Status report on transformational and major Crown projects
The information contained herein is accurate and reliable as of 31 January 2018
Project name | AIRLIFT CAPABILITY PROJECT - TACTICAL | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Airlift Capability Project – Tactical (ACP-T) is to acquire an assured and effective tactical airlift capability that will replace the CC-130E Hercules aircraft fleet. This acquisition will provide the capability to logistically support international and domestic operations. | ||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Aerospace Equipment Acquisition. The ACP-T has the following project outcomes:
This capability is being delivered to the Royal Canadian Air Force. |
||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to this project. Canada will receive IRBs equivalent to 100% of the eligible contract value from Lockheed Martin Corporation for both the acquisitions and the In-Service Support. | ||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||||||||||
Prime contractor | Lockheed Martin Corporation - Marietta, Georgia, USA | ||||||||||||||||||||||
Major subcontractors | Cascade Aerospace - Abbotsford, British Columbia, Canada IMP Aerospace - Enfield, Nova Scotia, Canada CAE - Montreal, Quebec, Canada Standard Aero - Winnipeg, Manitoba, Canada HAAS Group - Oshawa, Ontario, Canada |
||||||||||||||||||||||
Project phase | Implementation: December 2007 Closeout (expected): 2019 |
||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||
Progress report and explanation of variances | The ACP-T project is achieving project objectives, notably:
Scope: The ACP-T project is on track to deliver its 2007 approved scope. Cost: The ACP-T project is currently within the 2007 approved budget. Schedule: The project has experienced a delay against the 2007 approved schedule. The ACP-T FOC and Project Closeout dates were amended twice. The first change was as a result of a delay in the implementation of the development of the Block 7 modifications. Then, due to changing Communications, Navigation, Surveillance - Air Traffic Management (CNS-ATM) requirements, the CC-130J fleet had to be modified to include an Automatic Dependent Surveillance - Broadcast (ADS-B) system in order to operate over the US and Europe. Closeout activities are being completed concurrently with ADS-B modifications. The Effective Project Closeout is expected in December 2018. The Full Operational Capability will coincide with the expected completion of the ADS-B modification in August 2018. Work Plan: In the Fiscal Year 2018-19, the ACP-T project will achieve the following:
|
Project name | ARCTIC AND OFFSHORE PATROL SHIP | ||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Arctic and Offshore Patrol Ship (AOPS) project is to acquire a new ice-capable offshore patrol capability which will provide the capability to conduct armed sea-borne surveillance in Canada's Economic Exclusion Zone, including the Arctic. | ||||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Maritime Equipment Acquisition. The AOPS project has the following project outcomes:
This capability will be delivered to the Royal Canadian Navy. |
||||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to this project. Canada will receive IRBs equivalent to 100% of the contracted value for the AOPS implementation. |
||||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||||||||||||
Prime contractor | Acquisition: Irving Shipbuilding Inc. – Halifax, Nova Scotia, Canada In-Service Support: Thales Canada Inc. and Thales Australia Inc. – Ottawa, Ontario, Canada |
||||||||||||||||||||||||
Major subcontractors | Gibbs & Cox Maritime Solutions – Arlington, Virginia, USA Lockheed Martin – Ottawa, Ontario, Canada General Electric – Peterborough, Ontario, Canada Fleetway Inc. – Ottawa, Ontario, Canada Lloyds Register – Toronto, Ontario, Canada BAE Systems – Ottawa, Ontario, Canada L-3 MAPPS – St Laurent, Quebec, Canada |
||||||||||||||||||||||||
Project phase | Implementation: December 2014 Closeout (expected): 2024 |
||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||
Progress report and explanation of variances | The AOPS project is achieving project objectives, notably:
Scope: The project is on track to deliver its 2014 approved scope. Cost: The project is currently within the 2014 approved budget. Under the contract terms Irving Shipbuilding Inc. is required to inform Canada within seven months of the delivery of Ship 1 whether Ship 6 is affordable within the same contractual ceiling price. Schedule: Production activities are underway, with Ship 1 delivery expected in 2019 in accordance with the approved schedule. Work Plan: In the Fiscal Year 2018-19, the AOPS project will achieve the following:
|
Project name | CANADIAN CRYPTOGRAPHIC MODERNIZATION PROGRAM | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Canadian Cryptographic Modernization Program (CCMP) is to modernize the Government of Canada’s aging cryptographic equipment and infrastructure in order to safeguard classified information and maintain Canada’s ability to establish secure communications both nationally and internationally. CCMP is an omnibus project that includes multiple sub-projects for modernizing cryptographic equipment and a cyclical project for modernizing the key management infrastructure. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Defence Information Technology Systems Acquisition, Design and Delivery. The CCMP Omnibus project will deliver affordable information protection to departments and agencies in the Government of Canada (GC) by means of the following sub-projects:
Note: The Secure Mobile Environment sub-project was cancelled. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Industrial benefits | N/A | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Sponsoring department | Communications Security Establishment (CSE) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Participating departments | Departments and agencies of the Government of Canada using cryptographic equipment to protect classified information | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Prime contractor | N/A |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Major subcontractors | Various allied manufacturers of cryptographic equipment |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project phase | Implementation of the first CCMP sub-project: September 2009 Closeout of the CCMP Omnibus project (expected): 2022 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Progress report and explanation of variances | The CCMP Omnibus project is achieving project objectives, notably:
Scope: The CCMP Omnibus project is on track to deliver its 2005 approved scope. Cost: The CCMP Omnibus project is currently within the 2017 approved budget. Schedule: The schedule is dependent on the U.S. Cryptographic Modernization Initiative and the Key Management Infrastructure Program. Canada’s collaboration with the United States of America allows Canada to leverage U.S. research and development and maintain interoperability with its Allies. Completion dates for the sub-projects are regularly reviewed for alignment with the U.S. initiative/program. The CCMP Omnibus Project originated as a 12-year program ending in 2016 but it has been extended to 2022 due to increased complexity and delays in the CSMI Project that relies on input from the United States Key Management Infrastructure (KMI) Program. Work Plan: In the Fiscal Year 2018-19, the CCMP project will achieve the following: CSMI Phase 1A, CSMI Phase 2A and IFF Mode 5 are scheduled for completion in 2018-19. Work will continue on the CSMI Phase 2B, Network Encryption, Secure Radio and Combat Net Radio Enhancement projects that are scheduled for completion between 2020 and 2022. Project that relies on input from the United States Key Management Infrastructure (KMI) Program. |
Project name | CANADIAN SEARCH AND RESCUE HELICOPTER PROJECT | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Canadian Search and Rescue Helicopter (CSH) project is to acquire a fleet of 15 new helicopters that will replace the CH-113 Labrador. This acquisition will provide the capability to support search and rescue services for the population of Canada. |
||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Aerospace Equipment Acquisition. The CSH project has the following project outcomes:
This capability is being delivered to the Royal Canadian Air Force (RCAF). |
||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy was applied to this project. Canada has received its IRBs and the contractor has successfully completed its IRB obligations. |
||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||
Prime contractor | Leonardo MW Ltd. (formerly Augusta Westland International Limited, and before that, European Helicopters Industries Ltd. (EHI)) – Farnborough, UK |
||||||||||||||
Major subcontractors | Westland Helicopters - Yeovil, UK Augusta Spa - Cascina Costa, Italy General Electric Canada Inc. - Mississauga, Ontario, Canada |
||||||||||||||
Project phase | Implementation: September 2001 Closeout (expected): 2017-18 |
||||||||||||||
Major milestones |
|
||||||||||||||
Progress report and explanation of variances | The CSH project has achieved the following project objectives, notably;
Scope: The project will deliver its 1998 approved scope. Cost: The project will deliver under the 1998 approved budget. Schedule: To conform to the design specification, the project is funding a minor retrofit on the fleet which is to be carried out when major maintenance is conducted. Due to this work, the Project Closeout date identified in the 1998 submission was delayed from 2006 to 2017. All retrofit activities have physically been completed. Claims have been received for completions of the last 2 milestones and payments are being processed. Final step will be to formally close the project, which is expected to be completed by end of FY 2017-18. |
Project name | CANADIAN SURFACE COMBATANT PROJECT | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Canadian Surface Combatant (CSC) project is to acquire a new surface combatant capability that will replace the Iroquois Class destroyers and the Halifax Class frigates. This acquisition will provide the capability to monitor and defend Canadian waters and to make contributions to international naval operations. |
||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Maritime Equipment Acquisition. The CSC project has the following project outcomes:
This capability is being delivered to the Royal Canadian Navy. |
||||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy of Canada’s Defence Procurement Strategy (DPS) applies to the selection of an existing warship design and design team to design the Canadian Surface Combatant. As such, a DPS value proposition will be a weighted and rated aspect of the evaluation to select the bidder and design that provides the best overall value for Canadians. Canada will receive equivalent to 100% of the contracted value for both the acquisition and the In-Service Support contracts. |
||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED), and its regional development agencies | ||||||||||||||||
Prime contractor | Irving Shipbuilding Inc., Halifax, Nova Scotia, Canada |
||||||||||||||||
Major subcontractors | Being selected through a competitive Request for Proposals (RFP) |
||||||||||||||||
Project phase | Definition: June 2012 Implementation (expected): Early 2020s |
||||||||||||||||
Major milestones |
|
||||||||||||||||
Progress report and explanation of variances | The CSC project is achieving project objectives, notably:
Scope: Industry was engaged in early 2016 on a potential refinement to the procurement strategy to competitively select an existing warship to modify rather than to develop a new design. Informed by this engagement, Government announced the approval of this refinement on 13 June 2016. The project remains on track to achieve the scope as approved in May 2016. Cost: The upcoming Definition Phase 2 will initially focus on further requirements reconciliation and the ship design phases. Completion of the design phases will inform the costing of the project. This activity will be jointly undertaken by project staff, Irving Shipbuilding Inc. and its sub-contractors. Schedule: Definition Phase 1 activities are underway and Definition Phase 2 is expected to start in fall 2018. It is estimated the project will be in the Definition Phase 2 for three years until the award of the implementation contract – this is an improvement over the previous four years minimum that would be required if the CSC were to be a new design. The evaluation of the Request for Proposals (RFP) was previously targeted for completion in spring 2017 as approved in May 2016 but has now shifted to spring 2018 due to the delay in the release of the RFP and extension of bid period. Work Plan: In the Fiscal Year 2018-19, the CSC project will achieve the following:
|
Project name | CP-140 - AURORA INCREMENTAL MODERNIZATION /STRUCTURAL LIFE EXTENSION PROJECTS | ||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The combined objective of the CP-140 Aurora Incremental Modernization Project (AIMP) and the Aurora Structural Life Extension Project (ASLEP) is to modernize and extend the life of 14 of Canada’s 18 CP-140 Aurora aircraft in order to maintain the fleet’s operational capabilities until the fleet’s planned retirement date of 2030. This work will provide the capability to conduct Intelligence, Surveillance and Reconnaissance (ISR) in order to detect threats to Canadian security as early as possible. AIMP was originally an omnibus project consisting of 23 sub-projects. As of October 2013, the remaining on-going AIMP projects were consolidated under one project. |
||||||||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Aerospace Equipment Acquisition. The AIMP has the following project outcomes:
The ASLEP has the following project outcome:
This capability is being delivered to the Royal Canadian Air Force (RCAF). |
||||||||||||||||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy of Canada’s Defence Procurement Strategy (DPS) applies to this project. Canada will receive ITBs equivalent to 100% of the contracted value of the General Dynamics Mission Systems - Canada acquisitions contract. |
||||||||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||||||||||||||||
Prime contractor | General Dynamics Mission Systems - Canada - Ottawa, Ontario, Canada Lockheed Martin Aeronautics - Marietta, Georgia, USA |
||||||||||||||||||||||||||||
Major subcontractors | IMP Aerospace – Halifax, Nova Scotia, Canada |
||||||||||||||||||||||||||||
Project phase | Implementation: June 2015 Closeout (expected): June 2022 |
||||||||||||||||||||||||||||
Major milestones | AIMP
ASLEP
|
||||||||||||||||||||||||||||
Progress report and explanation of variances | The AIMP and ASLEP projects are achieving project objectives, notably:
Scope: Both projects are on track to deliver their implementation approved scope (AIMP: 2015, ASLEP: 2013), though AIMP Block IV is at risk due to IMP Aerospace capacity to meet modification schedule for all aircraft for planned FOC. The modernized Aurora aircraft has restored Canada’s airborne maritime surveillance capabilities while providing significant enhancements to its overland surveillance capabilities with its world-class integrated mission systems capabilities as demonstrated during domestic and international surveillance missions. Cost: Both projects are on track to deliver within the 2015 approved budgets. An increase in IMP Aerospace rates (both retroactive and forecast), for which negotiation is ongoing with PSPC, has increased cost and reduced flexibility. Schedule: As a result of delays in production, Full Operational Capability dates for AIMP and ASLEP have been delayed from the 2015 approved schedule. Work Plan: In the Fiscal Year 2018-19, the AIMP and ASLEP projects will achieve the following: Delivery of last two Block III Combined Production aircraft in April and December 2018. Completion of the prototype AIMP Block IV modification in September, with Ground and Flight test over the winter 2018-19. Induction of the second Block IV aircraft (‘Proof-of-Fit’) in Summer 2018. |
Project name | FIXED-WING SEARCH AND RESCUE AIRCRAFT REPLACEMENT PROJECT | ||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Fixed Wing Search and Rescue Aircraft Replacement (FWSAR) project is to replace the capability provided by the current fixed-wing SAR fleets of CC-115 Buffalo and CC-130H Hercules aircraft by acquiring new, sensor-equipped aircraft with long-term In-Service Support (ISS), to ensure the Canadian Armed Forces continue to provide an acceptable response to SAR incidents anywhere in the Canadian Area of Responsibility (AoR). |
||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Aerospace Equipment Acquisition. The FWSAR project has the following project outcomes:
This capability is being delivered to the Royal Canadian Air Force. The primary beneficiary is the Canadian population who require Search and Rescue Services. |
||||||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy of Canada’s Defence Procurement Strategy (DPS) applies to this project. Canada will receive ITBs equivalent to 100% of the contracted value for both the acquisitions and the In-Service Support. |
||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||||||
Prime contractor | Airbus Defence and Space S.A. – Madrid, Spain |
||||||||||||||||||
Major subcontractors | PAL Aerospace – St. John’s, Newfoundland, Canada CAE – Montreal, Quebec, Canada Pratt & Whitney Canada – Longueuil, Quebec, Canada L-3 WESCAM – Burlington, Ontario, Canada |
||||||||||||||||||
Project phase | Implementation: December 2016 Project Closeout (expected): 2023 |
||||||||||||||||||
Major milestones |
|
||||||||||||||||||
Progress report and explanation of variances | The FWSAR project is achieving project objectives, notably:
Scope: The project is on track to deliver the 2016 approved scope. Cost: The project is currently within the 2016 approved budget. Schedule: The project is currently on track to deliver the project milestones in accordance with the 2016 approved schedule. Work Plan: In the Fiscal Year 2018-19, the FWSAR project will achieve the following:
|
Project name | FORCE MOBILITY ENHANCEMENT PROJECT | ||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Force Mobility Enhancement (FME) project is to acquire a Leopard 2-based Armoured Engineer Vehicle (AEV) and Armoured Recovery Vehicles (ARV) capability to replace the current Leopard 1-based AEV and ARV fleets. This acquisition will provide the capability to move earth and clear mines, to ensure that troops have a clear, safe path. |
||||||||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Land Equipment Acquisition. The FME project has the following project outcomes:
This capability is being delivered to the Canadian Army (CA). |
||||||||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to this project. Canada will receive IRBs equivalent to 100% of the contracted value in Phase 1 only, with the exception of the government-to-government purchase of the Leopard 2 Main Battle Tanks (MBT) chassis. |
||||||||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies | ||||||||||||||||||||||||||||
Prime contractor | Flensburger Fahrzeugbau (FFG) - Flensburg, Germany Gesellschaft mit beschränkter Haftung (GmbH) - Flensburg, Germany Krauss-Maffei Wegmann GmbH and Co. KG (KMW) - Munich, Germany Urdan Metal and Casting Industries Ltd - Tel Aviv, Israel Kongsberg Defence and Aerospace - Norway |
||||||||||||||||||||||||||||
Major subcontractors | Flensburger Fahrzeugbau (FFG) Canada - Bathurst, New Brunswick, Canada Kongsberg Protech Systems Canada - London, Ontario, Canada |
||||||||||||||||||||||||||||
Project phase | Phase 1 (AEV) Implementation: March 2012 Phase 2 (TMI) Implementation: November 2013 Closeout (expected): March 2019 |
||||||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||||||
Progress report and explanation of variances | The FME project is achieving project objectives. As of 31 December 2017:
Scope: The project is on track to deliver its approved 2012 scope. Cost: The project is currently within budget as approved in 2012. Schedule. The project will incur a delay to the approved 2012 schedule of Closeout in September 2017, with Closeout now anticipated in March 2019. Due to the limited availability of the Canadian Army to conduct training, the IOC dates for Phases 1 and 2 were delayed. The Senior Review Board (SRB) meeting on 5 February 2016 endorsed revisions to the IOC dates. IOC for Phase 1 was completed in December 2017. FOC for FME is delayed until December 2018 due to contractor delivery delays for outstanding spares. Work Plan: In the Fiscal Year 2018-19, the FME project will achieve the following: FOC and Project Closeout will be achieved upon acceptance of the remaining AEVs, completion of the remaining Optimized Front Protection modifications and completion of the remaining Leopard 2 MBTs Tactical Mobility Implement modifications. |
Project name | FUTURE FIGHTER CAPABILITY PROJECT | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Future Fighter Capability Project (FFCP) is to successfully acquire and transition into service 88 advanced fighter aircraft along with the associated equipment, weapons and sustainment capability that leverages Canadian capabilities and contributes to economic growth and jobs. |
||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Aerospace Equipment Acquisition. The FFCP has the following project outcomes:
This capability will be delivered to the Royal Canadian Air Force (RCAF). |
||||||||||||||||
Industrial benefits | Canada’s Industrial and Technological Benefits (ITB) Policy applies to the acquisition and sustainment of the permanent replacement fighter fleet. This will require that industry make investments in Canada equal to the value of the acquisition and In-Service Support contracts/agreements. Canada will seek, through negotiations, contractual commitments from industry that align with the Value Proposition (VP) strategic objectives. Canada will continue to engage with stakeholders on advancing industrial and technological benefits for companies in Canada, and promoting innovation, ensuring best value and supporting Canada’s defence priorities. |
||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||
Prime contractor | To be determined (TBD) |
||||||||||||||||
Major subcontractors | TBD |
||||||||||||||||
Project phase | Definition: November 2017 |
||||||||||||||||
Major milestones |
|
||||||||||||||||
Progress report and explanation of variances | The FFCP project is achieving project objectives, namely:
Scope: DND is collaborating with PSPC and ISEDC to replace the fighter fleet, focusing on options that match Canada’s defence needs. Cost: An acquisition budget of $15B-$19B Canadian was announced as part of “Strong, Secure, Engaged” Defence Policy. The project’s implementation budget will be informed by ongoing project definition work including engagement with governments and industry, and is contingent on approval as part of the Project Approval process for Implementation. Schedule: While the schedule remains aggressive, the project is currently on schedule to issue solicitation documents in 2019. Work Plan: In the Fiscal Year 2018-19, the FFCP project will achieve the following:
The Project plans to release draft solicitation documents to potential suppliers for review in Fall 2018. |
Project name | HALIFAX CLASS MODERNIZATION/FRIGATE LIFE EXTENSION | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Halifax Class Modernization/Frigate Life Extension (HCM/FELEX) project is to modernize the combat systems and carry out a mid-life upgrade on the Royal Canadian Navy's fleet of 12 Canadian-built Halifax Class patrol frigates. This work will ensure that the Halifax Class patrol frigates continue to operate effectively as the backbone of the Royal Canadian Navy fleet. |
||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Maritime Equipment Acquisition The HCM/FELEX project has the following project outcomes:
This capability is being delivered to the Royal Canadian Navy. |
||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to this project. Canada will receive IRB’s equivalent to 100% of the contracted value for both the acquisitions and the In-Service Support. |
||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||||||||
Prime contractors |
|
||||||||||||||||||||||
Major subcontractors | N/A |
||||||||||||||||||||||
Project phase | Implementation: October 2010 Closeout (expected): January 2019 |
||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||
Progress report and explanation of variances | The HCM/FELEX project is achieving project objectives, notably:
Scope: The project is on track to deliver its September 2008 approved scope. Cost: The project is currently within budget, based on September 2008 approval. Schedule: The project is on track to deliver the project milestones in accordance with its September 2008 approved schedule. Implementation activities are ongoing and Full Operational Capability is expected in January 2018. Work Plan: In the Fiscal Year 2018-19, the HCM/FELEX project will achieve the following:
|
Project name | HALIFAX CLASS POINT DEFENCE MISSILE SYSTEM UPGRADE | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Halifax Class Point Defence Missile System Upgrade (PDMSU) project is to develop and acquire an evolution to the current Evolved SeaSparrow Missile (ESSM) Point Defence Missile System, fitted in the Halifax class ships. This work will sustain the Royal Canadian Navy’s Halifax class ships’ ability to defend against current and future threats originating from surface, sub-surface, air and land-based platforms. |
||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Maritime Equipment Acquisition. This project is linked to the Force Capability Guidance that allows the CAF to support the Government's foreign policy and national security objectives through this joint-nation project. The PDMSU project has the following project outcomes:
This capability is being delivered to the Royal Canadian Navy. |
||||||||||||||
Industrial benefits | The development work, performed under the ESSM Block 2 Engineering and Manufacturing Development Memorandum of Understanding (MOU), consists of Government work and industrial work. While the Government work will be performed primarily by the U.S. Government, the industrial work is shared among the Contributing Participants in accordance with their cost share percentages. Work share for Implementation Phase is governed by the MOU for the Production of the ESSM Block 2, with work share based on the country’s percentage of total missile acquired. As a result, the work share is 100% of the value associated with the production of the contracted missiles. Canada’s Integrated Regional Benefits (IRB) Policy does not apply to this project. |
||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies. |
||||||||||||||
Prime contractor | NATO SeaSparrow Surface Missile System Project |
||||||||||||||
Major subcontractors | Raytheon Missile Systems Company - Louisville, KY, USA |
||||||||||||||
Project phase | Implementation: March 2017 Closeout (expected): March 2028 |
||||||||||||||
Major milestones |
|
||||||||||||||
Progress report and explanation of variances | The PDMSU project is achieving project objectives, notably:
Scope: The project is on track to deliver its 2017 approved scope. Cost: The project is currently within its 2017 approved budget. Schedule: The PDMSU project is on track to deliver the project milestones in accordance with its schedule. Work Plan: In the Fiscal Year 2018-19, the PDMSU project will initiate the development of Combat Systems software upgrade to support the ESSM Block 2 capabilities, perform the in-field testing and evaluation of Block 2 transceiver, and initiate the first phase of Packaging, Handling, Storage and Transportation (PHS&T) testing. |
Project name | INTERIM FIGHTER CAPABILITY PROJECT | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Interim Fighter Capability Project (IFCP) is to pursue the acquisition of Australian F/A-18 aircraft, associated spares and equipment to supplement the current CF-18 fleet to address the fighter capability gap. |
||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Aerospace Equipment Acquisition. The IFCP has the following project outcomes:
This capability will be delivered to the Royal Canadian Air Force (RCAF). |
||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy of Canada’s Defence Procurement Strategy (DPS) does not apply to the purchase of military equipment from a foreign government where a prime contractor is not involved; however, there will be opportunities for Canadian Industry supporting the current fleet. |
||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies. |
||||||||||||||
Prime contractor | Acquired from the Australian Government through Government to Government arrangement (Instrument of Sale). |
||||||||||||||
Major subcontractors | TBD |
||||||||||||||
Project phase | Definition: February 2017 Implementation (expected): Fall 2018 |
||||||||||||||
Major milestones |
|
||||||||||||||
Progress report and explanation of variances | The IFCP project is achieving project objectives, namely:
Cost: The project’s implementation budget is contingent on approval as part of the Project Approval (PA) process for Implementation. Schedule: The project is currently on its December 2017 approved schedule. Work Plan: In the Fiscal Year 2018-19, the IFCP project will achieve the following:
|
Project name | LAND FORCES INTELLIGENCE, SURVEILLANCE, TARGET ACQUISITION AND RECONNAISSANCE SYSTEM | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Land Forces Intelligence, Surveillance, Target Acquisition and Reconnaissance (LF ISTAR) System is to deliver and evolve an integrated, interoperable ISTAR capability through the acquisition of or enhancement to capabilities in the areas of communications, command and control and sensors. This work will improve the ability of commanders to visualize the operational area, manage sensors and information collection resources, and to plan and implement actions to successfully complete operational missions. LF ISTAR is an omnibus project with 10 sub-projects. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Land Equipment Acquisition. The LF ISTAR Omnibus project will deliver an integrated intelligence capability by means of the 10 sub-projects:
This capability is being delivered to the Canadian Army. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy of Canada’s Defence Procurement Strategy (DPS) applies to this project. Canada will receive ITBs equivalent to 100% of the contracted value for both the acquisitions and the In-Service Support. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Prime contractors |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Major subcontractor | ELTA System, Israel – Partnered with Rheinmetal Canada for Medium Range Radar |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Project phase | Implementation: November 2005 Closeout (expected): March 2020 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Progress report and explanation of variances | The LF ISTAR project is achieving project objectives, namely:
Scope: The project is on track to deliver its approved 2003 scope. Cost: The project is currently within budget. Some funds will need to be reallocated amongst sub-projects, but the overall cost will remain within the LF ISTAR Omnibus approved budget from 2003. Meetings are in progress to complete Revised Expenditure Approval. Schedule: The project has experienced some delays from its approved 2003 schedule. The project is progressing well and has only the following remaining capabilities to deliver before project Closeout, currently estimated for March 2020:
Work Plan: In the Fiscal Year 2018-19, the LF ISTAR project will achieve the following: Implementation activities will focus on remaining sub-projects to continue delivery of required equipment and provide In-Service Support to fielded equipment. The Contract for the 2nd FUAV Blackjack system is expected to be awarded once the procurement strategy has been approved. |
Project name | JOINT SUPPORT SHIP | ||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Joint Support Ship (JSS) project is to acquire new support ships to replace the Auxiliary Oiler Replenishment (AOR) fleet. This acquisition will provide the capability to provide at-sea support to deployed naval task groups, and to provide limited sealift and support to operations ashore. |
||||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Maritime Equipment Acquisition. This capability is being delivered to the Royal Canadian Navy. |
||||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to this project. Canada will receive IRBs equivalent to 100% of the contracted value for both the acquisitions and the In-Service Support. For the In-Service Support contract, a Defence Procurement Strategy (DPS) value proposition will be a weighted and rated aspect of the evaluation to select the most qualified bidder. |
||||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||||||||||
Prime contractor | Acquisition: Vancouver Shipyards Co. – North Vancouver, British Columbia, Canada In-Service Support: A single long-term In-Service Support Contract (ISSC) to support the Arctic and Offshore Patrol Ship (AOPS) and Joint Support Ship (JSS) vessels is in place. |
||||||||||||||||||||||||
Major subcontractors | Alion Science and Technology (Canada) Corporation – Ottawa, Ontario, Canada Thales Canada Inc. – Ottawa, Ontario, Canada Computer Sciences Canada Inc. – Ottawa, Ontario, Canada Germanischer Lloyd Canada (DNV-GL) – Montreal, Quebec, Canada ThyssenKrupp Marine Systems Canada Inc. – Ottawa, Ontario, Canada VARD Electro – Tennfjord, Norway VARD Electro Canada Inc. – Vancouver, British Columbia, Canada Trident Maritime Systems – Crozet, Virginia, USA L-3 Communications MAPPS Inc. – St. Laurent, Quebec, Canada |
||||||||||||||||||||||||
Project phase | Definition: June 2010 Implementation (expected): Fall 2019 |
||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||
Progress report and explanation of variances | The JSS project is achieving project objectives, notably:
Scope: The project is on track to deliver its August 2016 approved scope. Cost: The Project Definition activities remain within the August 2016 approval. The Definition work will define the project’s implementation budget. Schedule: Challenges in achieving multiple approvals and contract/task awards have delayed planned construction and delivery dates for these ships as they relate to the August 2016 approval. Further delays may occur depending on the progress of the other NSS projects preceding JSS at the same shipyard. Work Plan: In the Fiscal Year 2018-19, the JSS project will achieve the following: The JSS design will progress towards achieving an acceptable production design to enable the start of construction. With approved increased authorities being pursued to enable the procurement of long lead items as early as Spring 2018, it is expected that procurement of long lead items will commence by Summer 2018, to ensure materiel availability to start construction. Current discussions underway between Canada and the shipyard could also result in schedule compression opportunities being exploited, including the potential to commence the early construction of some JSS components. |
Project name | LIGHT ARMOURED VEHICLE III UPGRADE PROJECT | ||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Light Armoured Vehicle (LAV) III upgrade project is to upgrade a significant portion of the LAV III fleet. The LAV III upgrade project will capitalize on existing and evolving technology to provide a highly protected, yet highly mobile Light Armoured Vehicle capability which will protect the soldiers and equipment of the CAF in current and future operations. |
||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Land Equipment Acquisition. The LAV III upgrade project has the following project outcomes:
This capability is being delivered to the Canadian Army. |
||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to this project. Canada will receive IRBs equivalent to 100% of the contracted value from General Dynamics Land Systems-Canada for both the acquisitions and In-Service Support. |
||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||||
Prime contractor | General Dynamics Land Systems-Canada - London, Ontario, Canada |
||||||||||||||||||
Major subcontractors | N/A |
||||||||||||||||||
Project phase | Implementation: October 2011 Closeout (expected): 2021 |
||||||||||||||||||
Major milestones |
|
||||||||||||||||||
Progress report and explanation of variances | The LAV III upgrade project is achieving project objectives, notably:
Scope: In November 2016 the project received the additional authority to deliver the full upgrade to the 141 LAV III Operational Requirements Integration Task (LORIT) vehicles which were originally only to receive a partial upgrade under the scope of the project approved in October 2011. Cost: The project is within the budget established in November 2016 as part of the amended scope approval. Schedule: The project remains on schedule as established in November 2016 as part of the amended scope approval. Work Plan: In the Fiscal Year 2018-19, the LAV III Upgrade project will achieve the following:
|
Project name | LIGHTWEIGHT TOWED HOWITZER | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Lightweight Towed Howitzer (LWTH) project is to acquire 25 M777 155mm lightweight towed howitzers, to augment the 12 M777 howitzers already in service. The project will also institutionalize capability enhancements in terms of the lethality, range, precision, mobility and digitization, which will support the missions and tasks likely to be assigned to the CAF. |
||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Land Equipment Acquisition. The LWTH project has the following project outcomes:
This capability is being delivered to the Canadian Army. |
||||||||||||||||||||||
Industrial benefits | Canada’s Industrial Regional Benefits (IRB) Policy applies to this project. Canada will receive IRBs equivalent to 100% of the value for the BAE Systems M777 Lightweight Towed Howitzer Foreign Military Sales Acquisition case. Canada will receive IRBs equivalent to 100% of the value for SELEX GMS acquisition contract. |
||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||
Participating departments |
Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||||||||
Prime contractor | BAE Systems - Barrow-in-Furness, Cumbria, UK |
||||||||||||||||||||||
Major subcontractors | Leonardo - Edinburgh, UK |
||||||||||||||||||||||
Project phase | Implementation: October 2012 Effective Project Closeout (expected): March 2018 |
||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||
Progress report and explanation of variances | The LWTH project is achieving project objectives, notably:
Scope: The project is on track to deliver its 2008 approved scope. Cost: The project is currently within the 2008 approved budget. Schedule: The project has experienced a delay of five years against the 2010 approved schedule, primarily as a result of technical challenges associated with the Course Correcting Fuse (CCF) Precision Guidance Kit (PGK) ammunition. 52% of CCF/PGK were delivered by November 2017 and final delivery is now scheduled in July 2018. PGK is the last remaining linkage to FOC. Work Plan: In the Fiscal Year 2018-19, the LWTH project will achieve the following: LWTH will achieve EPC in March 2018 and Project Closeout will be achieved upon acceptance of the final equipment deliverables and completion of all remaining minor activities such as FMS Cases for batteries, ammunition and MSVS Gun tractors. |
Project name | MARITIME HELICOPTER PROJECT | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Maritime Helicopter Project (MHP) is to acquire a new maritime helicopter capability to replace the CH-124 Sea King. This acquisition will address the operational deficiencies of the current CH-124, eliminate the supportability difficulties of the older helicopter, and provide a sufficient fleet size of multi-purpose shipborne Maritime Helicopters for operations well into the 21st century. |
||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Aerospace Equipment Acquisition. The MHP has the following project outcomes:
This capability is being delivered to the Royal Canadian Air Force and will support the Royal Canadian Navy. |
||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to this project. Canada will receive IRBs equivalent to 107% of the contracted value for the acquisitions and 80% of the contracted value for the In-Service Support portion from Sikorsky Aircraft. |
||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||||||||
Prime contractor | Sikorsky International Operations Incorporated - Stratford, Connecticut, USA |
||||||||||||||||||||||
Major subcontractors | General Dynamics Mission Systems - Canada - Ottawa, Ontario, Canada L-3 MAS - Mirabel, Quebec, Canada |
||||||||||||||||||||||
Project phase | Implementation: November 2004 Closeout (expected): 2022 |
||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||
Progress report and explanation of variances | The MHP is achieving project objectives, notably:
Scope: On 18 June 2014, following a revised Project Approval (Implementation), the Government of Canada and Sikorsky International Operations Incorporated signed a contract amendment. This amendment extended the In-Service Support Agreement out to 2038 and re-baselined the project schedule. Cost: The MHP is currently within the 2004 approved budget. Schedule: The MHP is on track to deliver the project milestones in accordance with its approved schedule, as re-baselined in the revised Project Approval (Implementation) in June 2014. Implementation activities are ongoing. Work Plan: In the Fiscal Year 2018-19, the MHP project will achieve the following:
Return of all Block 1 aircraft to Sikorsky for retrofit into the Block 2 configuration. |
Project name | MEDIUM SUPPORT VEHICLE SYSTEM PROJECT | ||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Medium Support Vehicle System (MSVS) project is to acquire a new medium-weight truck capability that will replace the Medium Logistic Vehicle Wheeled (MLVW) fleet. The acquisition will provide the capability to transport troops, cargo, and equipment and to perform Unit level and combat services support functions. |
||||||||||||||||||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Land Equipment Acquisition. The MSVS project has the following project outcomes, divided in phases:
This capability is being delivered to the Canadian Army. |
||||||||||||||||||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) applies to Phase 1, Phase 2 and Phase 4 of this project. Canada will receive IRBs equivalent to 100% of the contracted value for both the acquisitions and In-Service Support. The IRB Policy does not apply to Phase 3, the "Shelter Kitting" contract. |
||||||||||||||||||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||||||||||||||||||||||||
Prime contractor |
|
||||||||||||||||||||||||||||||||||||||
Major subcontractors | N/A |
||||||||||||||||||||||||||||||||||||||
Project phase | Implementation: May 2015 Closeout (expected): 2020 |
||||||||||||||||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||||||||||||||||
Progress report and explanation of variances | The MSVS project is achieving project objectives, notably:
Scope: The project is on track to deliver its 2015 approved scope for Phase 4 and Phase 5. Cost: The project is currently within the 2015 approved budget. Schedule: Mack Defense LLC requested the postponement of the SMP Truck deliveries to minimize concurrent requirement verification and production efforts. Therefore, the planned delivery of the SMP Trucks (Phase 4) has been delayed by approximately three months from the 2015 schedule. Work Plan: In the Fiscal Year 2018-19, the MSVS project will achieve the following: The closure of Phase 2 and 3 of the MSVS Project which are related to the delivery of the Baseline Shelters and their kitting. With the delivery of the SMP Trucks, it is planned to reach an initial operating capability including logistics support for the vehicles. |
Project name | MEDIUM-TO-HEAVY LIFT HELICOPTERS | ||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Medium-to-Heavy Lift Helicopters (MHLH) project is to establish a new transport helicopter capability based in Petawawa, Ontario to support land-based domestic and international operations. |
||||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Aerospace Equipment Acquisition. The MHLH project has the following project outcomes:
This capability is being delivered to the Royal Canadian Air Force and will support the Canadian Army. |
||||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to this project. Canada will receive IRBs equivalent to 100% of the contracted value for both the acquisitions and the integrated In-Service Support. |
||||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||||||||||
Prime contractor |
|
||||||||||||||||||||||||
Major subcontractors | N/A |
||||||||||||||||||||||||
Project phase | Implementation: June 2009 Closeout (expected): 2020 |
||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||
Progress report and explanation of variances | The MHLH project is achieving project objectives, notably:
Scope: The MHLH project is on track to deliver its 2009 approved scope. Cost: The MHLH project is currently within the 2009 approved budget. Schedule: The Full Operational Capability and Project Closeout were delayed relative to the 2009 approved schedule. The new dates for Full Operational Capability and Closeout are summer 2018 and 2020 respectively. Delays to the original Full Operational Capability and Closeout dates were due to pilot production and Directional Infrared Countermeasures system integration and delivery. Work Plan: In the Fiscal Year 2018-19, the MHLH project will achieve Full Operational Capability. |
Project name | MERCURY GLOBAL | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Mercury Global (MG) project is to acquire assured access capabilities to around-the-world wideband satellite communications (SATCOM), which will provide the Canadian Armed Forces (CAF) with secure, reliable and high availability wideband communications. |
||||||||||||||
Project outcomes | This project is attributed to Departmental Results Framework Core Responsibility - Procurement of Capabilities / Defence Information Technology Systems Acquisition, Design and Delivery. The MG project has the following project outcomes:
This capability is being delivered to the Canadian Armed Forces. |
||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to the first two phases of this project. In Phase 1, Canada will receive IRBs equivalent to 100% of the contracted value on a separate agreement between Boeing and Public Services and Procurement Canada (PSPC) for the ninth WGS space vehicle (satellite). In Phase 2, Canada will receive IRBs equivalent to 100% of the contracted value for both the acquisition and the In-Service Support. In Phase 3, Canada will receive Industrial and Technological Benefits (ITBs) equivalent to 100% of the contracted value for both the capital acquisition and the In-Service Support as part of the Defence Procurement Strategy (DPS). |
||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||
Prime contractor | Space segment – United States Department of Defense (DoD) via a Memorandum of Understanding Anchor Segment – General Dynamics Mission Systems - Canada; Ottawa, Ontario, Canada Strategic Deployment Terminals - To be determined (TBD) Early Access Terminals – Telesat Canada - Ottawa, Ontario, Canada |
||||||||||||||
Major subcontractors | Satellite Manufacturer - Boeing, St. Louis, Missouri, USA |
||||||||||||||
Project phase | Implementation: October 2014 Closeout (expected): September 2019 |
||||||||||||||
Major milestones |
|
||||||||||||||
Progress report and explanation of variances | The MG project is achieving project objectives, notably:
Scope: The project is on track to deliver the 2014 and 2018 Treasury Board (TB) approved scope. In addition, WGS satellites eight (8) and nine (9) have completed the Wideband Digital Channelizer upgrade, which will almost double their current bandwidth. This satellite modification was undertaken by the U.S. Department of Defense; International Partners will not share the cost, in part or in total, for this upgrade. These satellites have been launched and are currently operational. Cost: The project is currently within the 2014 and 2018 TB approved budgets. Schedule: The project has experienced a delay against the 2014 approved schedule. The schedule has been re-baselined in the approved 2018 TB submission. Work Plan: In the Fiscal Year 2018-19, the MG project will achieve the following: Delivery of the 67 SDTs are expected in FY 2018-19. The SDT contract also includes Initial Cadre Training for operators and maintainers. Transition to In-Service Support (ISS) will take place as the terminals are delivered, the contractor is mandated for 15 years of ISS for the SDTs under the same contract. For the MG Anchor Segment, WGS Type Certification is planned to be achieved by November 2018 allowing all Anchor Stations across the different sites to be certified. The Central, Eastern and Western sites are planned to be accepted by January 2019. Developing the Network Management System which will control all Anchor Stations is ongoing. |
Project name | PROTECTED MILITARY SATELLITE COMMUNICATIONS | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Protected Military Satellite Communications (PMSC) project is to acquire guaranteed access to an Advanced Extremely High Frequency (AEHF) Military Satellite Communications System, which will provide the capability for near-worldwide (650N-650S) assured, secure, jam-resistant communications for the command and control of deployed Canadian commanders and forces, as well as interoperability with some of our principal allies, the United States, the United Kingdom, and the Netherlands. |
||||||||||||||
Project outcomes | This project is attributed to Departmental Results Framework Core Responsibility - Procurement of Capabilities / Defence Information Technology Systems Acquisition, Design and Delivery. The PMSC project has the following project outcomes:
This capability is being delivered to the Canadian Army, Navy, and Air Force. |
||||||||||||||
Industrial benefits | The US Department of Defence (DoD) committed to a work share with Canadian Industry under the completed Phase 1 portion. Canada’s Industrial and Benefits (IRB) Policy was applied to Phase 2 of this project and an IRB agreement was negotiated with Raytheon. Canada will receive IRBs equivalent to 100% of the contracted value. |
||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||
Prime contractor | United States Department of Defense (DoD) via Foreign Military Sales (FMS) |
||||||||||||||
Major subcontractors | Raytheon - Waltham, Massachusetts, USA |
||||||||||||||
Project phase | Implementation: November 2003 Effective Project Closeout (expected): September 2026 |
||||||||||||||
Major milestones |
|
||||||||||||||
Progress report and explanation of variances | The PMSC project is achieving project objectives, notably:
Scope: The project is on track to deliver the 2003 approved scope. Cost: The project is currently within the 2003 approved budget. Risk mitigation strategies have been identified to minimize future costs due to installations that exceeded budgeted estimates. These strategies have included, awarding installation activities to the supplier with the lowest overall cost structure, and the feasibility of proceeding with firm-fixed price contracts has been explored and implemented. Schedule: Installation of the PMSC system on the Canadian Patrol Frigates (CPF) is progressing well with 11 of the 12 ships completed. The remaining ship is scheduled for completion in March 2018. Due to slippages in the US DoD overall satellite launch schedule and Victoria Class Submarine (VCS) installations, the PMSC System Full Operational Capability, has moved to Juen 2026 from the original (2003 approved) expected date of November 2017. Work Plan: Project scope is largely delivered and transitioned to the responsible in-service organization. In the Fiscal Year 2018-19, the PMSC project will achieve the following: Delivery of an FMS sustainment case contract in support of the Naval Multiband Terminal) control groups and antennas, support DGMEPM/DMEPM (Submarines) installation of PMSC on HMCS CORNERBROOK during her current Extended Docking Work Period (EDWP), and transition leadership of the International Partner AEHF Working Group (IPAWG) and Operations and Sustainment MOU to the in-service technical authority. |
Project name | REMOTELY PILOTED AIRCRAFT SYSTEM (formerly JOINT UNMANNED SURVEILLANCE AND TARGET ACQUISITION SYSTEM) | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Remotely Piloted Aircraft System project (RPAS) is to provide a capability to conduct Joint Intelligence, Surveillance and Reconnaissance (ISR) and precision strikes operations in a networked, system-of-systems environment that will enable the flow of information among multiple, interconnected platforms and operational headquarters. |
||||||||||||||
Project outcomes | This project is attributed to the Strong, Secure, Engaged defence policy document. The RPAS project has the following project outcome:
This capability will be delivered to the Royal Canadian Air Force, and will support the Canadian Army, the Royal Canadian Navy and Special Operations Forces. |
||||||||||||||
Industrial benefits | The Defence Procurement Strategy (DPS) applies to this project and DND is collaborating with Innovation, Science and Economic Development Canada (ISED) to define its implementation. |
||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||
Prime contractor | To be determined (TBD) |
||||||||||||||
Major subcontractors | TBD |
||||||||||||||
Project phase | Option Analysis: 24 September 2015 |
||||||||||||||
Major milestones |
|
||||||||||||||
Progress report and explanation of variances | RPAS is in the Options Analysis phase. The Industry responses to a Request for Information (RFI) in 2016 were used to develop the Business Case Analysis (BCA) options. The BCA was endorsed by Defence Capability Board on 27 October 2017. At the Senior Review Board of 20 September 2017, project Joint Unmanned Surveillance and Target Acquisition System was renamed to the Remotely Piloted Aircraft System. In the Fiscal Year 2018-19, the RPAS project will continue to develop options. |
Project name | SUBMARINE CAPABILITY LIFE EXTENSION | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Submarine Capability Life Extension (SCLE) project is to acquire a submarine capability to replace the Oberon class submarine fleet. The acquisition supports Canada's ability to conduct surveillance and control of its territory, airspace and maritime areas of jurisdiction, as well as Canada's ability to participate in bilateral and multilateral operations. |
||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Maritime Equipment Acquisition. The SCLE project has the following project outcomes:
This capability is being delivered to the Royal Canadian Navy (RCN). |
||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy was applied to this project. Canada received IRBs equivalent to 100% of the contracted value for both the acquisitions and the In-Service Support. |
||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||
Prime contractor | The Government of the United Kingdom, (UK) of Great Britain and Northern Ireland, Ministry of Defence, UK |
||||||||||||||||
Major subcontractors | British Aerospace Engineering (BAE) Marine Systems (formerly Vickers Shipbuilding and Engineering Limited (VSEL)/Marconi Marine), Cumbria, UK |
||||||||||||||||
Project phase | Implementation: June 1998 Closeout (expected): 2019 |
||||||||||||||||
Major milestones |
|
||||||||||||||||
Progress report and explanation of variances | The SCLE project is achieving project objectives, notably:
Scope: The project is on track to deliver the 2003 approved scope. Cost: All performance objectives of this project will be met within the allocated budget approved in 2003. Schedule: Due to the requirement to complete the installation and testing of two Engineering Change (EC) projects in HMCS Corner Brook, Project Closeout is dependent upon finishing the ongoing Extended Docking Work Period (EDWP) in early 2020, 1 year later than previously planned. Work Plan: In the Fiscal Year 2018-19, the SCLE project will progress with the remaining EC projects (Mark 48 torpedo and Self Noise Monitoring System), as well as finalize material purchases in preparation for Project Closeout. |
Project name | TACTICAL ARMOURED PATROL VEHICLE | ||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Tactical Armoured Patrol Vehicle (TAPV) project is to deliver a wheeled combat vehicle, which has a high degree of tactical mobility and crew survivability, to the Canadian Army that will fulfill a variety of roles on the battlefield, including but not limited to reconnaissance and surveillance, security, command and control, and cargo and armoured transport of personnel and equipment. |
||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Land Equipment Acquisition. The TAPV project has the following project outcomes:
This capability is being delivered to the Canadian Army. |
||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to the acquisition and support contracts, with requirements for IRB equal to 100% of the contract value. |
||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||||
Prime contractor | Textron Systems Canada Incorporated - Ottawa, Ontario, Canada |
||||||||||||||||||
Major subcontractors | Textron Marine and Land Systems - Louisiana, USA Kongsberg Protech Systems Canada - London, Ontario, Canada Rheinmetall Canada - Ottawa, Ontario, Canada Engineering Office Deisenroth Canada - Ottawa, Ontario, Canada |
||||||||||||||||||
Project phase | Implementation: June 2012 Closeout (expected): 2020 |
||||||||||||||||||
Major milestones |
|
||||||||||||||||||
Progress report and explanation of variances | The TAPV project is achieving project objectives, notably:
Scope: The project is on track to deliver the 2012 approved scope. Cost: The project is within its 2012 approved expenditure authority. Schedule: In August 2014, a first round of testing identified design challenges associated with reliability. The project returned to the contract design phase in order to allow the complex, inter-related designs for the vehicle’s structure, suspension and steering to be improved. A second round of reliability testing was successful, and other qualification activities were completed by June 2016. Work Plan: In the Fiscal Year 2018-19, the TAPV project will achieve the following:
|
Project name | TANK REPLACEMENT PROJECT | ||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Tank Replacement Project (TRP) is to acquire a Leopard 2 Main Battle Tank (MBT) capability to replace the Leopard 1 MBT fleet. The acquisition will provide the CAF with a modern, heavily protected, mobile, direct fire support capability. The TRP is divided into two phases. |
||||||||||||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Land Equipment Acquisition. The TRP has the following project outcomes, in two phases: Phase 1
Phase 2
This capability is being delivered to the Canadian Army (CA). |
||||||||||||||||||||||||||||
Industrial benefits | Canada’s Industrial and Regional Benefits (IRB) Policy applies to solely Phase Two of this project. Canada will receive IRBs equivalent to 100% of the contracted value for both the acquisitions and In-Service Support. |
||||||||||||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||||||||||||||
Prime contractors |
|
||||||||||||||||||||||||||||
Major subcontractors | N/A |
||||||||||||||||||||||||||||
Project phase | Implementation: June 2009 Closeout (expected): December 2017 |
||||||||||||||||||||||||||||
Major milestones |
|
||||||||||||||||||||||||||||
Progress report and explanation of variances | The TRP is achieving project objectives, notably:
Scope: The project is on track to deliver the 2009 approved scope. Cost: Costs continue to be tightly managed within the cost ceiling in accordance with the core deliverables and prioritized activities. The project is within the 2009 approved budget. Schedule: The project is behind the schedule established in the 2009 Project Approval (Implementation). The Senior Review Board (SRB) at its meeting in February 2017 approved the use of Effective Project Closeout in December 2017 with formal Project Closeout in December 2018 in order to receive final delivery for Integrated Logistics Support requirements. Work Plan: In the Fiscal Year 2018-19, the TRP project will achieve the following: project Closeout will be achieved upon completion of the last A6M DVE upgrade, other minor System Engineering changes and delivery of Integrated Logistics Support spares and technical publications. |
Project name | UNDERWATER WARFARE SUITE UPGRADE | ||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Description | The objective of the Underwater Warfare Suite Upgrade (UWSU) project is to upgrade the underwater warfare sensor suite currently installed in the Halifax Class frigates. The work will address deficiencies, improve ship underwater sensor performance in the challenging littoral environment and provide a system design to enable continual improvement in a cost-effective manner. |
||||||||||||||||||
Project outcomes | This project is attributed to the Departmental Results Framework Core Responsibility - Procurement of Capabilities / Maritime Equipment Acquisition. The UWSU project has the following project outcomes:
This capability will be delivered to the Royal Canadian Navy. |
||||||||||||||||||
Industrial benefits | The Industrial and Technological Benefits (ITB) Policy of Canada’s Defence Procurement Strategy (DPS) applies to this project. Canada will receive ITBs equivalent of 100% of the contracted value for both the acquisition and In-Service Support. |
||||||||||||||||||
Sponsoring department | Department of National Defence (DND) | ||||||||||||||||||
Contracting authority | Public Services and Procurement Canada (PSPC) | ||||||||||||||||||
Participating departments | Innovation, Science and Economic Development Canada (ISED) and its regional agencies |
||||||||||||||||||
Prime contractor | To be determined (TBD) |
||||||||||||||||||
Major subcontractors | N/A |
||||||||||||||||||
Prime contractor (In-Service Support) | TBD | ||||||||||||||||||
Project phase | Definition: May 2015 Implementation (expected) April 2018 |
||||||||||||||||||
Major milestones |
|
||||||||||||||||||
Progress report and explanation of variances | The UWSU project is achieving project objectives, notably:
Scope: The project is on track to deliver the May 2015 approved scope. The final scope options for ships six through twelve, if all equipment upgrades are not permanently fitted on all ships, will be indicated as part of the implementation approval submission. Cost: The project is currently within the definition phase authorized budget, based on May 2015 approval. Substantive cost for the implementation phase will be indicated within the implementation approval submission. Schedule: Milestone dates reflect substantive schedule estimates incorporating the impact of delays for definition and implementation approvals, plus also for installations within the Halifax-Class docking work period program. Milestone dates would be extended if more than a minimum of six full-up ship set installations are required. Work Plan: In the Fiscal Year 2018-19, the UWSU project will achieve the following:
|
Page details
- Date modified: