services)
Recommendation # | MAP | OPI | ADM(RS) Assessment of Progress | |||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1. Capability Cost Trade-Off | 1.1 The operational impact and availability of JSS in relation to the number of ships will be articulated in the next revision of the statement of operational requirements to be presented and endorsed at the annual Senior Review Board meeting in 2012. | Commander Royal Canadian Navy | Full Implementation | |||||||||||||||||||||||||||||||
2. Project Schedule | 2.1 ADM(RS) project scheduling recommendations will be adopted. The JSS PMO will update its Project Master Schedule to ensure that all identified Project Definition activities have appropriate resources assigned with realistic productivity considerations and levels. | ADM(Mat) | Obsolete or Superseded | |||||||||||||||||||||||||||||||
2.2 The JSS PMO will ensure the NSPS Secretariat maintains the issue of non-combat work package sequencing as an open action item within its DND/Canadian Coast Guard Project Action Log. This will promote a regular dialogue on this schedule risk between NSPS, DND, Department of Fisheries, and the Canadian Coast Guard on the optimal scheduling of the affected projects. Finally, given the interdepartmental significance, visibility into this risk has been elevated to the Major Crown Project-Interdepartmental Oversight Committee level. | ADM(Mat) | Full ImplementationFootnote 4 |
||||||||||||||||||||||||||||||||
3. Contract Management | 3.1 The recommendations proposed by ADM(RS) in support of contract management will be taken into consideration when developing future contracts in support of JSS, specifically the build contract with the designated NSPS shipyard. | ADM(Mat) | Preparation for Implementation | |||||||||||||||||||||||||||||||
4. Contract Management | 4.1 ADM(RS) recommendations concerning vendor reporting and statement of work clarity have been implemented in both the Military Off The Shelf and New Design procurement documents. Terms of payment are presently being negotiated to ensure payments will be in line with actual work (milestones) completed. | ADM(Mat) | Obsolete or Superseded | |||||||||||||||||||||||||||||||
5. Human Resources Management | 5.1 Project Management Support Office, in consultation with Director Materiel Group Operational Research Acquisition Support Team, will undertake to develop a PMO staffing model to supplement the existing departmental methodology and guidance. | ADM(Mat) | Full ImplementationFootnote 5 |
|||||||||||||||||||||||||||||||
5.2 The JSS PMO has drafted a Human Resource Management Plan that reflects ADM(RS) recommendations to better address succession planning and surge requirements within the project. The Human Resource plan is currently under review and will be promulgated when ready. | ADM(Mat) | Full Implementation | ||||||||||||||||||||||||||||||||
6. In-Service Support Strategy | 6.1 Linking vendor performance to exercising an In-Service Support contract option will be considered in the next In-Service Support Statement of Work and In-Service Support Pro-Forma contract revisions. The criteria, metrics and associated penalties tied to maintenance deferral by the vendor will also be considered and will be articulated in detail in the above-mentioned revised documents. | ADM(Mat) | Full ImplementationFootnote 6 |
|||||||||||||||||||||||||||||||
7. Risk Management | 7.1 ADM(RS) risk management recommendations have been incorporated into the project’s draft Risk Management Plan. This revision of the Risk Management Plan is presently under review and will be promulgated in the fall of 2011. Updates include improved definitions for risk impact levels and the adoption of the five levels of risk severity, in accordance with the DND Integrated Risk Management policy. | ADM(Mat) | Full Implementation | |||||||||||||||||||||||||||||||
7.2 The JSS PMO will rescore all project risks in light of the new impact definitions and complete a risk quantification exercise using Project Management Body Of Knowledge’s Expected Monetary Value practices to assess the adequacy of the project’s existing risk mitigation and contingency levels. | ADM(Mat) | Full Implementation | ||||||||||||||||||||||||||||||||
Legend | ||||||||||||||||||||||||||||||||||
Obsolete or Superseded | No Progress or Insignificant Progress | Planning Stage | Preparation for Implementation | Substantial Implementation | Full Implementation |
Table B-1 Details – MAP Scorecard
Recommendation 1
MAP | OPI | Target Date | Progress to Date | Assessment | |
---|---|---|---|---|---|
1.1 The operational impact and availability of JSS in relation to the number of ships will be articulated in the next revision of the statement of operational requirements to be presented and endorsed at the annual Senior Review Board meeting in 2012. | Commander Royal Canadian Navy | November 2012 | In 2012 the JSS Statement of Operational Requirements was updated to address the following three issues:
Subsequent to the original audit of JSS, the new Defence Policy: Strong, Secure, Engaged (SSE) specified two JSS. The PMO has updated its communication products accordingly. |
Full Implementation | |
ADM(RS) Assessment of Progress on MAP: Full Implementation | |||||
Obsolete or Superseded | No Progress or Insignificant Progress | Planning Stage | Preparation for Implementation | Substantial Implementation | Full Implementation |
Table C-1 Details – Status of the Implementation of the MAP Item for Recommendation 1
Recommendation 2
MAP | OPI | Target Date | Progress to Date | Assessment | |
---|---|---|---|---|---|
2.1 ADM(RS) project scheduling recommendations will be adopted. The JSS PMO will update its Project Master Schedule to ensure that all identified Project Definition activities have appropriate resources assigned with realistic productivity considerations and levels. | ADM(Mat) | November 2011 | Since the original audit, roles regarding the project schedule have evolved. The Shipyard Contractor now manages the majority of the tasks that make up the greater project schedule, as opposed to the PMO. The PMO now monitors and provides feedback on the Shipyard Contractor’s Integrated Master Schedule. In particular, the PMO is monitoring and completing several tasks related to the Integrated Master Schedule with the Shipyard Contractor. These actions include:
Due to these changes, this MAP is obsolete and the original risk of project definition activities being delayed due to insufficient schedule controls within the PMO is no longer a significant concern. The risk has largely been transferred to the monitoring of the Shipyard Contractor’s schedule. |
Obsolete or Superseded | |
ADM(RS) Assessment of Progress on MAP: Obsolete or Superseded | |||||
Obsolete or Superseded | No Progress or Insignificant Progress | Planning Stage | Preparation for Implementation | Substantial Implementation | Full Implementation |
Table C-2 Details – Status of the Implementation of the MAP Item for Recommendation 2
Recommendation 3
MAP | OPI | Target Date | Progress to Date | Assessment | |
---|---|---|---|---|---|
3.1 The recommendations proposed by ADM(RS) in support of contract management will be taken into consideration when developing future contracts in support of JSS, specifically the build contract with the designated NSPS shipyard. | ADM(Mat) | Effective Project Approval | The original audit included a review of the draft NSPS Request For Proposal and identified areas for improvement with respect to contract clauses. It was recommended that ADM(Mat) include these clauses in the JSS implementation build contract. Although the implementation build contract has not been finalized, considerable progress has been made in addressing original concerns in two of the current definition phase contracts – the Design and Production Engineering and Long Lead Items contracts. The following progress was observed:
Much progress has been made, however until the future implementation build contract is in place with clauses to address risks raised in the original audit, this MAP cannot be considered complete. |
Preparation for Implementation | |
Revised target date: November 2019 | |||||
ADM(RS) Assessment of Progress on MAP: Preparation for Implementation | |||||
Obsolete or Superseded | No Progress or Insignificant Progress | Planning Stage | Preparation for Implementation | Substantial Implementation | Full Implementation |
Table C-3 Details – Status of the Implementation of the MAP Item for Recommendation 3
Recommendation 4
MAP | OPI | Target Date | Progress to Date | Assessment | |
---|---|---|---|---|---|
4.1 ADM(RS) recommendations concerning vendor reporting and Statement of Work clarity have been implemented in both the Military Off the Shelf and New Design procurement documents. Terms of payment are presently being negotiated to ensure payments will be in line with actual work (milestones) completed. | ADM(Mat) | March 2011 | The recommendation and associated MAP 4.1 had many elements that were specific to two 2011 definition phase contracts. These specific definition phase contracts are no longer in place as the scope of work has been completed. This MAP is therefore obsolete. Nonetheless, the follow-up examined the progress made before the obsolescence and observed that some progress had been made:
|
Obsolete or Superseded | |
ADM(RS) Assessment of Progress on MAP: Obsolete or Superseded | |||||
Obsolete or Superseded | No Progress or Insignificant Progress | Planning Stage | Preparation for Implementation | Substantial Implementation | Full Implementation |
Table C-4 Details – Status of the Implementation of the MAP Item for Recommendation 4
Recommendation 5
MAP | OPI | Target Date | Progress to Date | Assessment | |
---|---|---|---|---|---|
5.2 The JSS PMO has drafted a Human Resources Management Plan that reflects ADM(RS) recommendations to better address succession planning and surge requirements within the project. The Human Resources plan is currently under review and will be promulgated when ready. | ADM(Mat) | February 2012 | The Human Resources Plans from fiscal year 2011/2012 and 2017 (current version) include a section on succession management. It describes how the JSS PMO will identify positions that require added attention, and the activities that can be completed to mitigate possible future turnover of key personnel. The fiscal year 2011/2012 Human Resources Plan includes sharing of resources from Director General Maritime Equipment Program Management and the Engineering Logistic Management Support contractor to handle surges during the Project Definition phase. Further, the 2017 Memoranda of Understanding with the Canadian Coast Guard establishes how both organizations are expected to manage their various responsibilities required for the review work for project inspections. |
Full Implementation | |
ADM(RS) Assessment of Progress on MAP: Full Implementation | |||||
Obsolete or Superseded | No Progress or Insignificant Progress | Planning Stage | Preparation for Implementation | Substantial Implementation | Full Implementation |
Table C-5 Details – Status of the Implementation of the MAP Item for Recommendation 5
Recommendation 7
MAP | OPI | Target Date | Progress to Date | Assessment | |
---|---|---|---|---|---|
7.1 ADM(RS) risk management recommendations have been incorporated into the project’s draft Risk Management Plan. This revision of the Risk Management Plan is presently under review and will be promulgated in the fall of 2011. Updates include improved definitions for risk impact levels and the adoption of the five levels of risk severity, in accordance with the DND Integrated Risk Management Policy. | ADM(Mat) | December 2011 | The updated Risk Management Plan addressed the four risk management observations from the audit report. The Risk Management Plan and relevant documents included:
|
Full Implementation | |
ADM(RS) Assessment of Progress on MAP: Full Implementation | |||||
Obsolete or Superseded | No Progress or Insignificant Progress | Planning Stage | Preparation for Implementation | Substantial Implementation | Full Implementation |
Table C-6 Details – Status of the Implementation of the first MAP Item for Recommendation 7
Recommendation 7
MAP | OPI | Target Date | Progress to Date | Assessment | |
---|---|---|---|---|---|
7.2 JSS PMO will rescore all project risks in light of the new impact definitions and complete a risk quantification exercise using Project Management Body of Knowledge’s Expected Monetary Value practices to assess the adequacy of the project’s existing risk mitigation and contingency levels. | ADM(Mat) | March 2012 | All project risks in the updated risk register were assessed using the Expected Monetary Value method in accordance with the Project Management Body of Knowledge and had a quantitative measure associated with it. While there was no specific evidence of the PMO assessing the totals against their contingency amounts, they did calculate the total Expected Monetary value. The contingency available to the project, when compared to the total Expected Monetary value, should be sufficient to mitigate the risks. |
Full Implementation | |
ADM(RS) Assessment of Progress on MAP: Full Implementation | |||||
Obsolete or Superseded | No Progress or Insignificant Progress | Planning Stage | Preparation for Implementation | Substantial Implementation | Full Implementation |
Table C-7 Details – Status of the Implementation of the second MAP Item for Recommendation 7
Page details
- Date modified: